Borough of Cornwall
Anti-Data Center Policies
Cornwall Borough requires data centers to meet setbacks from homes and other protected places and minimum site-size requirements, raising costs and review burdens without barring approval.
Incentives
Financial Incentive
Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.
current law · Cornwall BoroughThe current rules are in Ordinance 2026-3, which Borough Council adopted on May 11, 2026.Cornwall Borough, Lebanon County — data-center ordinance (No. 2026-3)
What this means
The measure imposes setbacks from homes or other protected places and minimum site-size requirements. Data centers can still be approved, but these obligations meaningfully increase construction, compliance or review costs.
Restrictions & requirementsHide restrictions & requirements16
67 dBA day and 57 dBA night at the property line, § 14-2620.2.E
Section 14-2620.2.E(1)(a) to (c) require preliminary, interim (building permit), and as-built sound studies using ANSI S1.4 meters and generally accepted methodology, and Section 14-2620.3.D requires an annual noise study, but the limits apply to normal operations and no post-opening study is required at full operating load.
Generator testing on weekday daytime only; no hours cap, § 14-2620.3.E
Vibration study showing none past the property line, § 14-2620.2.E(3).
Water feasibility study for nonpublic sources, § 14-2620.2.C
Cooling method not required to be disclosed
Projected water demand in feasibility study, § 14-2620.2.C
Section 14-2620.2.C(4) requires the special exception application to demonstrate that adequate disposal of domestic, cooling, and industrial wastewater has been provided and approved by the Sewage Enforcement Officer, the public sewer provider, or DEP.
Utility certification of capacity; no third-party inspection, § 14-2620.2.D.
On-site generation is a separate use needing its own approval, § 14-2620.2.D(2).
Plan accepted by fire department, contact list kept current, § 14-2620.2.F and 3.C
Annual fire safety inspections, § 14-2620.2.F(1)(e)
Section 14-2620.2.B requires a traffic impact study with every special exception application under Section 13-406(3), but that study covers a fixed one-half or one-and-one-half mile area for the design year of the completed development, with no construction traffic analysis or study area reaching the nearest arterial or interchange the trucks will use.
Annual noise study report, § 14-2620.3.D
Noise exceedance is a violation, § 14-2620.2.E
Council may set a fee for its review of the annual study, § 14-2620.3.D
Benefits & exceptionsHide benefits & exceptions1
Approval pathway: Special exception in the Limited Industrial and General Industrial districts
Sources
Thank you to the Pennsylvania Data Center Ordinance Tracker for providing proposed local ordinance data for PA. Citation: padatacenterordinances.org, accessed November 3, 2026.Cookie preferences · Report missing data