Conewago Township
This restriction takes precedence for the map color while in effect.
Anti-Data Center Policies
Conewago Township’s enacted measure pauses covered data-center applications or development for 180 days, temporarily stopping affected projects but not permanently banning them.
Rating from Pennsylvania statewide as there are no scored current or future laws outside temporary restrictions for Conewago Township.
Incentives
Financial Incentive2
Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.
Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.
current law · Conewago TownshipThe Board of Supervisors adopted Resolution 2026-13, a 180-day moratorium on data center applications ending January 3, 2027.Conewago Township, York County — Resolution2026-13 data-center moratorium
What this means
The measure pauses covered data-center applications or development for 180 day. That stops affected projects from moving ahead during the pause, even though it is not a permanent ban.
Timing
- Ends
- 180-day; exact operative ending date not independently verified.
The Board of Supervisors adopted Resolution 2026-13, a 180-day moratorium on data center applications ending January 3, 2027.
Sources
pending · Conewago TownshipThe Planning Commission reviewed the draft again on October 26, 2026, the Board of Supervisors agenda for November 4, 2026 lists authorization to advertise the ordinance and the overlay map amendment, and a 180-day moratorium on data center applications runs until January 3, 2027.Conewago Township, York County — proposed data-center ordinance (None Adopted)
What this means
The proposal would impose setbacks from homes or other protected places, minimum site-size requirements and limited eligible locations. The limits sharply reduce usable sites or workable project designs, making development substantially harder despite an available approval route.
Restrictions & requirementsHide restrictions & requirements26
Conditional use by the Board of Supervisors; no approval expiration, § 701.a
Section 701.c.2.B sets 1,000 ft front, side, and rear yards where the site abuts a residential district or existing residential use, and Section 701.c.2.D bars any accessory structure or material storage within the required yards.
Updated noise study on expansion only; no new approval or phasing plan
45 dBA day and 40 dBA night, measured at sensitive receptors rather than the property line, § 701.c.8.F
Section 701.c.8.F caps project sound at ambient plus 5 dBA, with ambient defined as the lowest valid one-hour LA90 from a 48-hour survey and measurements made with ANSI/IEC Class 1 instruments for at least 15 minutes, but no floor is stated below which the cap does not apply.
60 dBC day and 50 dBC night, § 701.c.8
Preconstruction survey, noise impact study, and post-construction verification; no building permit study, § 701.c.8
Air-cooled or closed-loop required; high-loss evaporative cooling with potable water prohibited, § 701.c.10.D.
Water needs analysis only; no cap, reporting, or drought plan, § 701.c.10.B
Public sewer required with no on-site discharge, § 701.c.10.C
EPA Tier 4 generators and annual air quality testing, § 701.c.11
Written capacity verification from the utility; no third-party electrical inspection, § 701.c.9.B.
LEED standard, solar-ready roofs, and 10% renewable procurement over 50 MW; no on-site generation required, § 701.c.12
Emergency generation limited and peak shaving prohibited, § 701.c.11.D
Substations screened to 12 ft and new lines underground; no side or rear placement rule, § 701.c.4.C
50-ft buffer with berms and plantings, § 701.c.3
Section 701.c.14 requires two of five elements on principal facades and fenestration plus a material or color change on secondary facades, but sets no measurable intervals, material percentages, or color limits.
Ground equipment screened with acoustic screening and 12-ft substation barrier; ground equipment screen height tied to equipment height, § 701.c.4
Fire department review, annual inspections, radio coverage, and 24-hour signage; no annual plan update, § 701.c.13
Training of first responders required; no funding, § 701.c.13
Secondary containment; no storage setback, § 701.c.11.E
Annual fire safety inspections; no third-party electrical inspection, § 701.c.13
Traffic accommodation shown; no traffic study required, § 701.a.3
Construction routes on arterial roads only; no hours or road bond, § 701.c.15.H
110% security less salvage value; no closure notice or removal deadline, § 701.c.17
Annual noise testing for 3 years then every 3 years, plus annual air testing, § 701.c.8.M
Benefits & exceptionsHide benefits & exceptions1
Proposed approval pathway: Proposed: conditional use in a Data Center Overlay
Sources
Thank you to the Pennsylvania Data Center Ordinance Tracker for providing proposed local ordinance data for PA. Citation: padatacenterordinances.org, accessed November 3, 2026.Cookie preferences · Report missing data