Codorus Township

Anti-Data Center Policies

Codorus Township requires data centers to follow cooling and water-use rules, noise limits and sound testing, and setbacks from homes and other protected places. Approval remains possible, but these requirements add costs.

Incentives

Financial Incentive

Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.

current law · Codorus Township
The Board of Supervisors enacted the data center ordinance on June 9, 2026, although the signed copy leaves the ordinance number blank, and a proposed amendment that would widen the buffers to 300 feet, lower the noise limit to 40 dBA, and require closed-loop cooling for data centers that are not air-cooled was on the York County Planning Commission's October 20, 2026 agenda with a staff recommendation to adopt.Codorus Township, York County — data-center ordinance (Number Not Assigned (Enacted June 9, 2026))

What this means

The measure imposes cooling and water-use rules, noise limits and sound testing and setbacks from homes or other protected places. Data centers can still be approved, but these obligations meaningfully increase construction, compliance or review costs.

Restrictions & requirementsHide restrictions & requirements28
  • 125-ft planted buffer strip along lines within 500 ft of homes; no building setback distance, § 250-80.1(2)

  • 125-ft buffer strip along lines within 500 ft of schools, day care centers, hospitals, and parks, § 250-80.1(2)

  • Underlying district height; rooftop equipment set back and screened, § 250-80.1(1)(f) and (6)

  • Environmental impact assessment required, § 250-80.1(13)

  • Single 24-hour CNEL limit of 60 dBA at sensitive receptors and 70 dBA elsewhere, § 250-80.1(8)(b)

  • Section 250-80.1(8)(a) requires preliminary, interim, as-built, and six-month post-construction sound studies to show compliance with the CNEL limits in Section 250-80.1(8)(b), but names no measurement method, standard, or instrument and does not require full operating load.

  • 0.2 in/s peak particle velocity limit with pre- and post-construction studies; not a no-perceptible standard, § 250-80.1(10)(c)

  • Public water required and water feasibility study; no pump tests, § 250-80.1(4)(b) and (11)

  • Best available cooling technology must be shown; closed loop not required, § 250-80.1(17)

  • Projected water needs disclosed, § 250-80.1(11)

  • Public sewer required and water release identified, § 250-80.1(4)(b) and (11)

  • Stormwater management plan required, § 250-80.1(13)

  • Air permit applications and final permits provided to the Township; no Tier 4 rule, § 250-80.1(13)

  • Waste heat potential considered in cooling selection, § 250-80.1(17)

  • Hazardous materials removed and disposed of at decommissioning, § 250-80.1(18)(d)

  • Utility capacity letter and third-party electrical inspection before occupancy; no confirmation before approval, § 250-80.1(4)(a)

  • Substations 300 ft from homes and lines of 34.5 kV or less buried; substations not screened, § 250-80.1(3) and (4)(a)

  • 125-ft planted buffer strip next to or within 500 ft of residential property, § 250-80.1(2).

  • Rooftop equipment screened on four sides and ground equipment screened for sound; no 12-ft standard, § 250-80.1(5), (6), and (8)

  • Architectural depictions from all lot lines and streets; no viewshed study, § 250-80.1(5)(f)

  • In-building radio coverage and fire chief review; no emergency plan, § 250-80.1(9) and (12)

  • Third-party electrical inspection before occupancy; no annual inspections, § 250-80.1(4)(a)

  • Construction trip estimates only; no traffic impact study

  • Construction transportation plan with routes and hours; no road damage bond, § 250-80.1(19)

  • 110% security with no salvage credit, but no removal deadline or closure notice, § 250-80.1(18)

  • Estimate and security updated every 5 years, not after the first year, § 250-80.1(18)

  • As-built and six-month post-construction sound studies and one post-construction vibration study, § 250-80.1(8) and (10)

  • Responsible party named in the decommissioning plan; end user not required, § 250-80.1(18)(b)

Benefits & exceptionsHide benefits & exceptions1
  • Approval pathway: Special exception in the General Commercial District

Sources

Thank you to the Pennsylvania Data Center Ordinance Tracker for providing proposed local ordinance data for PA. Citation: padatacenterordinances.org, accessed November 3, 2026.Cookie preferences · Report missing data