Carroll Township

Anti-Data Center Policies

Pennsylvania requires data centers over 25 megawatts to obtain local approvals and meet power, grid-cost, environmental, and community commitments; covered facilities also face annual energy and water reporting. These rules make large projects harder, not impossible, while eligible centers may receive equipment tax breaks.

Rating and summary from Pennsylvania statewide as there are no scored current or future laws outside temporary restrictions for Carroll Township.

Incentives

Financial Incentive

Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.

pending · Carroll Township
The data center section, new § 450-388, is part of proposed Ordinance No. 2026-258 (draft updated October 12, 2026), and the Board of Supervisors will hold a public hearing on November 2, 2026 at 5:30 p.m. and may consider adoption at the meeting that follows.Carroll Township, York County — proposed data-center ordinance (None Adopted)

What this means

The proposal would impose setbacks from homes or other protected places, minimum site-size requirements and cooling and water-use rules. Data centers still have an approval route, but the siting or operating limits significantly narrow feasible projects.

Restrictions & requirementsHide restrictions & requirements34
  • Riparian forest buffer of 100 ft on each side, wider on steep slopes and 25 ft more at wetlands, proposed § 450-388.R

  • Expansion over 10% in floor area or electrical load, added generators, or changed cooling requires a new conditional use, proposed § 450-388.S.

  • Proposed Section 450-388.H(1)(a) sets 50 dBA day and 40 dBA night at the boundary of property containing a Sensitive Receptor, but no metric, meter class, or procedure is stated for these limits; the Type 1 meter requirement in Section 450-388.H(6)(c) applies only to the low-frequency limits.

  • Proposed Section 450-388.H(1)(c) bars levels more than 10 dBA above pre-development ambient, but the ambient is not defined as L90, no measurement method is stated, and no floor is set below which the cap does not apply.

  • 55 dBC at the property line of sensitive receptors at all times, proposed § 450-388.H(6)

  • Proposed Section 450-388.H(12) requires preliminary, interim, and as-built studies (six months after occupancy and every 5 years) by a third-party acoustical expert, but no measurement standard is stated and the as-built study is not required at full operating load.

  • Generator testing only on weekdays from 9:00 a.m. to 3:00 p.m.; no hours cap, proposed § 450-388.I(5)(a)

  • Vibration studies and anti-vibration mounts; no numeric or perceptibility standard, proposed § 450-388.H(7) and H(9)

  • Must be served exclusively by public water, with a water resources study, proposed § 450-388.J(1) and J(3)

  • Once-through and high-loss potable evaporative cooling prohibited; closed-loop or other low-water systems required, proposed § 450-388.L.

  • Quarterly reporting of daily water use; no drought response plan, proposed § 450-388.J(6)

  • Proposed Section 450-388.J(4) requires the applicant to demonstrate adequate disposal of domestic, cooling, and industrial wastewater and states that discharge must be approved by the Dillsburg Area Authority, PA DEP, and SRBC, but it does not require those approvals before the zoning permit.

  • Annual diesel generator testing reports to confirm emissions within permitted limits and air permits before occupancy; no EPA Tier 4, proposed § 450-388.I(5)(c) and I(7)

  • Heat island impacts must be disclosed in the impact analysis; no waste heat reuse review, proposed § 450-388.O(5)

  • Decommissioning plan for removal of electronic equipment, cooling equipment, and batteries; no recycling or refrigerant plan, proposed § 450-388.U(1)

  • Provider capacity certification with the application and verification before occupancy; no third-party electrical inspection, proposed § 450-388.I(1) and I(8).

  • Capacity certification of load and peak demand, with rooftop or parking lot solar required, proposed § 450-388.I(8) and I(9).

  • Energy generation supplying the data center must meet the ordinance as though it were the principal use, proposed § 450-388.I(9).

  • Substations screened with a 10-ft opaque screen and placed to the side or rear, and on-site lines of 34.5 kV or less buried, proposed § 450-388.I(10)

  • Required grid upgrades and rate impacts disclosed and mitigated to the township's satisfaction; payment by applicant not required, proposed § 450-388.I(8)

  • 300 ft of green space with a 50-ft landscape screen and 15-ft berm along residential uses, proposed § 450-388.G

  • Low-reflective earth tone colors, no fluorescent or metallic colors, foundation plantings, and Board approval of the facade, proposed § 450-388.B.

  • Acoustical screening of rooftop equipment and four-sided acoustical barriers next to homes; no 12-ft minimum height for ground equipment, proposed § 450-388.C and H(4)

  • Building elevation renderings required with the conditional use submission, proposed § 450-388.B

  • Emergency Response Plan reviewed by the fire department, radio coverage, and 24-hour contact signs; no annual plan updates, proposed § 450-388.N

  • Applicant must show the fire department will have adequate equipment and training, and fiscal mitigation of emergency service costs, proposed § 450-388.N(4) and V(5).

  • Double-walled fuel storage with secondary containment and SPCC plans; no storage setbacks, proposed § 450-388.I(7)

  • Annual fire safety inspections; no third-party electrical inspection, proposed § 450-388.N(2)(f)

  • Trip generation described in the impact analysis; no traffic impact study, proposed § 450-388.O(1)

  • Developer must maintain and repair township roads used by construction traffic; no work hours, haul routes, or bond, proposed § 450-388.V(1)

  • 110% financial security and immediate notice of cessation; removal within 12 months, proposed § 450-388.U(2)-(4)

  • Quarterly wastewater and water use reports and as-built sound studies every 5 years, proposed § 450-388.J(6) and H(12)

  • Proposed Section 450-388.T sets civil penalties of up to $800 per violation per day and allows suspension of permits or revocation of conditional use approval, but no notice and hearing precede revocation and MPC Sections 616.1 and 617.2 are not cited.

  • Owner pays for the Township Engineer's review of decommissioning estimates; no applicant-funded review of other studies, proposed § 450-388.U(2)

Benefits & exceptionsHide benefits & exceptions1
  • Proposed approval pathway: Proposed: conditional use in the I Industrial Zone

Sources

Thank you to the Pennsylvania Data Center Ordinance Tracker for providing proposed local ordinance data for PA. Citation: padatacenterordinances.org, accessed November 3, 2026.Cookie preferences · Report missing data