Covington Township
Anti-Data Center Policies
Covington Township’s enacted ordinance requires data centers to meet noise limits, undergo sound testing, maintain setbacks, and meet minimum site-size rules, increasing costs while still allowing approval.
Incentives
Financial Incentive
Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.
current law · Covington TownshipThe rules are in Ordinance 2025-03, which the Board of Supervisors adopted by a 3 to 2 vote on July 24, 2025.Covington Township, Lackawanna County — data-center ordinance (No. 2025-03)
What this means
The measure imposes noise limits and sound testing, setbacks from homes or other protected places and minimum site-size requirements. Data centers can still be approved, but these obligations meaningfully increase construction, compliance or review costs.
Restrictions & requirementsHide restrictions & requirements23
Article IV Sections 401, 402, and 404.9 add the DCET Data Center and Energy Technology District and adopt an amended zoning map showing it, and Article V Section 1.a permits data centers by conditional use, but the amendment does not expressly exclude data centers from all other districts.
Conditional use, Article V § 1.a; no approval expiration
Environmental impact statement required under § 531, Article V § 1.b(8)
DCET campus defined and planned as one development, Article III and Article V § 1.b
Master plan for the whole campus, with parcels added only by Township approval, Article V § 1.b
65 dBA day and 55 dBA night at property lines, Article V § 1.c.vii
Preliminary study with the conditional use and as-built study six months after occupancy, Article V § 1.c.vii
Testing must meet the noise limits; no time or hours limits
Water feasibility study of wells within 1,000 ft, with a Township study at the developer's cost; no bar on wells for cooling, Article V § 1.c.v
Projected water needs disclosed and SRBC or DRBC approval above thresholds, Article V § 1.c.v
Study must identify how water will be released and its impacts; no approved discharge plan, Article V § 1.c.v
Interconnection agreement confirming capacity and utility approval of power use before construction; no electrical inspection, Article V § 1.c.vi
Power generation plants listed as conditional uses in the DCET and small modular reactors by special exception; no separate setbacks, § 407
Power storage permitted without fire standards
Known electric rate impacts must be stated in the interconnection agreement, Article V § 1.c.vi
100-ft woodland buffer along all exterior property lines, Article V § 1.c.ii.
Equipment placement rules only; no screening
Only a second emergency access; no emergency plan
Trip generation in the master plan and a traffic and/or community impact study, Article V § 1.b(5) and 1.c.iv
Decommissioning required only for small modular reactors
One as-built sound study after opening, Article V § 1.c.vii
Article V Section 5 requires written notice of a violation and a time to correct it, followed by fines set by Board resolution, injunctive relief, and attorney fees, and Section 1.c.vii allows a zoning permit to be rescinded for noise violations, but revocation is not preceded by a hearing and Sections 616.1 and 617.2 of the Municipalities Planning Code are not cited.
Article V Section 3 requires, with the Master Plan fee, a $20,000 escrow deposit to pay the Township's professional fees in processing the application, replenished in $10,000 increments, and Section 1.c requires sound and water studies approved by the Township at the developer's expense.
Benefits & exceptionsHide benefits & exceptions1
Approval pathway: Conditional use in the DCET Data Center and Energy Technology District
Sources
Thank you to the Pennsylvania Data Center Ordinance Tracker for providing proposed local ordinance data for PA. Citation: padatacenterordinances.org, accessed November 3, 2026.Cookie preferences · Report missing data