Borough of Bridgeport

Anti-Data Center Policies

Bridgeport Borough’s enacted ordinance allows data centers but requires noise limits and testing, setbacks from homes and other protected places, and limits on backup generators or on-site power, adding compliance and review costs.

Incentives

Financial Incentive

Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.

current law · Bridgeport Borough
The current rules are in Ordinance 2026-005, which Borough Council adopted on July 21, 2026.Bridgeport Borough, Montgomery County — data-center ordinance (No. 2026-005)

What this means

The measure imposes noise limits and sound testing, setbacks from homes or other protected places and limits on backup generators or on-site power. Data centers can still be approved, but these obligations meaningfully increase construction, compliance or review costs.

Restrictions & requirementsHide restrictions & requirements22
  • Environmental impact analysis required, § 560-1913.6.F

  • Added parcels require new conditional use; no capacity rule, § 560-1913.4.J

  • Day and night limits of ambient plus 3 dB(Z); no dBA limits, § 560-1913.4.D

  • Section 560-1913.4.D caps noise at 3 dB(Z) above the Daytime or Nighttime Ambient Sound, which Section 560-1913.3.I and J define as the average level measured with a Class 1 meter at five perimeter points over two weeks.

  • Infrasound assessment required; no dBC limit, § 560-1913.6.F

  • Section 560-1913.6.G requires a prospective study with the conditional use application and Section 560-1913.7.C requires an as-built study six months after occupancy, both using ANSI S1.4-2014 meters (Section 560-1913.7.C(4)).

  • None perceptible past property lines, with vibration study, § 560-1913.4.D and 6.G.

  • Public water required; private wells barred including cooling, § 560-1913.4.C

  • Anticipated water usage disclosed, § 560-1913.4.C

  • Public sewer with flows and capacity shown; no cooling discharge plan, § 560-1913.4.C

  • Servers, storage, and batteries removed at closure; no recycling plan, § 560-1913.4.I

  • Utility approval and interconnection agreement before construction; no inspection, § 560-1913.7.D

  • 100-ft planted screening buffer around buildings, § 560-1913.4.A.

  • Softening buffer at facades only, § 560-1913.4.A

  • Roof equipment screened; no 12-ft or acoustic rule, § 560-1913.4.A

  • Emergency plan approved by emergency coordinators; no annual update, § 560-1913.7.A

  • Section 560-1913.6.D requires a traffic impact analysis with every conditional use application, covering traffic during construction and after operation begins on all roadways, intersections, and interchanges within at least a two-mile radius, with likely truck routes.

  • Construction traffic studied only; no hours, routes, or bond

  • Plan and agreement, 18-month removal; no financial security, § 560-1913.4.I

  • As-built study and noise monitoring on request every 6 months, § 560-1913.7.C

  • Borough-selected woodland study at applicant cost only, § 560-1913.7.B

  • Studies posted on Borough website 30 days before hearing, § 560-1913.5.C

Benefits & exceptionsHide benefits & exceptions1
  • Approval pathway: Conditional use in the GIC General Industrial Commercial District

Sources

Thank you to the Pennsylvania Data Center Ordinance Tracker for providing proposed local ordinance data for PA. Citation: padatacenterordinances.org, accessed November 3, 2026.Cookie preferences · Report missing data