Anti-Data Center Policies

East Bradford Township’s enacted rules require data centers to meet cooling and water-use standards, setbacks and minimum site sizes, increasing costs; approval remains possible.

Incentives

Financial Incentive

Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.

current law · East Bradford Township
The rules are in Ordinance 04-2026, which the Board of Supervisors adopted on September 10, 2026.East Bradford Township, Chester County — data-center ordinance (No. 04-2026)

What this means

The measure imposes cooling and water-use rules, setbacks from homes or other protected places and minimum site-size requirements. Data centers can still be approved, but these obligations meaningfully increase construction, compliance or review costs.

Restrictions & requirementsHide restrictions & requirements25
  • Conditional use before the Board of Supervisors, § 115-38.C; no approval expiration

  • Must meet the Chapter 74 noise limits; no separate data center limits, § 115-40.1.F(2)

  • Where the baseline exceeds the Chapter 74 limit, operations may not materially increase it; no 10 dBA cap, § 115-40.1.F(4)

  • Full-spectrum modeling of low-frequency noise required; no dBC limit, § 115-40.1.F(2)(e)

  • Pre-construction study with the application and as-built study within 180 days of operation; none at building permit, § 115-40.1.F

  • Testing limited to 10 a.m. to 4 p.m. weekdays and capped at 100 hours per year, § 115-40.1.E(7)

  • Section 115-40.1.F(1) and F(2) require pre-construction and as-built noise and vibration studies, and F(2)(f) caps ground vibration at 0.02 in/sec peak particle velocity at or beyond the property line, measured under U.S. Bureau of Mines RI 8507, with ISO 2631-1 for human perception.

  • Must connect to public water, may not use groundwater or surface withdrawals as the primary cooling source, and provider confirmation of supply required, § 115-40.1.H

  • Air-cooled or closed-loop cooling required; alternatives only if they use less water and energy, § 115-40.1.H(5).

  • Daily and annual water use estimates and a drought response plan; no cap or ongoing reporting, § 115-40.1.H

  • Diesel generators must meet EPA Tier 4 with annual testing reports to the Township, § 115-40.1.E(7)

  • Electronic waste plan for removal and recycling of servers, batteries, and hazardous materials, § 115-40.1.M.

  • Documentation of the utility interconnection application and transmission security agreement; no electrical inspection, § 115-40.1.E(6)

  • Energy usage plan required; rooftop solar listed only as an example, § 115-40.1.E

  • Power generation serving the data center is a separate principal use with its own approval, placed behind the data center from homes, § 115-40.1.J(1).

  • Substations at the side or rear and screened; on-site lines of 34.5 kV and below buried, § 115-40.1.J

  • Facade offsets, material limits, and articulation standards, § 115-40.1.D.

  • Ground and rooftop equipment screened on all sides; no height or acoustic standard, § 115-40.1.C

  • Scaled architectural elevations required, § 115-40.1.D

  • Emergency response plan accepted by the fire department, with radio coverage and 24-hour contact signs, but no annual updates, § 115-40.1.K

  • Annual fire safety inspections; no third-party electrical inspection, § 115-40.1.K(1)(e)

  • Construction plan sets times and locations for construction vehicles; no road bond, § 115-40.1.L

  • Decommissioning plan and notice of closure, with financial security only if the Township requires it and completion within 18 months, § 115-40.1.N

  • One as-built noise and vibration study, plus annual generator test reports, § 115-40.1.E(7) and F(2)

  • Corrective action plan and remediation within 90 days of noncompliance, § 115-40.1.F(3)

Benefits & exceptionsHide benefits & exceptions1
  • Approval pathway: Conditional use in the I Industrial district