Collier Township
Anti-Data Center Policies
Pennsylvania requires data centers over 25 megawatts to obtain local approvals and meet power, grid-cost, environmental, and community commitments; covered facilities also face annual energy and water reporting. These rules make large projects harder, not impossible, while eligible centers may receive equipment tax breaks.
Rating and summary from Pennsylvania statewide as there are no scored current or future laws outside temporary restrictions for Collier Township.
Incentives
Financial Incentive
Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.
pending · Collier TownshipThe draft, dated August 2026, was posted on the township website on August 15, 2026, and the Board of Commissioners set a public hearing for October 12, 2026, when its agenda listed a motion to approve the draft as Ordinance No. 743, but no minutes or other record of the outcome had been posted as of October 28, 2026.Collier Township, Allegheny County — proposed data-center ordinance (None Adopted)
What this means
The proposal would impose cooling and water-use rules, money set aside for eventual removal and noise limits and sound testing. Data centers can still be approved, but these obligations meaningfully increase construction, compliance or review costs.
Restrictions & requirementsHide restrictions & requirements26
Conditional use decided by the Board of Commissioners after a hearing, § 27-1802.1.G; approval expires only if no permit application is filed within 12 months, with one 12-month extension, § 27-1802.2.
I-1 limit of 40 ft for principal structures, § 27-1603.10; rooftop mechanical equipment may exceed it by up to 15 ft, § 27-1906
Compliance with DEP, federal, and local environmental rules and no direct stream intake or outtake, § 27-1806.15.A and L.ii.3; no riparian buffer
67 dBA weekday day and 57 dBA night and weekend at the property line, and 57 dBA at residential and sensitive receptor lines, § 27-1806.15.H.i and iv
Section 27-1806.15.H.i requires preliminary, interim, and as-built studies using ANSI S1.4 meters and generally accepted methodology.
Testing limited to 9 a.m. to 3 p.m. weekdays and capped at 100 hours per year, § 27-1806.15.K.v.4
Vibration study showing no vibration perceptible beyond the property line, § 27-1806.15.H.iii.
Public water capacity letter, or a water feasibility study for nonpublic sources; no well restriction or pump test, § 27-1806.15.L.ii
Section 27-1806.15.L.iv requires a closed-loop cooling system.
Analysis of anticipated raw water needs required; no cap, reporting, or drought plan, § 27-1806.15.L.ii.1
Section 27-1806.15.L.iii requires the applicant to demonstrate that domestic, cooling, and industrial wastewater disposal has been provided and approved by the local sanitary authority and DEP.
Diesel generators must meet EPA Tier 4; no emissions testing or reports, § 27-1806.15.K.v.1 and 3
Heat rejection and cooling discharge designed to avoid thermal impacts on adjacent properties; no waste heat reuse review, § 27-1806.15.J.iv
Decommissioning plan covers disposal of hazardous and recycling materials; no server, battery, or refrigerant plan, § 27-1806.15.N.i.1
Electric provider must certify available capacity with the application; no electrical inspection, § 27-1806.15.K.i.
Energy generation supplying the data center is a separate use needing its own permit under the zoning rules for that use, § 27-1806.15.K.iii.
Substations counted as part of the data center and accessory uses, Part 2 definitions; no screening or line burial rule
Battery storage must comply with NFPA standards; no battery-specific suppression, § 27-1806.15.I.i.3
Enhanced screening or screen planting where abutting residential uses, § 27-1806.15.C, with a 35-ft Buffer Area A next to S-C and R districts, § 27-1903.2.A
Mechanical equipment screened from public rights-of-way with sound-attenuating enclosures; not all sides or 12 ft, § 27-1806.15.J
Emergency Response Plan reviewed and accepted by the fire department; no annual updates, radio coverage, or 24-hour contacts, § 27-1806.15.I
Disposal of hazardous materials addressed in the decommissioning plan, § 27-1806.15.N.i.1
Traffic Impact Analysis for I-1 conditional uses with 10,000 sq ft or more of floor area, § 27-1802.1.D, and truck traffic demonstration, § 27-1806.15.F
As-built sound study six months after occupancy, with later studies at Township discretion, § 27-1806.15.H.i.3
Section 27-1902.11.B, applied by Section 27-1803.1.B, requires a written enforcement notice under Section 27-2402 with a reasonable time to correct and makes an uncorrected violation grounds for revoking the occupancy permit, and Section 27-2402 provides the enforcement notice with a 30-day appeal right and civil enforcement judgments.
Section 27-1902.10 allows the Township to retain a technical expert at the applicant's cost during review of an application for zoning approval.
Benefits & exceptionsHide benefits & exceptions1
Proposed approval pathway: Conditional use in the I-1 Industrial District (draft)
Sources
Thank you to the Pennsylvania Data Center Ordinance Tracker for providing proposed local ordinance data for PA. Citation: padatacenterordinances.org, accessed November 3, 2026.Cookie preferences · Report missing data