Carbondale Township

Anti-Data Center Policies

Pennsylvania requires data centers over 25 megawatts to obtain local approvals and meet power, grid-cost, environmental, and community commitments; covered facilities also face annual energy and water reporting. These rules make large projects harder, not impossible, while eligible centers may receive equipment tax breaks.

Rating and summary from Pennsylvania statewide as there are no scored current or future laws outside temporary restrictions for Carbondale Township.

Incentives

Financial Incentive

Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.

pending · Carbondale Township
The October 1, 2026 public hearing draft was the subject of a public hearing on October 1, 2026, the township confirmed on October 22, 2026 that it has not been adopted, and the Supervisors' agenda listed the November 5, 2026 meeting for consideration of adoption.Carbondale Township, Lackawanna County — proposed data-center ordinance (None Adopted)

What this means

The proposal would impose extra site and approval requirements. These add a modest compliance burden without clearly preventing otherwise eligible projects.

Restrictions & requirementsHide restrictions & requirements35
  • Conditional use before the Supervisors; approval expires after 24 months when land development is required, Sections 567.1 and 732.7.

  • Section 564.101 and 564.102 require 1,000 ft from the nearest residential district boundary or sensitive receptor lot line to the exterior walls of any principal or accessory building and to any ground-mounted equipment of 200 cubic feet or more, including cooling, ventilation, and power equipment and all substations and generators.

  • 150 ft riparian buffer and floodplain exclusion; no wider buffer on steep slopes, Section 749.4

  • Section 749.1001(f) requires the developer's agreement to describe the timing and sequencing of development and a timeline for each phase, but it does not state the electrical demand of each phase, and no provision requires a new approval for added capacity.

  • Section 6154.303 and Table 1 set 55 dBA daytime and 45 dBA quiet-hour limits at residential receiving lot lines, reduced by 5 dB only when the source qualifies as cyclical, steady, or tonal noise.

  • Article 2 defines steady or tonal noise more than 5 dBA above the background sound level as noise pollution, with background measured by a sound level meter over at least five minutes, but no L90 statistic is stated and no floor sets a level below which the cap does not apply.

  • 50 dBC day and 40 dBC night at residential lot lines, Section 6154.303

  • Section 565.203 requires preliminary, interim, and post-construction sound studies by an acoustical expert using sound level meters meeting ANSI S1.4-2014, and Section 565.203(a) to (c) require annual compliance testing with the facility operating at maximum design heat rejection load and computing capacity.

  • Generator testing only 9 a.m. to 5 p.m. on weekdays; no hours cap, Section 749.902

  • Water feasibility study approved by the Township Engineer and DEP, Section 565.201

  • Water-use management plan and closed-loop systems only where feasible, Section 565.104

  • Water-use management plan required; no cap or drought plan, Section 565.104

  • Section 565.201(c) requires every data center application to include a verification letter showing adequate capacity for the discharge of industrial wastewater, including cooling water, approved by the Township Engineer, Sewage Enforcement Officer, and DEP, and approval is not granted until the providers confirm capacity.

  • Stationary diesel generators must meet EPA Tier 4 Final; no annual emissions testing, Section 565.104

  • Heat must not be perceptible beyond the lot line; no waste heat reuse review, Section 565.104

  • Decommissioning plan requires proper disposal of electronic equipment and batteries, Section 749.703

  • Electric utility capacity letter and will-serve letters required before zoning approval; no electrical inspection, Section 565.201.

  • Ancillary power generation is a separate conditional accessory use with generator setbacks, Sections 4.5 and 749.902.

  • Substations screened and set back with other ground equipment, Sections 564.1 and 564.205

  • Building-mounted battery systems must meet NFPA 855, with monitoring and alarms, Section 749.802

  • Buffer yards of 30 to 80 ft, Section 564.202

  • Outdoor lighting must be shielded and meet illumination limits, Section 749.3

  • Facade articulation required for every 200 ft of wall length, Section 565.102.

  • Ground equipment screened by opaque barriers and rooftop equipment screened on all sides; no 12 ft height, Section 564.205

  • Graphic renderings required at the applicant's public meeting; no visual impact study, Section 749.601

  • 24-hour emergency contact signage and annual fire department inspections; no emergency plan review, Sections 749.103 and 749.1001

  • Applicant must provide first responder training and is encouraged to fund equipment, Section 749.603

  • Types of materials stored on site must be disclosed, Section 565.204

  • Annual fire department inspections required, Section 749.1001

  • Section 565.202 requires a traffic impact study for all data center applications, describing construction stages and operation, but the study area is the immediate vicinity of the site and is not required to reach the nearest arterial or interchange the trucks will use.

  • Security of 110% of removal cost and immediate notice, but 18 months allowed for removal, Sections 749.701 to 749.708

  • Annual operational noise compliance report, Section 565.203

  • Section 567.3 provides civil judgments of up to $5,000 per violation per day, and Section 565.203(d)(4) suspends or revokes the operating permit after 90 days of noise noncompliance, but revocation is not preceded by notice and a hearing and Sections 616.1 and 617.2 of the Municipalities Planning Code are not cited.

  • Section 567.105 requires the applicant to pay all land development application fees and engineer review fees for a data center before final approval, and Section 565.203(b) has a municipality-selected acoustical consultant funded by the operator's escrow.

  • Entrance signage must name the operating company and owner, Section 749.103

Benefits & exceptionsHide benefits & exceptions1
  • Proposed approval pathway: Proposed: conditional use in the Energy and Information Technology Overlay

Sources

Thank you to the Pennsylvania Data Center Ordinance Tracker for providing proposed local ordinance data for PA. Citation: padatacenterordinances.org, accessed November 3, 2026.Cookie preferences · Report missing data