Borough of Boyertown
Anti-Data Center Policies
Pennsylvania requires data centers over 25 megawatts to obtain local approvals and meet power, grid-cost, environmental, and community commitments; covered facilities also face annual energy and water reporting. These rules make large projects harder, not impossible, while eligible centers may receive equipment tax breaks.
Rating and summary from Pennsylvania statewide as there are no scored current or future laws outside temporary restrictions for Borough of Boyertown.
Incentives
Financial Incentive
Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.
pending · Boyertown BoroughBorough Council scheduled a public hearing and possible enactment for November 2, 2026 at 7:00 p.m., the same evening as the Colebrookdale Board of Commissioners, and Pike Township's hearing was reported for November 3, 2026.Boyertown Borough, Berks County — proposed data-center ordinance (None Adopted)
What this means
The proposal would impose setbacks from homes or other protected places, minimum site-size requirements and cooling and water-use rules. Data centers still have an approval route, but the siting or operating limits significantly narrow feasible projects.
Restrictions & requirementsHide restrictions & requirements30
60 ft maximum height, 62.a.i
Hydrological study of groundwater quality only; no riparian buffer or environmental impact assessment, 62.q
The Data Center definition includes Data Center Equipment and Accessory Uses on the same tract or assemblage of adjacent parcels developed as a unified development under a single land development plan, and 62.a.xiii requires 1,000 ft from any data center on another property.
Building cap only; no new approval for added phases or capacity, 62.a.iv
Noise must meet Section 511 of the joint ordinance, whose limits are not in the amendment text, 62.h
Section 62.i requires preliminary, interim, as-built (within 3 months of occupancy), and quarterly noise studies using ANSI S1.4-2014 meters, but no study is required at full operating load.
Testing capped at 50 hours per year and barred on poor air quality days; no weekday daytime limit, 62.r.iii
Public water required and hydrological study of nearby private wells with monitoring wells; no pump tests, 62.n and 62.q
Section 62.a.x requires a closed-loop liquid-based cooling system and bars air cooling as the primary system, but the equipment definition includes cooling towers and no water-use rate or noise showing is required for evaporative systems.
Quantity of water required must be disclosed; no cap, reporting, or drought plan, 62.p
Cooling fluids and condensate must be hauled off site and may not enter sewers, stormwater, or groundwater; no discharge plan approval, 62.a.x and 62.o
Cooling fluids barred from stormwater and battery fire runoff contained where practicable; no added design standards, 62.a.x and 62.a.xii
Natural gas generators must meet state and federal air rules, with annual hour reports and air monitors; no EPA Tier 4, 62.a.xi and 62.r
Electronics, batteries, and generators removed and recycled where practicable; refrigerants not addressed, 62.w
Utility interconnection agreement showing capacity with the application; no electrical inspection, 62.k.
On-site generation limited to temporary emergency use, 62.m
Substations integrated into the architecture or screened from homes and equipment in the rear yard; no buried line rule, 62.a.viii and 62.m
Batteries must meet applicable fire, building, and electrical codes with spill containment; NFPA 855 not named, 62.a.xii
Known impacts on electric rates must be noted; no cost assignment, 62.k
Bermed buffer with dense evergreen and deciduous screen next to residential districts and uses; width not stated, 62.v.iii
Ground and rooftop equipment screened with noise mitigation; no 12-ft or acoustic screen standard, 62.v.ii
Emergency Response Plan approved by the Fire Marshal; no annual update, radio coverage, or posted contacts, 62.b
Sections 62.f and 62.g require the data center to provide or pay for annual responder training and to supply specialized equipment to the fire and ambulance companies, but training before occupancy is not required and the equipment is not kept on site.
Secondary containment for glycol lines and battery electrolyte; no storage setbacks, 62.a.x and 62.a.xii
Secondary emergency access required; road class not addressed, 62.d
Section 62.w requires removal of electronic equipment, batteries, and generators within 6 months after end of useful life with funds of at least 125 percent of net cost, but no recorded agreement is required and removal or reuse of buildings is not addressed.
Estimate at zoning permit and every fifth year; no first-year update, 62.w
Quarterly noise studies and annual generator operation reports, 62.i.iv and 62.r.vii
Noise violations must be remediated; no specific penalties, 62.i
Applicant pays for its own noise studies; no municipal expert review, 62.i
Benefits & exceptionsHide benefits & exceptions1
Proposed approval pathway: Proposed: special exception in Colebrookdale's GI/Q district (joint zoning, Ordinance 04-2026)
Sources
- www.boyertownborough.org
- ecode360.com
- ecode360.com
- www.boyertownborough.org
- colebrookdale.org
- colebrookdale.org
- colebrookdale.org
- colebrookdale.org
- www.boyertownborough.org
- www.boyertownborough.org
- www.boyertownborough.org
- www.boyertownborough.org
- www.boyertownborough.org
- colebrookdale.org
- berksconnect.com
- drive.google.com
- padatacenterordinances.org
Thank you to the Pennsylvania Data Center Ordinance Tracker for providing proposed local ordinance data for PA. Citation: padatacenterordinances.org, accessed November 3, 2026.Cookie preferences · Report missing data