Columbia Borough permits data centers in designated districts without special discretionary approval, providing a clearer route while ordinary zoning and building rules still apply.
Incentives
Financial Incentive
Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.
current law · Columbia BoroughThe rule comes from Ordinance No. 957 of 2025, adopted on August 26, 2025, and after Council revised Draft Ordinance 2026-966 at a September 24, 2026 special meeting, its October 27, 2026 agenda listed the county review of Ordinance 2026-967, a zoning text amendment on the permitted use of data centers, and a vote on authorizing it to be advertised.Columbia Borough, Lancaster County — data-center ordinance (No. 957 Of 2025)
What this means
The measure expressly allows data centers in designated districts without a special discretionary use approval. This gives developers a clearer approval route, while ordinary zoning and building rules still apply.
Restrictions & requirementsHide restrictions & requirements1
Permitted by right, Ch. 220 Attachment 2
Benefits & exceptionsHide benefits & exceptions1
Approval pathway: Permitted by right in the Light Business and General Industrial districts