Borough of Cleona
Anti-Data Center Policies
Cleona borough’s enacted ordinance requires separation from homes and other protected places, minimum site sizes, and noise limits and testing. Approval remains possible, but these restrictions narrow where data centers can be built and how they can operate.
Incentives
Financial Incentive
Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.
current law · Cleona BoroughThese standards were set by Ordinance No. 337, the comprehensive zoning and map amendments, which Council adopted unanimously on October 5, 2026.Cleona Borough, Lebanon County — data-center ordinance (No. 337)
What this means
The measure imposes setbacks from homes or other protected places, minimum site-size requirements and noise limits and sound testing. Data centers still have an approval route, but the siting or operating limits significantly narrow feasible projects.
Restrictions & requirementsHide restrictions & requirements18
55 dBA weekday daytime and 45 dBA night and weekend at the nearest residential property, § 803A.1E(1)
Section 803A.1E(1) requires a preliminary study in the special exception process, an interim study at building permit, an as-built study six months after occupancy, and annual certification, using ANSI S1.4 meters and generally accepted methodology.
Vibration study showing no vibration perceptible beyond the property line, § 803A.1E(3).
Water feasibility study required for nonpublic water sources, and public authority certification for public water, § 803A.1F(1)-(2)
Projected water demand disclosed in the water feasibility study, and river basin commission approval above set thresholds, § 803A.1F(2)-(3)
Disposal of cooling and industrial wastewater must be approved by the sewage enforcement officer or DEP before approval, § 803A.1F(4)
Electric provider must certify available capacity and service; no electrical inspection, § 803A.1G(1).
Known impacts on electric rates must be noted, and the applicant funds all utility connections at no cost to the Borough, § 803A.1G(1) and I
25-ft landscape buffer next to residential property and public roads, § 803A.1C(1)
Two design elements every 150 horizontal feet on facades facing roads or residences, § 803A.1J.
Equipment within 500 ft of a road or residence enclosed or fully screened; no height standard, § 803A.1D(1)
Emergency response plan reviewed and accepted by the fire department; no radio coverage or posted contacts, § 803A.1H(1)
First responders must receive system-specific training and equipment, with annual training for changes; funding not assigned, § 803A.1H(1)(iv)
Annual fire safety inspections, § 803A.1H(1)(v)
Section 803A.1L requires a preliminary traffic impact assessment in every case, with improvements at the applicant's expense.
Financial security of 110% of decommissioning cost; no closure notice or removal deadline, § 803A.1M
Annual noise compliance certification by an acoustical expert, § 803A.1E(1)(iv)
As-built noise exceedance is a violation of the ordinance, § 803A.1E(1)(iii)
Benefits & exceptionsHide benefits & exceptions1
Approval pathway: Conditional use in the Industrial District
Sources
Thank you to the Pennsylvania Data Center Ordinance Tracker for providing proposed local ordinance data for PA. Citation: padatacenterordinances.org, accessed November 3, 2026.Cookie preferences · Report missing data