Bethlehem Township’s enacted ordinance allows data centers but requires cooling and water-use measures, technical studies, utility checks, and noise limits and testing, adding review and compliance costs.
Incentives
Financial Incentive
Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.
current law · Bethlehem TownshipThe current rules are in Ordinance No. 06-26, which the Board of Commissioners adopted on June 1, 2026.Bethlehem Township, Northampton County — data-center ordinance (No. 06-26)
What this means
The measure imposes cooling and water-use rules, technical studies and utility checks and noise limits and sound testing. Data centers can still be approved, but these obligations meaningfully increase construction, compliance or review costs.
Restrictions & requirementsHide restrictions & requirements15
Environmental impact study by an environmental engineer, § 275-189A(77)(o)
§ 275-132 applies: 57 dBA day and 53 dBA night at residential lines, § 275-189A(77)(i)
Preliminary study in the conditional use process and as-built study 6 months after occupancy, § 275-189A(77)(i)
Wells, groundwater, and surface water strictly prohibited; utility capacity documentation, § 275-189A(77)(l)
Closed-loop required when water cools; seasonal outside-air cooling; evaporative not restricted, § 275-189A(77)(j) and (k)
Utility capacity documentation and DRBC approval above thresholds, § 275-189A(77)(l) and (m)
Impact study must identify heat impacts and mitigation, § 275-189A(77)(o)
Power authority capacity documentation in the conditional use process; no third-party inspection, § 275-189A(77)(l).
Assessment of impacts on electric and water rates required, § 275-189A(77)(l)
100 ft buffer yard next to residential districts or uses, § 275-189A(77)(q).
Rooftop sound equipment fully screened, § 275-189A(77)(e)
Emergency response plan required, § 275-189A(77)(p)
Only the general conditional use traffic standard
As-built sound study results given to the Zoning Officer, § 275-189A(77)(i)
Final escrow release withheld until noise compliance, § 275-189A(77)(i)
Benefits & exceptionsHide benefits & exceptions1
Approval pathway: Conditional use in the GI and LI districts
Sources
Thank you to the Pennsylvania Data Center Ordinance Tracker for providing proposed local ordinance data for PA. Citation: padatacenterordinances.org, accessed November 3, 2026.Cookie preferences · Report missing data