Cherrytree Township
This restriction takes precedence for the map color while in effect.
Anti-Data Center Policies
Cherrytree Township has enacted a temporary pause on covered data-center applications or development while it prepares new rules; this is not a permanent ban.
Rating from Pennsylvania statewide as there are no scored current or future laws outside temporary restrictions for Cherrytree Township.
Incentives
Financial Incentive2
Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.
Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.
current law · Cherrytree TownshipThe supervisors declared the zoning ordinance substantively invalid for data centers and adopted Resolution No. 26-44, imposing a limited moratorium while a curative amendment is prepared.Cherrytree Township, Venango County — data-center moratorium / curative resolution 26-44 (2026-06-01)
What this means
The measure pauses covered data-center applications or development while new rules are prepared. That stops affected projects from moving ahead during the pause, even though it is not a permanent ban.
Timing
The supervisors declared the zoning ordinance substantively invalid for data centers and adopted Resolution No. 26-44, imposing a limited moratorium while a curative amendment is prepared.
Sources
pending · Cherrytree TownshipThe draft is a curative amendment and comprehensive zoning update that follows Resolution No. 26-44 of June 1, 2026, and the Board of Supervisors will hold its public hearing on November 2, 2026 at 5:30 p.m., with a vote on the ordinance listed on the agenda of its 6:00 p.m. meeting that evening.Cherrytree Township, Venango County — proposed data-center ordinance (None Adopted)
What this means
The proposal would impose money set aside for eventual removal and noise limits and sound testing. Data centers can still be approved, but these obligations meaningfully increase construction, compliance or review costs.
Restrictions & requirementsHide restrictions & requirements1
Conditional use reviewed and decided by the Board of Supervisors under Article VI; no one-year expiration of approval, Section 3
Benefits & exceptionsHide benefits & exceptions1
Proposed approval pathway: Proposed: conditional use in the C/L Commercial/Light Industrial Overlay District
Sources
Thank you to the Pennsylvania Data Center Ordinance Tracker for providing proposed local ordinance data for PA. Citation: padatacenterordinances.org, accessed November 3, 2026.Cookie preferences · Report missing data