Buck Township

Anti-Data Center Policies

Buck Township’s enacted ordinance requires setbacks from homes and other protected places, plus noise limits and sound testing. Data centers can still seek approval, but these limits narrow where and how they can operate.

Incentives

Financial Incentive

Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.

current law · Buck Township
The standards are in Sections 5.930 to 5.935 of Ordinance No. 6-2026, which replaced the December 2025 zoning ordinance and which the posted signed copy shows the Board of Supervisors adopted on June 16, 2026.Buck Township, Luzerne County — data-center ordinance (Ordinance No. 6-2026)

What this means

The measure imposes setbacks from homes or other protected places and noise limits and sound testing. Data centers still have an approval route, but the siting or operating limits significantly narrow feasible projects.

Restrictions & requirementsHide restrictions & requirements26
  • Conditional use heard and decided by the Board of Supervisors; no lapse period for the approval, Sections 5.310 and 5.933.b

  • Schools and parks named in the purpose statement only; no setback, Section 5.931.a

  • Copies of PNDI, NEPA, and PHMC documents where required by other agencies; no riparian buffer or impact assessment, Section 5.935.g

  • Five-year plan of additional facilities only; no expansion triggers, Section 5.934.c

  • Single 50 dBA limit at the property line with no stated method, Section 5.935.j; octave-band standard of Section 6.430 cross-referenced

  • Section 6.430 octave-band limits, cross-referenced in Section 5.934.b(11), use older bands (20 to 75, 75 to 150 Hz) rather than the 31.5, 63, and 125 Hz bands; no dBC limit

  • Noise description by a professional engineer with the application; no measured study after opening, Section 5.934.b(11)

  • Vibration detectable without instruments barred at the property line; no study required, Section 5.935.l

  • Public water supplier documentation or a water feasibility study, plus DRBC approval of withdrawals, Sections 5.934.b(13) and 6.450

  • Closed-loop cooling encouraged only, Section 6.450.a

  • Projected water demand disclosed only if the Township requires a feasibility study for a non-public source, Section 6.450.c

  • Erosion control and stormwater applications must be filed before approval under base requirements, Section 5.935.n

  • Tier IV diesel certified generators; no annual emissions testing or reports, Section 5.934.b(14)(c)

  • Substations counted as accessory uses and on-site lines underground to the maximum extent possible; no substation screening or placement, Article 11 and Section 5.932.c

  • Known impacts on electric rates and availability must be noted; no upgrade costs or service agreement, Section 5.934.b(14)(a)

  • Landscaping to screen and buffer the data center under Section 4.700; no width stated, Section 5.935.m

  • Landscape screening of the data center and generator enclosures; no height or all-sides standard, Sections 5.935.m and 5.934.b(14)(c)

  • Emergency services plan provided to the fire company for review and comment, with a posted 24-hour contact; no annual update, Sections 5.935.o and 5.935.p

  • Bulk fuel storage must meet county Section 508 and Section 6.410; no spill plan filed, Section 5.934.b(14)(d)

  • Professional certification of compliance within 90 days of operation; no annual inspection, Sections 5.934.d and 5.935.f

  • Route of travel plan only; no traffic impact study, Section 5.935.d(2)

  • Construction haul route plan and an optional road bond; no construction hours, Section 5.935.d(2)-(3)

  • Definition includes cryptocurrency mining and server farms but not artificial intelligence; incidental computer rooms exempt without a size or power limit, Article 11

  • Unresolved violation after 30-day notice is grounds for revoking the permit, with no hearing; general enforcement with a $500 judgment, Sections 5.935.p and 9.530

  • Hearing notice must say information is on the Township website; no applicant meeting or project website, Section 5.933.b(1)

  • Owner and applicant named, and changes in owner or operator reported within 90 days; no end user, Sections 5.934.b(1) and 5.934.e

Benefits & exceptionsHide benefits & exceptions1
  • Approval pathway: Conditional use in the I-1 Manufacturing District

Sources

Thank you to the Pennsylvania Data Center Ordinance Tracker for providing proposed local ordinance data for PA. Citation: padatacenterordinances.org, accessed November 3, 2026.Cookie preferences · Report missing data