Municipality of Clairton

Pro-Data Center Policies

Clairton allows data centers in designated districts without special discretionary-use approval, providing a clearer approval route while ordinary zoning and building rules still apply.

Incentives

Financial Incentive

Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.

current law · Clairton municipality
The current zoning ordinance is Chapter 337 of the city code, adopted July 8, 2014 as Ordinance No. 1891, with its permitted-use table (Table 337-18) last amended May 12, 2015 by Ordinance No. 1908.Clairton City, Allegheny County — data-center ordinance (No. 1891)

What this means

The measure expressly allows data centers in designated districts without a special discretionary use approval. This gives developers a clearer approval route, while ordinary zoning and building rules still apply.

Restrictions & requirementsHide restrictions & requirements2
  • Limited to C/I and I districts, Table 337-18

  • Permitted by right in C/I and I, Table 337-18

Benefits & exceptionsHide benefits & exceptions1
  • Approval pathway: Permitted by right in the C/I and I districts

Sources

Thank you to the Pennsylvania Data Center Ordinance Tracker for providing proposed local ordinance data for PA. Citation: padatacenterordinances.org, accessed November 3, 2026.Cookie preferences · Report missing data