Clifford Township

Anti-Data Center Policies

Clifford Township’s enacted ordinance requires setbacks from homes and other protected places, cooling and water-use rules, and funds for eventual removal; approval remains possible, but limits narrow where projects can operate.

Incentives

Financial Incentive

Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.

current law · Clifford Township
The supervisors held public hearings on September 9 and October 13, 2026 and enacted the ordinance in 2026, and the township has posted the signed copy, whose handwritten enactment date could not be read clearly.Clifford Township, Susquehanna County — data-center ordinance (No. 4-2026)

What this means

The measure imposes setbacks from homes or other protected places, cooling and water-use rules and money set aside for eventual removal. Data centers still have an approval route, but the siting or operating limits significantly narrow feasible projects.

Restrictions & requirementsHide restrictions & requirements27
  • Land development approval under SALDO (S5, S20); no conditional use

  • 500 ft setback from streams and wetlands; impact analysis (S6, S7.A)

  • Material size alteration requires permit (S4.B)

  • Township commercial/industrial noise ordinance applies (S9)

  • Section 9 requires preliminary, interim, and as-built sound studies, but it states no measurement method and does not require the as-built study at full operating load.

  • None perceptible past property line, vibration study (S9).

  • Groundwater limited to domestic use and cooling water from rivers and streams only; feasibility study, no pump tests (S10.B, S11.C)

  • Closed loop required; open evaporative towers prohibited (S11.A)

  • Monthly metered reporting, 10% cap; no drought plan (S10.B)

  • Section 10.D requires the applicant to show that adequate means of wastewater disposal have been provided and approved by the Sewage Enforcement Officer or the Pennsylvania DEP.

  • Tier 4 generators; no emissions testing (S14.B)

  • Heat island mitigation and heat recovery plan (S6, S14.A).

  • Utility capacity certification; third-party electrical inspection (S14.B)

  • Energy minimization and electric service plan; no on-site renewables (S14)

  • On-site generation a separate use with own approval (S14.B.2).

  • Section 14 requires a full electric service plan and makes the applicant pay all costs of required infrastructure upgrades with financial security.

  • 75 ft buffer, 50 ft planted (S8)

  • Non-reflective materials, color limits, facade articulation (S7.A)

  • Rooftop and ground equipment screened; no height or acoustic standard (S7, S8)

  • Secondary containment, spill plan; no storage setbacks (S13)

  • Section 15.B.3 requires annual fire safety inspections by a qualified professional on behalf of the data center.

  • Traffic impact evaluation in application (S6)

  • Haul roads identified, road bond (S6)

  • Net cost plus 10 percent bond and 48-hour notice; removal within 12 months, or 6 months after township notice (S19)

  • Section 19.D requires a professional engineer estimate after the first year of operation and every fifth year thereafter, and Section 19.E requires the owner to post and maintain funds equal to net decommissioning costs plus 10 percent.

  • Monthly water logs; monthly then quarterly power reports (S10, S14)

  • Section 20.A.2 revokes approval if the facility falls out of conformity and Section 20.C sets civil penalties of up to $5,000 per violation per day.