Decatur Township

Anti-Data Center Policies

Pennsylvania requires data centers over 25 megawatts to obtain local approvals and meet power, grid-cost, environmental, and community commitments; covered facilities also face annual energy and water reporting. These rules make large projects harder, not impossible, while eligible centers may receive equipment tax breaks.

Rating and summary from Pennsylvania statewide as there are no scored current or future laws outside temporary restrictions for Decatur Township.

Incentives

Financial Incentive

Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.

pending · Decatur Township
The undated draft amendment to SALDO Ordinance No. 92 has been submitted to the Clearfield County Planning and Community Development Office for review, and the township Planning Commission had not yet reviewed it as of November 2, 2026, with no hearing or vote scheduled.Decatur Township, Clearfield County — proposed data-center ordinance (None Adopted)

What this means

The proposal would impose setbacks from homes or other protected places, cooling and water-use rules and noise limits and sound testing. Data centers still have an approval route, but the siting or operating limits significantly narrow feasible projects.

Restrictions & requirementsHide restrictions & requirements24
  • Agricultural land is listed as a sensitive receptor for setbacks, but preserved farmland is not barred, § 201 and § 620.C

  • Principal buildings, accessory structures, and substations 1,000 ft from existing homes, with ground equipment barred from setbacks, § 620.C(2) and P(2)(a)(iii)

  • 35 ft maximum with waiver possible; rooftop equipment screened but not counted in height, § 620.B and P(2)(b)

  • Structures 200 ft from streams and wetlands, and an Environmental Impact Assessment is required; no wider buffer on steep slopes, § 620.C(4) and U

  • Single 57 dBA CNEL limit at property boundaries; no stated measurement method, § 620.F(1)

  • Water feasibility study for non-public sources, with wells within 1,000 ft mapped; no pump tests, § 620.S(2)

  • Water cooling systems must be closed loop, § 620.S(3)

  • Projected water demand and use by purpose disclosed in the feasibility study, § 620.S(2)(a) and (c)

  • Public authority must certify the sewage system can accept the flow, and the study states water discharged and by what means, § 620.S(1) and (2)(e)

  • Stormwater plan consistent with the local stormwater ordinance and DEP rules, § 620.U(3)

  • Tier 4 or greater generators required; no annual testing or reports, § 620.M(1)

  • Written verification from the service provider that capacity is available with the application, and third-party electrical inspection before operation, § 620.I

  • Solar Energy Plan with projected annual use and solar installed within 12 months of occupancy; no phase peaks or efficiency, § 620.M(2)

  • On-site or behind-the-meter generation permitted if it meets environmental, safety, and interconnection standards; not a separate use, § 620.M(1)

  • Substations screened 8 ft and placed to the side or rear, and on-site lines of 34.5 kV and below buried, § 620.L

  • Battery storage must meet NFPA 855 with battery-specific suppression, § 620.H(2)

  • 100 to 300 ft dense evergreen buffer along frontage and lines within 1,000 ft of homes; replacement of dead plants not required, § 620.P(3)

  • Ground equipment completely screened behind opaque walls and rooftop equipment screened on all four sides, with noise barriers when needed, § 620.P(2) and F(2)

  • Line-of-sight siting goal only; no visual study or renderings, § 620.A(2)(a)

  • Must confirm local departments have proper chemicals and supplies; no training requirement, § 620.T

  • Third-party final electrical inspection before operation only, § 620.I(5)

  • Vehicle trips described in the impact analysis only; no traffic study, § 620.Q(1)

  • Decommissioning plan with bond or letter of credit of at least 100% of cost; no removal timeline, § 620.V(1)-(2)

  • Requirements remain conditions of approval, with injunctive relief and liens for decommissioning, § 620 and V(3)