East Buffalo Township
Neutral Data Center Policies
East Buffalo Township requires removal funding, technical and utility studies, and noise limits and testing, adding costs while still allowing data-center approval. Another enacted change defines data-center-related uses without itself adding approval or operating rules.
Incentives
Financial Incentive2
Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.
Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.
current law · East Buffalo TownshipThe Supervisors unanimously adopted the ordinance amending Chapter 27 at their October 26, 2026 meeting, according to the Daily Item, which described a two-tier process (a special exception for projects of more than three lots and a conditional use for smaller ones) that does not appear in the advertised text, and the signed ordinance and its number have not been posted.East Buffalo Township, Union County — data-center ordinance (Adopted October 26, 2026, Number Not Posted)
What this means
The measure imposes money set aside for eventual removal, technical studies and utility checks and noise limits and sound testing. Data centers can still be approved, but these obligations meaningfully increase construction, compliance or review costs.
Restrictions & requirementsHide restrictions & requirements26
60 ft maximum inclusive of roof-mounted equipment, § 533(3)(a)-(b); not tied to the district limit
Water feasibility study for nonpublic water only; no riparian buffer or environmental assessment, § 533(7)(b)
67 dBA weekday day and 57 dBA night and weekend at the property line, ANSI S1.4 meters, § 533(6)(a); above 50 and 45 dBA
Preliminary study in land development, interim study at building permit, and as-built study six months after occupancy, § 533(6)(a)(1)-(3)
Vibration study showing no vibration perceptible beyond the property line; perception-only standard, § 533(6)(c)
Public water certification, or a water feasibility study for nonpublic sources; no pump test, § 533(7)(a)-(b)
Water use for cooling disclosed in the feasibility study for nonpublic water; no cooling method rule, § 533(7)(b)(3)
Projected water demands disclosed for nonpublic water and SRBC approval above thresholds; no reporting or drought plan, § 533(7)(b)-(c)
Disposal of cooling and industrial wastewater must be provided and approved by the Sewage Enforcement Officer or DEP, § 533(7)(d)
Decommissioning plan covers removal of electronic waste and disposal of batteries and refrigerants; no ongoing plan or contract, § 533(12)(a)-(b)
Electric provider must certify available capacity and service; no service agreement before zoning permit, § 533(8)(a)
Substations counted as data center accessory uses and nearby equipment enclosed or screened; no line burial, § 201 and § 533(5)(a)
Battery storage must meet NFPA 855 with battery-specific fire suppression; no setbacks or hazard analysis, § 533(9)(b)
Known impacts on electric rates or availability must be noted; grid upgrade costs not assigned, § 533(8)(a)
25-ft native landscape buffer next to residential districts, sensitive receptors, and roads, § 533(4)
Equipment within 100 ft of roads, residential districts, or sensitive receptors enclosed or screened, and a sound wall may be required; not all equipment, § 533(5)(a) and (6)(d)
Emergency Response Plan reviewed and accepted by the fire department and EMS; no annual update or posted contacts, § 533(9)(a)
Plan must ensure first responders receive training specific to the installed system, § 533(9)(a)(4)
Disposal of batteries, fuel, and refrigerants addressed in the decommissioning plan; no storage setbacks or containment, § 533(12)(b)(2)
Annual fire safety inspections by a qualified professional; no report to a municipal official, § 533(9)(a)(5)
Access roads evaluated in the emergency plan; no road class or secondary access requirement, § 533(9)(a)(3)
Agreement with 110% security at permit, notice of cessation, and removal of all buildings and equipment within 6 months after 12 months idle; agreement not required to be recorded, § 533(12)(c)-(e)
Cost estimate updated every 5 years with security adjusted to 110%; no update after the first year, § 533(12)(c)(2)
One as-built sound study six months after occupancy, later studies at Township discretion, § 533(6)(a)(3)
A sound limit violation found by the as-built study is a violation of the ordinance; no revocation grounds, § 533(6)(a)(3)
Applicant pays Township costs for the decommissioning agreement and estimates only, § 533(12)(c)(7); no consultant review of studies
Benefits & exceptionsHide benefits & exceptions1
Approval pathway: Special exception in the Industrial (I-1) District
Sources
current law · East Buffalo TownshipThe Supervisors adopted Ordinance 429, which added data center and data mining definitions to the zoning.East Buffalo Township, Union County — data-center ordinance / amendment 429 (2025-11-24)
What this means
The measure adds a definition for data centers or related computing uses. The described change does not itself establish a new approval route, operating restriction or financial benefit.