Dennison Township

Anti-Data Center Policies

Dennison township’s enacted ordinance allows data centers only on qualifying sites, with minimum size and setback requirements that substantially restrict where and how they can be built.

Incentives

Financial Incentive

Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.

current law · Dennison Township
The current rules are in Ordinance No. 2 of 2026, which the Board of Supervisors adopted on July 8, 2026, following a public hearing held that evening.Dennison Township, Luzerne County — data-center ordinance (No. 2 Of 2026)

What this means

The measure imposes setbacks from homes or other protected places, minimum site-size requirements and limited eligible locations. The limits sharply reduce usable sites or workable project designs, making development substantially harder despite an available approval route.

Restrictions & requirementsHide restrictions & requirements33
  • Section 2.C and Section 4.A.4 permit data centers only on parcels mapped in the DC-O District, which is shown on the Official Zoning Map and Exhibit A, and state that the underlying I-1 uses are unchanged.

  • Conditional use before the Board of Supervisors; no approval expiration, § 4

  • Barred on land under a farmland preservation easement; no agricultural security area bar, § 6.A.1

  • Boundary setback protects all neighbors; no use-specific setbacks for schools, day care, hospitals, or parks, § 5

  • Phases are covered by one conditional use approval; no new approval for added capacity, § 1.F

  • Single 50 dBA LAeq limit at the tract boundary, day and night, § 7.D.2

  • Section 7.D.4 requires a worst-case predictive study with the application and an as-built field test within 90 days of the first certificate of occupancy, measured by the LAeq and ANSI Type 1 or 2 method in Section 7.D.3.

  • Generators limited to backup and testing use; no testing hours or hours cap, § 4.A.3

  • Vibration study showing none perceptible beyond the tract boundary, § 7.D.7.

  • Section 7.E.3 bars continuous groundwater use for cooling and requires trucked cooling water, and Section 7.E.5 requires a feasibility study with drawdown and recovery testing of wells.

  • Section 7.E.3 allows only closed-loop non-evaporative, dry air-cooled, or closed-loop chilled water or glycol systems and prohibits open-loop water-cooled systems.

  • 20,000 gallon per day cap on nonpublic potable water; drought plan only if the township declares a shortage, § 7.E.4 and E.8

  • Section 7.E.3 requires DEP approval for disposal of cooling water and Section 7.E.7 requires wastewater facilities approved by the SEO or DEP, but neither states that the approvals must be in hand before the zoning permit.

  • Township stormwater ordinance compliance and long-term maintenance required, § 5

  • Generators must meet federal and state air quality requirements, § 4.A.3.b

  • Batteries, fuel, and refrigerants disposed of under state and federal law at decommissioning; no server recycling plan, § 7.I.4

  • Utility documentation that 230 kV service is feasible before approval; no electrical inspection, § 2.D.2 and § 7.F.1.

  • On-site generation for normal operations is a separate principal use with its own approvals, § 7.F.2.

  • Transformers and substations are accessory and must be located or screened to limit visibility, § 4.A.2 and § 7.C.4

  • NFPA 855 with suppression and monitoring designed for the technology installed, § 7.G.3.

  • 100-ft planted buffer next to residential districts, homes, and roads, § 7.A.1.

  • Full-cutoff, downward fixtures and no light source visible from homes; no property-line trespass limit, § 7.D.8

  • General facade articulation and material requirements without measurable standards, § 7.C

  • Equipment within 300 ft of residential districts or roads enclosed or screened; fences up to 10 ft, § 7.B

  • Elevations of all sides required; no visual impact study, § 7.C.5

  • Emergency plan reviewed by the fire department; no annual update, radio coverage, or posted contacts, § 7.G.2

  • First responder training plan with funding for fire and EMS, refreshed annually, § 7.G.2.d.

  • Annual fire and life-safety inspections; no third-party electrical inspection, § 7.G.2.e

  • Security for full removal cost, start within 1 year and finish within 18 months; not 110% or 6 months, § 7.I

  • Security reviewed every two years; no first-year update, § 7.I.2

  • One as-built test, with periodic re-testing only if made a condition of approval, § 7.D.4 and D.5

  • Township may require confirmatory noise testing, paid by the operator only if an exceedance is found, § 7.D.5

  • Operator defined and the building permit noise study must reflect the proposed operator; no end user disclosure, § 1.H and § 7.D.4

Benefits & exceptionsHide benefits & exceptions1
  • Approval pathway: Conditional use in the Data Center Overlay (DC-O) District

Sources

Thank you to the Pennsylvania Data Center Ordinance Tracker for providing proposed local ordinance data for PA. Citation: padatacenterordinances.org, accessed November 3, 2026.Cookie preferences · Report missing data