East Brandywine Township
Anti-Data Center Policies
East Brandywine Township’s enacted ordinance allows data centers but requires cooling and water-use controls, noise limits and testing, and setbacks from homes and other protected places, adding construction and compliance costs.
Incentives
Financial Incentive
Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.
current law · East Brandywine TownshipThe rules are in Ordinance 4 of 2026, which the Board of Supervisors adopted on July 16, 2026, and the Board has scheduled a November 12, 2026 hearing on a developer's curative amendment that would permit data centers by right throughout the R-2 Residential district, starting with a site on East Reeceville Road.East Brandywine Township, Chester County — data-center ordinance (No. 4 Of 2026)
What this means
The measure imposes cooling and water-use rules, noise limits and sound testing and setbacks from homes or other protected places. Data centers can still be approved, but these obligations meaningfully increase construction, compliance or review costs.
Restrictions & requirementsHide restrictions & requirements14
55 dBA day and 45 dBA night at residential receivers, § 399-102.9.O, Table 2
Section 399-102.9.O, Table 6, treats an increase of more than 3 dBA above the baseline ambient level documented before construction as a violation, measured with a Type 1 or Type 2 ANSI meter (Table 5), but the baseline is not defined as L90 and no floor is set below which the cap does not apply (text read from the codified section on eCode360).
70 dBC day and 60 dBC night, § 399-102.9.O, Table 3
Study with application and within 180 days of operation, § 399-102.9.O(1), (3)
65 VdB perception limit with study, § 399-102.9.O(3)(f)
Public water supply required, § 399-102.9.H, J
Closed-loop required; alternatives must use less water, § 399-102.9.I.
Tier 4 diesel generators with annual testing reports, § 399-102.9.E, F
Thermal impact mitigation plan with waste heat reuse evaluation, § 399-102.9.K.
Electronic waste plan for servers, batteries, and hazardous materials, § 399-102.9.L, N.
Energy usage plan required; renewables not required, § 399-102.9.D
Roof-mounted equipment screened, § 399-102.9.C
Closure notice and hazardous material removal within 1 year; no security, § 399-102.9.M, N
One post-construction noise study, § 399-102.9.O(3)
Benefits & exceptionsHide benefits & exceptions1
Approval pathway: Conditional use in the CS/LI district
Sources
pending · East Brandywine TownshipProposes defining data centers and allowing them by right in the R-2 residential district; the amendment is part of a pending zoning challenge, not an enacted regulation.Proposed Curative Amendment to East Brandywine Township Code Sections 399-27 and 300-17
What this means
The proposal would allow data centers by right in the R-2 residential district, removing a major zoning barrier to building them (“permit the use by-rite within the R-2 Residential district”). The use would still need to meet the Township’s zoning standards, so this is a substantial benefit, not an unrestricted approval.
People behind it
- 500 E RE BY Trust
Applicant that filed the validity challenge and proposed the curative amendment concerning data center use.
Restrictions & requirementsHide restrictions & requirements1
The proposed amendment would require data centers to comply with the standards in Chapter 300; the provided documents do not specify those standards.
Benefits & exceptionsHide benefits & exceptions1
The proposed curative amendment would allow data centers by right in the R-2 Residential district, subject to the standards in Chapter 300. (by-rite within the R-2 Residential district; standards delineated in Chapter 300)
Sources
Thank you to the Pennsylvania Data Center Ordinance Tracker for providing proposed local ordinance data for PA. Citation: padatacenterordinances.org, accessed November 3, 2026.Cookie preferences · Report missing data