Centre Township

Anti-Data Center Policies

Pennsylvania requires data centers over 25 megawatts to obtain local approvals and meet power, grid-cost, environmental, and community commitments; covered facilities also face annual energy and water reporting. These rules make large projects harder, not impossible, while eligible centers may receive equipment tax breaks.

Rating and summary from Pennsylvania statewide as there are no scored current or future laws outside temporary restrictions for Centre Township.

Incentives

Financial Incentive

Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.

pending · Centre Township
The draft, an unnumbered amendment to the 2004 Zoning Ordinance with blank enactment lines, was provided by the township office on October 26, 2026, and the October 27, 2026 Supervisors agenda lists a motion to advertise it for a public hearing at the November Supervisors meeting.Centre Township, Berks County — proposed data-center ordinance (None Adopted)

What this means

The proposal would impose setbacks from homes or other protected places, minimum site-size requirements and cooling and water-use rules. Data centers still have an approval route, but the siting or operating limits significantly narrow feasible projects.

Restrictions & requirementsHide restrictions & requirements30
  • Special exception in the LI Limited Industrial District only, § 405.3.T

  • Section 405.3.T(1)(k) requires 1,000 ft from any data center on another property, and the Section 201 definition treats parcels in a single land development plan as one data center, but lots under common ownership or control filed separately are not regulated as one use.

  • Section 405.3.T(11)(a) sets 50 dBA day and 45 dBA night as 5-minute LAeq at residential and sensitive receiving properties, measured with a Type 1 meter under ANSI/ASA S1.13-2020 and S12.18-1994 by a qualified acoustical consultant.

  • 60 dBC day and 55 dBC night at residential and sensitive receivers, § 405.3.T(11)(a)

  • Section 405.3.T(12) requires a preliminary study with the special exception application, an interim study at building permit, and an as-built study within three months of occupancy, using ANSI S1.4-2014 meters.

  • Testing and maintenance capped at 50 hours per year; no weekday daytime limit, § 405.3.T(22)(c)

  • Public water required with water and hydrological studies; no pump test, § 405.3.T(16), (18), and (19)

  • Section 405.3.T(8) requires a closed-loop liquid-based cooling system and bars air cooling as the primary system, but it does not address evaporative heat rejection, limit its water use, or tie it to the noise limits.

  • Quantity of water required must be disclosed; no cap, reporting, or drought plan, § 405.3.T(18)

  • Cooling fluids and condensate removed off site and barred from sewer and stormwater; no discharge plan approval, § 405.3.T(8)

  • Containment of fire suppression water and cooling fluids only; no general stormwater standards, § 405.3.T(8)-(9)

  • Natural gas generators must meet state and federal air rules; annual reports only if the Board requires, § 405.3.T(22)-(23)

  • General limit on heat under applicable law only, § 405.3.T(24)

  • Electronic Waste Plan for servers, hazardous materials, and batteries, § 405.3.T(21).

  • Utility interconnection agreement showing capacity with the application; no electrical inspection, § 405.3.T(20).

  • Energy Usage Plan and 10% renewable procurement above 50 MW; rooftop solar only as a documented effort, § 405.3.T(15)

  • Only backup generators addressed

  • Substations part of the use, located in the rear yard, and screened; no buried lines, § 405.3.T(1)(i) and (29)(b)

  • Known impacts on electric rates must be noted, § 405.3.T(20)

  • Berm and dense planted buffer next to residential districts and uses; no width set, § 405.3.T(29)(c)

  • Ground and rooftop equipment screened with noise mitigation; no height standard, § 405.3.T(29)(b)

  • Emergency Response Plan approved by the fire chief and emergency contacts given to 911; no annual update or radio coverage, § 405.3.T(2) and (28)

  • Section 405.3.T(6) and (7) require annual training for fire and EMS personnel at the operator's expense and specialized equipment provided to the local fire and EMS providers, but training is not required before occupancy and the equipment is not kept on site.

  • Secondary containment for cooling fluids and battery spills; no storage setbacks, § 405.3.T(8)-(9)

  • Secondary emergency access required; no road class requirement, § 405.3.T(4)

  • Section 405.3.T(30) requires security of at least 125 percent of net decommissioning cost, a utility agreement to report a 50 percent drop in consumption, and removal of equipment, batteries, and generators within six months, but the agreement is not recorded and buildings are not required to be removed unless reused within two years.

  • One as-built noise study after opening; generator reports only if the Board requires, § 405.3.T(12)(c) and (22)(g)

  • Violations must be promptly remediated; no specific penalties, § 405.3.T(12)(c)

  • Applicant pays for its own noise studies; no township expert review

  • Emergency contact information only after approval; no developer or operator disclosure before approval, § 405.3.T(28)

Benefits & exceptionsHide benefits & exceptions1
  • Proposed approval pathway: Proposed: special exception in the LI Limited Industrial District

Sources

Thank you to the Pennsylvania Data Center Ordinance Tracker for providing proposed local ordinance data for PA. Citation: padatacenterordinances.org, accessed November 3, 2026.Cookie preferences · Report missing data