Cecil Township
Anti-Data Center Policies
Pennsylvania requires data centers over 25 megawatts to obtain local approvals and meet power, grid-cost, environmental, and community commitments; covered facilities also face annual energy and water reporting. These rules make large projects harder, not impossible, while eligible centers may receive equipment tax breaks.
Rating and summary from Pennsylvania statewide as there are no scored current or future laws outside temporary restrictions for Cecil Township.
Incentives
Financial Incentive
Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.
pending · Cecil TownshipThe Board of Supervisors declared its zoning invalid as exclusionary of data centers on August 3, 2026 and posted the unnumbered draft on October 28, 2026 for a workshop on November 4, 2026, and no hearing date has been confirmed.Cecil Township, Washington County — proposed data-center ordinance (Draft (Unnumbered))
What this means
The proposal would impose setbacks from homes or other protected places, minimum site-size requirements and noise limits and sound testing. Data centers still have an approval route, but the siting or operating limits significantly narrow feasible projects.
Restrictions & requirementsHide restrictions & requirements29
Conditional use decided by the Supervisors; approval expires if no occupancy, building, or grading permit application is filed within two years, Draft § 240-61.3A and § 240-13
Minor data centers limited to one building of 20,000 sq ft, and I-2 dimensional standards otherwise apply; no campus or megawatt cap for major data centers, Draft Section 1 and Draft § 240-61.3B
45 ft plus up to 15 ft of roof-mounted equipment (major) and 30 ft plus 10 ft (minor); rooftop equipment not counted in the height, Draft § 240-61.3B(2) and § 240-61.2B(2)
Air and water quality studies and a geotechnical report addressing environmental impact; no riparian buffer, Draft § 240-61.3J and L
LEQ limits of 50 dB daytime and 45 dB evening and nighttime at rural and low-density residential and sensitive receptor properties, with ANSI S1 and S12 measurement, Draft § 240-61.3E(3) and (5)
Pure tone limits by octave band at 32, 63, and 125 Hz and other frequencies, plus an unweighted peak limit, Draft § 240-61.3E(3)(d) and (e)
Sound modeling by ISO 9613-2 with the application and an as-built study six months after occupancy; no interim study or full-load requirement, Draft § 240-61.3E(7)
Generator tests may exceed limits only in daytime hours, including weekends, for one cumulative hour per week; weekend testing allowed, Draft § 240-61.3E(4)(e)
Vibration may not exceed ISO 2631-2 residential day criteria of 200 um/s RMS in any one-third octave band, with a vibration study, Draft § 240-61.3E(6) and (7)
Public water certification, and a hydrogeologic study with aquifer testing for nonpublic sources of 20,000 gpd or more; public water not mandated, Draft § 240-61.3F(2) to (5)
Water feasibility study must describe water used for cooling; no cooling method rule, Draft § 240-61.3F(4)(c)
Quarterly metered withdrawal reports for groundwater sources; no drought plan, Draft § 240-61.3H(4)
Water feasibility study must describe water recycled or discharged and by what means; no wastewater approvals required, Draft § 240-61.3F(4)(d)
Air quality study and one year of monitoring; no generator emission standard, Draft § 240-61.3J
Electronic Waste Plan for servers, batteries, and hazardous materials; no disposal contract, Draft § 240-61.3M
Battery storage must meet NFPA 855 with battery-specific fire suppression, Draft § 240-61.3K(2)
Known impacts on electric rates or availability must be noted; no upgrade cost or tariff terms, Draft § 240-61.3I(2)
50-ft landscape buffer next to residential districts and sensitive receptors, with dead plants replaced within 150 days; below 100 ft, Draft § 240-61.3C
Facades facing roads, residential districts, or homes need two of three design elements every 150 horizontal feet, Draft § 240-61.3N
Equipment within 1,000 ft of roads, residential districts, or sensitive receptors fully enclosed or fully screened; no height or acoustic standard, Draft § 240-61.3D
Emergency Response Plan reviewed and accepted by the fire department and emergency management services; no annual update or walk-through, Draft § 240-61.3K(1)
First responders must receive system-specific training; no applicant-delivered annual training or equipment, Draft § 240-61.3K(1)(d)
Electronic Waste Plan addresses storage and removal of hazardous materials; no storage setbacks or spill plan, Draft § 240-61.3M
ERP provides for annual fire safety inspections by a qualified professional; no report to a municipal official, Draft § 240-61.3K(1)(e)
Construction noise exempt only during daytime hours with noise controls; no haul routes or road bond, Draft § 240-61.3E(4)(f)
Decommissioning plan with 110 percent funds and completion within 18 months of closure; not recorded and beyond 6 months, Draft § 240-61.3Q
Quarterly reports on metered water withdrawals and groundwater levels, plus air and water monitoring reports at six and twelve months, Draft § 240-61.3H(4) and J(2)
As-built noise violation is a violation of the ordinance; general enforcement only, Draft § 240-61.3E(7)(b)
Pollutant studies by experts mutually agreed upon by the township and operator; consultant review cost not assigned, Draft § 240-61.3J(1)
Benefits & exceptionsHide benefits & exceptions1
Proposed approval pathway: Proposed: conditional use in the I-2 (major) and SD (minor) districts under a posted draft