Borough of Briar Creek

Anti-Data Center Policies

Pennsylvania requires data centers over 25 megawatts to obtain local approvals and meet power, grid-cost, environmental, and community commitments; covered facilities also face annual energy and water reporting. These rules make large projects harder, not impossible, while eligible centers may receive equipment tax breaks.

Rating and summary from Pennsylvania statewide as there are no scored current or future laws outside temporary restrictions for Borough of Briar Creek.

Incentives

Financial Incentive

Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.

pending · Briar Creek Borough
The undated draft, referred to by the borough as Ordinance 202-2026, has not been adopted and was listed under the solicitor's report on the October 28, 2026 Council work session agenda, and on October 20, 2026 the borough said no public hearing date had been set.Briar Creek Borough, Columbia County — proposed data-center ordinance (None Adopted)

What this means

The proposal would impose setbacks from homes or other protected places, cooling and water-use rules and noise limits and sound testing. Data centers still have an approval route, but the siting or operating limits significantly narrow feasible projects.

Restrictions & requirementsHide restrictions & requirements35
  • Allowed only in the I District, which excludes agricultural districts; no preserved farmland or agricultural security area bar, Section 3

  • 45-ft limit including rooftop equipment, § 27-438.1.E

  • Environmental Impact Assessment covering riparian buffers, streams, and wetlands; no riparian buffer width, § 27-438.1.M(6)

  • Section 27-438.1.R requires separate approval for any expansion, intensification, change in capacity or cooling technology, increase in water or energy demand, or added accessory infrastructure, but it does not exempt like-for-like replacement.

  • 60 dBA weekday day and 55 dBA night and weekend at the property line, with 45 dBA at night at sensitive receptor lines; day limit above 50 dBA, § 27-438.1.G(1)

  • Low-frequency noise to be limited by design; no numeric limit or study, § 27-438.1.G(1)

  • Section 27-438.1.G(1)(a) to (c) require preliminary, interim, and as-built sound studies using ANSI S1.4 meters, with the as-built study six months after occupancy, but the as-built study is not required at full operating load.

  • Generator testing allowed as industry standards require; no hours limit, § 27-438.1.G(2)

  • Vibration study showing no vibration perceptible beyond the property line, § 27-438.1.H(3).

  • Water feasibility study for nonpublic sources with wells within 2 miles and safe yield, and public lines must be pursued before aquifer withdrawals; no pump tests, § 27-438.1.L(3), (4), and (7)

  • Closed-loop cooling required, but release through cooling towers allowed, § 27-438.1.L(1)

  • Analysis of the quantity of water required; no cap, usage reporting, or drought plan, § 27-438.1.L(2) and (4)

  • Section 27-438.1.L(9) requires the applicant to show that disposal of domestic wastewater and cooling or industrial discharge has been provided and approved by the Sewage Enforcement Officer, Municipal Authority, SRBC, or DEP, but it does not state that the approval must be in hand before the zoning permit.

  • Stormwater practices and SALDO compliance required; no added standard, § 27-438.1.B and D(2)

  • Tier 4 or greater generators required; no emissions testing or reports, § 27-439.2

  • Heat may not be perceptible beyond the property line and heat impacts assessed; no waste heat plan, § 27-438.1.H(1) and M(6)

  • Decommissioning plan must cover removal of electronic waste and disposal of batteries, fuel, and refrigerants, § 27-438.1.T(1) and (2).

  • Utility certification of capacity and an interconnection agreement with the application, and third-party electrical inspection before occupancy, § 27-438.1.K(3) and (4)

  • Generation supplying the data center in normal operation is a separate use requiring separate approval, § 27-438.1.K(2) and § 27-439.1.

  • Battery storage must meet NFPA 855 and UL 9540 with automatic lithium-ion fire suppression, § 27-440.C(2) and I(9).

  • Section 27-438.1.K(3)(a) requires an interconnection agreement with the electric service provider, K(3)(b) to (e) require evidence that capacity and infrastructure are sufficient, and K(3)(f) makes the applicant pay for needed upgrades, but the upgrades and their cost are not required to be disclosed.

  • Vegetative buffer around the entire perimeter; no 100-ft width, § 27-438.1.N

  • Year-round vegetative buffering to screen the facility; no equipment screening height or acoustic screening, § 27-438.1.N

  • Line-of-sight siting goal only; no visual study, renderings, or elevations, § 27-438.1.D(2)

  • Emergency Response Plan accepted by the fire department, radio coverage, and 24-hour contact signage; no annual updates, § 27-438.1.J

  • Types and storage of materials disclosed in the impact analysis; no data center storage setbacks or containment, § 27-438.1.M(5)

  • Third-party electrical inspection before occupancy; no annual data center fire inspection, § 27-438.1.K(4)

  • Section 27-438.1.M(2) requires a traffic impact study in every case covering both construction and operation for roadways, intersections, bridges, and interchanges within one-half mile of the site, but the fixed radius does not necessarily reach the nearest arterial or interchange the trucks will use.

  • Construction traffic analyzed; no work hours, haul routes, or road bond, § 27-438.1.M(2)

  • Section 27-438.1.T(4) to (12) require security of 110 percent of decommissioning cost at the construction permit and removal of the data center and accessory equipment within 6 months after 12 months of nonuse, but the agreement is not recorded and the provisions do not address lawful reuse of buildings within 2 years.

  • Cost estimate after the first year and every fifth year, with security updated every 5 years, § 27-438.1.T(11) and (12)

  • Section 27-1302 defines a data center to include cryptocurrency mining, blockchain processing, artificial intelligence, and supercomputers, and excludes equipment secondary and customarily incidental to another use, but the exclusion sets no stated size or power limit.

  • One as-built sound study after opening, with later studies at the borough's option, § 27-438.1.G(1)(c)

  • Noise violations found by the as-built study are violations of the ordinance; general enforcement, § 27-438.1.G(1)(c)

  • Independent hydrologist and scientist review allowed; cost assigned only for a noise expert after a violation, § 27-438.1.G(3), L(3), and M(1)

Benefits & exceptionsHide benefits & exceptions1
  • Proposed approval pathway: Proposed: conditional use in the I District

Sources

Thank you to the Pennsylvania Data Center Ordinance Tracker for providing proposed local ordinance data for PA. Citation: padatacenterordinances.org, accessed November 3, 2026.Cookie preferences · Report missing data