Derry Township
Anti-Data Center Policies
Mifflin County’s enacted amendment requires sound studies, sets noise and minimum-lot rules, and provides power-related guidelines for covered municipalities; it does not ban data centers. The description’s “if enacted” wording conflicts with its enacted status.
Rating and summary from Mifflin County as there are no scored current or future laws outside temporary restrictions for Derry Township.
Incentives
Financial Incentive
Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.
pending · Derry TownshipThe draft ordinance is unnumbered and undated, and the Supervisors voted on September 21, 2026 to advertise a public hearing on adoption for November 16, 2026.Derry Township, Mifflin County — proposed data-center ordinance (None Adopted)
What this means
The proposal would impose cooling and water-use rules, money set aside for eventual removal and noise limits and sound testing. Data centers can still be approved, but these obligations meaningfully increase construction, compliance or review costs.
Restrictions & requirementsHide restrictions & requirements31
Conditional use under the § 215-133 review procedures; no one-year expiration of approval, Sections 2 to 4
District height limit applies, inclusive of rooftop equipment; no 40 ft limit, § 215-111C B.
Environmental and community impact analysis, PNDI clearance, and the 25 Pa. Code 102.14 riparian buffer rules stated as applying, § 215-111C S, Y, and Z
Section 215-111C H(1) sets 50 dBA day and 40 dBA night and weekend at the property line where the site borders residential, rural, forest, health care, or agricultural zones, measured with ANSI S1.4 sound level meters and generally accepted methodology.
Section 215-111C H(1) to (3) require a sound study with the application, a preliminary study at building permit, and an as-built study six months after occupancy using ANSI S1.4 meters, but the as-built study is not required at full operating load.
Public water supply required for all data centers, so wells may not be used, with authority certification of supply, § 215-111C U(1)
Water-based cooling must be closed-loop without direct exposure to the atmosphere, § 215-111C U(2)
Water demand analysis with average, maximum daily, and peak seasonal demand; no cap, reporting, or drought plan, § 215-111C U(2)
Sewer authority must confirm it can accept the flow and cooling water may not be discharged to stormwater; no approved cooling discharge plan, § 215-111C U(1)-(2)
Section 215-111C S(6) applies the Township stormwater ordinance and Section 215-111C U(2) and (3) bar cooling water discharge to stormwater and require secondary containment for cooling chemicals, but no added treatment or spill containment is required for runoff from fuel, generator, and transformer areas.
On-site generation must meet environmental standards; no Tier 4 requirement, § 215-111C O
Electronic Waste Plan for hazardous materials and electronic waste; servers, batteries, and refrigerants not named, § 215-111C V(2)
Service provider verification of adequate capacity with the application and verification of a third-party final electrical inspection, § 215-111C K(1) and (6)
Energy Usage Plan required; on-site solar only encouraged, § 215-111C K(2) and X
Substations screened to 8 ft and placed to the side or rear, with on-site lines of 34.5 kV and below buried, § 215-111C N(1)-(3)
Planted buffer of 100 ft, rising to 150 or 300 ft for larger footprints, along lines within 1,000 ft of homes or residential zones, § 215-111C R(3).
Low-reflective earth tone colors required, metallic and fluorescent colors barred, and campus massing transitions required, § 215-111C T and A(3).
Ground equipment screened behind an opaque wall and rooftop equipment screened on all four sides; no 12 ft height or acoustic standard, § 215-111C R(2)
Buildings must be sited to reduce visual impact, but no visual study or elevations required, § 215-111C A(2)
Emergency Response Plan submitted to the fire department and county emergency services with in-building radio coverage; no annual updates or posted 24-hour contacts, § 215-111C P(1) and V
Applicant must ensure first responders receive training; funding not required, § 215-111C P(2)
Secondary containment and spill prevention for cooling chemicals; no storage setbacks, § 215-111C U(2)-(3)
Third-party final electrical inspection before occupancy; no annual fire inspections, § 215-111C K(6)
Section 215-111C S(5) requires a Traffic Impact Study for every data center covering construction traffic impacts, delivery trips, and intersection capacity, but it sets no study area reaching the nearest arterial or interchange the trucks will use.
Public road access and a secondary emergency access required; no arterial or collector road requirement, § 215-111C A(4)
Construction traffic is only a study topic; no work hours, haul routes, or road bond
Security of 110% and notice of cessation, but removal may finish up to 240 days after the final abandonment determination, Section 6 A(1)-(5)
One as-built sound study six months after occupancy, § 215-111C H(3)
Section 7 A(2) revokes approval if the data center is altered out of conformity and Section 215-111C H(3) requires remediation of noise violations, but no notice or hearing precedes revocation and MPC Sections 616.1 and 617.2 are not cited.
Operator pays the township's costs to review decommissioning estimates only, Section 6 A(8)
Operator defined, but developer, operator, and end user not required to be named
Benefits & exceptionsHide benefits & exceptions1
Proposed approval pathway: Proposed: conditional use in the General Commercial, Light Industrial, and Heavy Industrial Zones
Sources
Thank you to the Pennsylvania Data Center Ordinance Tracker for providing proposed local ordinance data for PA. Citation: padatacenterordinances.org, accessed November 3, 2026.Cookie preferences · Report missing data