Borough of Chester Heights

Anti-Data Center Policies

Chester Heights allows data centers as conditional uses in limited-industrial districts, but setbacks, site-size, water, cooling, study, and cleanup-security requirements can constrain projects.

Incentives

Financial Incentive

Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.

current law · Borough of Chester Heights
Allows data centers in Limited Industrial districts only with conditional-use approval and imposes requirements for their energy and water use, noise, emissions, safety, screening, and eventual decommissioning.Ordinance No. aa7 — Data Center and Data Center Campus Zoning Standards

What this means

The measure would allow data centers as conditional uses in limited-industrial districts, but applicants would face significant burdens, including strict water-use rules, noise and environmental studies, large buffers, and financial security for eventual cleanup. These requirements could make projects substantially more costly and difficult, even though they are not banned.

People behind it

  • Identified as the petitioner for the data center zoning amendment in the Delaware County Planning Commission materials.

  • Proposed and enacted the ordinance amending the Borough’s zoning code to regulate data centers.

Restrictions & requirementsHide restrictions & requirements22
  • Data centers are allowed only by conditional use in the Limited Industrial districts, requiring conditional-use approval before development. permit data centers by conditional use

  • The County Planning Commission’s review of the amendment identifies a 10-acre minimum tract for data centers over 100,000 square feet, a 60-foot maximum height, and a 250-foot setback from property lines. 10-acre minimum tract size

  • Projects must meet at least a certified level under the LEED BD+C: Data Centers rating system, or an equivalent design standard approved by the Borough Engineer. Certified Level

  • A conditional-use application must include a professionally prepared Energy Usage Plan documenting demand, power sources, storage, backup power, renewable-energy and efficiency efforts, and utility interconnection steps. Energy Usage Plan

  • A grid-connected proposal with planned demand over 50 MW must procure at least 10% of its power from qualifying renewable generation in the applicable regional transmission organization, through a power-purchase agreement or similar mechanism rather than renewable-energy credits alone. over 50 megawatts

  • On-site energy-generation systems serving normal operations are treated as a separate principal use and require applicable approvals; they may be on the same property only under the specified shared-ownership and operation conditions. Peak shaving or supplying power to the grid is prohibited unless specifically approved. separate principal use

  • Substations or energy-generation systems abutting a nonindustrial zoning boundary or a property with a Sensitive Receptor must be at least 500 feet from the property line. Substations also face siting and screening rules, and on-site power lines of 34.5 kV or less must be buried. set back a minimum of 500 feet

  • For a data center over 100,000 square feet or one using an on-site substation, the applicant must hold an advertised public meeting at least 14 days before the first conditional-use hearing and maintain a public project website from at least two weeks before that meeting through final land-development approval. at least fourteen (14) days prior

  • Water-based cooling must use a closed-loop system; open-loop, once-through, and water-intensive evaporative cooling are prohibited, subject to a possible alternative demonstrated to use less water and energy. Applicants must document public-water service and capacity, and groundwater, springs, or direct surface-water withdrawals cannot be proposed as sources. closed-loop water system

  • Applicants must document wastewater needs, public-system treatment and conveyance capacity, and compliance with industrial pretreatment requirements. HVAC or closed-loop-system water may not be discharged through the public wastewater system, and untreated wastewater may not be discharged to stormwater systems, surface waters, aquifers, tanks, or wells. shall not be permitted to be discharged

  • A professionally prepared Thermal Impact Mitigation Plan addressing heat sources, off-site effects, mitigation, and feasible heat reuse is required with the conditional-use application and may require supplemental plans before approval. Thermal Impact Mitigation Plan

  • Applicants must submit pre-construction noise and vibration studies and post-construction studies within 180 days after operations begin. Noise limits vary by adjoining land use and time of day; noncompliance or inconclusive results can require a corrective plan and remediation, and the Borough may require further testing or interim mitigation. within 180 days

  • The application must include a professional plan or report on compliance with air-pollution laws; six months after operations begin, the operator must submit an air-pollution and plume study, and annual testing and reporting are required thereafter. Six (6) months after

  • Diesel generators must meet EPA Tier 4 standards and undergo annual testing. Fossil-fuel emergency generators may be used only during an emergency outage or for maintenance/readiness testing capped at 100 hours per year; routine tests are limited to weekdays from 9 a.m. to 3 p.m. capped at 100 hours per year

  • A professionally prepared Emergency Response Plan, acceptable to the Borough’s fire department and emergency-management services, is required. It must address emergency effects, fire response, evacuation, responder training, annual fire inspections, and emergency-radio coverage; specified battery-storage facilities must meet NFPA 855 or similar standards. Emergency Response Plan

  • The application must include an Electronic Waste Plan for safe removal, recycling, or disposal of servers, hazardous materials, batteries, and related products when equipment is updated or decommissioned. Electronic Waste Plan

  • Data-center sites must provide boundary buffers and screening. Minimum vegetative buffers vary by building footprint: 100, 150, or 300 feet along specified street frontages and lines near residences or Sensitive Receptors, with 50-foot buffers along other specified property lines; enhanced berms are also required in certain locations. minimum 300-foot vegetative buffer yard

  • Lighting is subject to shielding and spill limits, including a maximum 0.1 footcandle at residential uses and 0.5 footcandle at nonresidential uses. LED sources may not exceed 3000K, luminaires may not be mounted more than 20 feet above grade, and parking and traffic-way lighting must generally be extinguished within 30 minutes after closing. 0.1 footcandle

  • Parking must provide one space per employee on the largest shift plus five visitor spaces; the Borough may require an additional 25% of required spaces to be held in reserve. one parking space

