Catawissa Township
Anti-Data Center Policies
Catawissa Township’s enacted ordinance restricts data centers to certain locations and minimum site sizes, and sets cooling and water-use rules; an approval route remains, but feasible projects are limited.
Incentives
Financial Incentive
Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.
current law · Catawissa TownshipThe Board of Supervisors adopted Ordinance 01-2026 unanimously at a public hearing on July 30, 2026, according to the township's August 11, 2026 meeting agenda and minutes.Catawissa Township, Columbia County — data-center ordinance (No. 01-2026)
What this means
The measure imposes minimum site-size requirements, limited eligible locations and cooling and water-use rules. Data centers still have an approval route, but the siting or operating limits significantly narrow feasible projects.
Restrictions & requirementsHide restrictions & requirements26
Section 4.1 establishes the Data Center Overlay District as shown on the Official Zoning Map, and Section 4.4 states that no Data Center shall be permitted outside the overlay.
50-ft building height; rooftop equipment to 65 ft, § 8
Environmental Impact Study required, § 9.I
Section 6.3 defines a Data Center Campus as buildings on a unified tract or assemblage of parcels under common ownership or control, Section 7.A permits the campus as one conditional use under one Master Plan (Section 9), and Section 8.G requires one mile between data centers on separate properties.
Section 7.E bars a later phase until prior phases comply, and Section 9.E requires the Energy Demand Analysis in the Master Plan to state projected electrical demand for each phase.
55 dBA day and 50 dBA night at the property line, § 9.C
Section 9.C requires preliminary, interim, and as-built noise studies, with measurements under ANSI S1.4-2014, but does not require the as-built study to be taken at full operating load.
0.1 in/sec PPV at property line with study, § 9.J
Monthly water use reporting; no drought plan, § 14
Cooling wastewater and discharge prohibited and certified, §§ 9.G, 11.A
DEP Chapter 102 and 105 stormwater plan, § 9.G
DEP and EPA standards; Tier IV only if required, §§ 9.E, 9.I
Heat plume mitigation plan; no reuse review, § 9.E
Utility capacity letters with application; no third-party inspection, § 10.E.
Substations screened from roads and neighbors, § 9.K
Required upgrades and responsibility disclosed, § 9.E
Landscaping and buffering plan; no width, § 9.K
Mechanical equipment screened, § 9.K
Emergency response plan; no annual update or radio, § 9.F
Hazardous materials management in emergency plan, § 9.F
Section 10.H lists a Traffic Impact Study among the required application contents but states no scope, so construction traffic and the study area are not addressed.
Work hours and truck routes; no road bond, § 13
Plan and security; no 110% or 6-month removal, §§ 9.M, 15
Security updated every 3 years, § 15
Continuous noise, monthly water, annual energy reports, § 14
Section 17 makes violations zoning violations enforced under the Zoning Ordinance and the MPC and states that approvals may be revoked, but gives no revocation grounds, notice, or hearing.
Benefits & exceptionsHide benefits & exceptions1
Approval pathway: Conditional use in a Data Center Overlay District