East Allen Township
Anti-Data Center Policies
Pennsylvania requires data centers over 25 megawatts to obtain local approvals and meet power, grid-cost, environmental, and community commitments; covered facilities also face annual energy and water reporting. These rules make large projects harder, not impossible, while eligible centers may receive equipment tax breaks.
Rating and summary from Pennsylvania statewide as there are no scored current or future laws outside temporary restrictions for East Allen Township.
Incentives
Financial Incentive
Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.
pending · East Allen TownshipSupervisors authorized advertising it on January 5, 2026, the Planning Commission reviewed Version 4 on April 2, 2026, and no adoption was found, while a separate comprehensive zoning rewrite (Ordinance 2026-01) was sent for advertising and planning review on August 27, 2026.East Allen Township, Northampton County — proposed data-center ordinance (None Adopted)
What this means
The proposal would impose noise limits and sound testing and minimum site-size requirements. Data centers can still be approved, but these obligations meaningfully increase construction, compliance or review costs.
Restrictions & requirementsHide restrictions & requirements21
50 ft maximum height; no rooftop limit, draft (26)A.2
Average continuous noise at or below pre-development levels; no numeric day and night limits, draft (26)F.1
Draft Section (26)F.1 limits average continuous data center noise to the average continuous level before development, measured as the 24-hour average decibel level at the property line.
Study must state low-frequency impacts; no dBC limit, draft (26)F.3(f)
Pre-hearing and post-occupancy studies, draft (26)F.2
Vibration not perceptible at the boundary; no vibration study, draft (26)G.2(b)
Public water required; consumption and capacity assessment, draft (26)A.4 and B.2
Cooling system documentation required, draft (26)G.1
Water consumption disclosed in capacity assessment, draft (26)B.2
Public sewer required; sewer consumption assessed, draft (26)A.4 and B.2
Will-serve letter and PJM interconnection documentation before approval, draft (26)B.1 and B.2.
Substations enclosed or behind a 10 ft opaque fence with evergreen screen; lines underground where practical, draft (26)E.6 and E.7
Draft Section (26)B.1 to B.3 require documentation of load availability, required upgrades, interconnection timelines, and PJM approval, a utility will-serve letter, and applicant payment for system improvements.
100 ft buffer with raised berm on all sides, draft (26)D.
Ground equipment enclosed or screened on three sides with acoustic walls; no 12 ft minimum, draft (26)E.3 and E.7
Plan approved by the fire department with radio repeater; no annual updates or posted contacts, draft (26)H.4 and J.1
Plan must ensure first-responder training; no funding, draft (26)J.1(e)
Annual fire safety inspections and township pre-planning inspection; no third-party electrical inspection, draft (26)J.1(f) and J.2
Draft Section (26)C.2 requires a traffic impact study under Section 250-55 in every case, showing no degradation of the roads serving the use.
Annual sound studies or studies on complaint, draft (26)F.2(c)
Township consultants may review the noise study; cost not assigned, draft (26)F.2
Benefits & exceptionsHide benefits & exceptions1
Proposed approval pathway: Proposed: conditional use in the Extractive Industrial District
Sources
Thank you to the Pennsylvania Data Center Ordinance Tracker for providing proposed local ordinance data for PA. Citation: padatacenterordinances.org, accessed November 3, 2026.Cookie preferences · Report missing data