  • A decommissioning plan is required, and decommissioning must begin within one year after operations cease or abandonment is noticed and generally be completed within 18 months after it begins. Before construction permits issue, the owner, operator, or developer must post financial security, maintain it, update its cost estimate every five years, and enter into a decommissioning agreement. within 1 year

  • The applicant or operator must bear specified costs, including required professional studies and testing, responder training, annual fire-safety inspections, and Borough review and preparation of decommissioning estimates and agreements. at the sole expense

  • Violations of required plans, limits, or operating requirements can trigger zoning enforcement after written notice and a 30-day opportunity to cure. Required compliance documents must be supplied within 10 days of a Borough request. thirty (30) day opportunity to cure

Benefits & exceptionsHide benefits & exceptions4
  • Data centers may be built in Limited Industrial districts through conditional-use approval, subject to the ordinance’s requirements. permit data centers by conditional use in the Limited Industrial Districts

  • The ordinance recognizes data-center accessory facilities—including cooling, security, storage, utility infrastructure, and temporary backup generators—as part of the data-center use when located on the same tract or on adjacent parcels developed as a unified project. Data Center Accessory Use

  • An energy-generation system may be located on the same property or campus as a data center if it is owned and operated by the same entity as the data center, with shared ownership maintained; it remains subject to applicable approvals and regulations. permitted upon the same property as a Data Center

  • Rooftop equipment may exceed the district’s maximum building height if fully screened and approved during conditional-use review. may exceed the applicable maximum district building height

Sources

current law · Chester Heights Borough
The standards were set by Ordinance No. 227, which Borough Council adopted on October 5, 2026.Chester Heights Borough, Delaware County — data-center ordinance (No. 227)

What this means

The measure imposes setbacks from homes or other protected places, minimum site-size requirements and cooling and water-use rules. Data centers still have an approval route, but the siting or operating limits significantly narrow feasible projects.

Restrictions & requirementsHide restrictions & requirements30
  • Conditional use in the Limited Industrial Districts only, § 185-81G

  • Building coverage limited by the district area regulations of § 185-82; no footprint or megawatt cap, § 185-81G(2)(e)

  • Data center campus defined and permitted as one conditional use, § 185-4 and § 185-81G

  • 55 dBA day and 45 dBA night at residential property lines; day limit above 50 dBA, § 185-81G Table 2

  • Section 185-81Gi(4), with Table 6, treats an increase of 3 dBA or more above the baseline ambient level documented before construction as a violation, measured with a Type 1 or Type 2 ANSI meter, but the baseline is not defined as L90 and no floor is set below which the cap does not apply.

  • 70 dBC day and 60 dBC night, above the 60 and 55 dBC standard, § 185-81G Table 3

  • Pre-construction study with the application and as-built study within 180 days of operation; none at building permit, § 185-81Gi(2)

  • Vibration study with numeric PPV and 65 VdB limits; no standard of none perceptible past the property line, § 185-81Gi(2)(c)

  • Public water only, with utility capacity confirmation; wells, springs, and surface withdrawals barred, § 185-81Gg(2)-(3)

  • Closed-loop required; open-loop, once-through, and evaporative cooling prohibited, § 185-81Gg(1)

  • Utility must confirm capacity for the proposed demand; no use cap, reporting, or drought plan, § 185-81Gg(2)

  • Wastewater plan including HVAC and closed-loop water, certified by the sewer authority with the conditional use application, § 185-81Gg(4)

  • Diesel generators must meet EPA Tier 4, with annual testing and emissions reports, § 185-81Gf(1)-(2) and j(3)

  • Thermal Impact Mitigation Plan including waste heat reuse evaluation, § 185-81Gh.

  • Electronic Waste Plan for servers, batteries, and hazardous materials; refrigerants in decommissioning, § 185-81Gl and p(4)(b).

  • Utility interconnection documentation with the application; no third-party electrical inspection, § 185-81Gd(1)(f)

  • Energy Usage Plan required; rooftop solar is listed as an effort to document, not a requirement, § 185-81Gd(1)

  • On-site generation is a separate principal use with a 500-ft setback where it abuts non-industrial zones or sensitive receptors, § 185-81Ge(1) and e(6).

  • Substations at the side or rear and screened; on-site lines of 34.5 kV and below buried, § 185-81Ge(3)-(5)

  • Vegetative buffer of 100 to 300 ft along lines within 500 ft of homes or sensitive receptors, § 185-81Go(5).

  • Equipment screened, rooftop on four sides, with acoustical barriers; no 12-ft standard and ground screening only from roads in industrial areas, § 185-81Gi(1) and o(4)

  • Elevations and renderings of facades visible off-site required, § 185-81G(3)(h)

  • Plan reviewed by the fire department, radio coverage, and 24-hour contact sign; no annual updates, § 185-81Gk(1)-(3)

  • Hazardous materials disposal addressed in the waste and decommissioning plans; no storage setbacks or containment, § 185-81Gl and p(4)(b)

  • Annual fire safety inspections at the applicant's expense; no third-party electrical inspection, § 185-81Gk(1)(e)

  • Security of net decommissioning cost plus 10% and closure notice, but removal may take up to 18 months after a one-year start, § 185-81Gp(2)-(5)

  • One as-built noise study and a six-month air study, with annual emissions reports; no ongoing noise, water, or power reporting, § 185-81Gi(2)(c) and j(2)-(3)

  • Plan violations treated as zoning violations under the general enforcement article, § 185-81Gq

  • Borough review of studies allowed; applicant pays only for review of decommissioning estimates, § 185-81Gp(5)(g)

  • Public meeting 14 days before the conditional use hearing and a project website through final approval; meeting not tied to planning commission review, § 185-81G Public Engagement (1)

Benefits & exceptionsHide benefits & exceptions1
  • Approval pathway: Conditional use in the Limited Industrial Districts

Sources