City of Bethlehem
Anti-Data Center Policies
Bethlehem’s enacted data-center rules, though some descriptions call them a proposal, require special approval and extensive studies; 1,000-foot setbacks, noise limits, and utility requirements may sharply limit suitable sites.
Incentives
Financial Incentive2
Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.
Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.
current law · City of BethlehemRequires data centers in Bethlehem to undergo special-exception zoning review and meet specific environmental, utility, noise, safety, and site-design requirements.Bethlehem Bill No. 28-2026, proposed data-center zoning amendment
What this means
The proposal would allow data centers in the Industrial district through case-by-case special-exception review, but requires many costly studies and operating safeguards. The 1,000-foot setbacks from homes and other sensitive places, along with strict noise limits and utility-capacity requirements, could make projects substantially harder to site and approve.
People behind it
- Cathy Fletcher
Transmitted the proposed ordinance to City Council for consideration in her interoffice memo.
Restrictions & requirementsHide restrictions & requirements20
Data centers would be allowed as a special exception in the Industrial (IN) district, requiring case-by-case review by the Zoning Hearing Board. Special Exception within the Industrial (IN) Zoning District.
Applicants must submit all required plans, studies, assessments, and strategies with whichever comes first: the zoning permit or land development application. The applicant bears the burden of showing compliance, and the stricter zoning requirement controls in a conflict. All required plans, studies, evaluations.
Applicants must provide a professionally prepared environmental impact assessment covering applicable effects on karst, air, soil, water, wildlife and habitat, and stormwater under normal and adverse conditions, and propose mitigation where needed. environmental impact assessment.
Applicants must provide a certified water-use report detailing demand, seasonal variation, cooling, reuse, and other specified factors, and demonstrate adequate public water capacity; City Water and Sewer Resources Department approval is sufficient for the capacity criterion. water utilization report.
Applicants must document wastewater characteristics, volume, destination, and pretreatment needs, and demonstrate adequate disposal capacity for domestic, cooling, and industrial wastewater. City Water and Sewer Resources Department approval is sufficient for the capacity criterion. wastewater disposal documentation.
Applicants must submit a professional-engineer-certified energy management plan, including peak and annual demand, load phasing, supply sources, utility upgrades, backup power, and a power-usage-effectiveness analysis. Grid-connected projects must provide the service provider’s certification of available capacity and service, and note known project-attributable effects on electric rates or availability. energy management plan.
An on-lot power plant or system designed or used to supply a data center directly is not treated as part of, or accessory to, the data center; it is a separate primary use requiring approval under the zoning rules for that use. separate and primary use.
Applicants must provide an electronic-waste and decommissioning plan for safe removal or disposal of servers, batteries, hazardous materials, electronic waste, cooling equipment, and related infrastructure when equipment is replaced or the facility is decommissioned. electronic waste and decommissioning plan.
Applicants must submit a certified emergency response plan addressing, among other things, fire suppression, evacuation, site access, hydrants and water flow, high-voltage equipment, first-responder training, and the type, quantity, and location of onsite batteries, fuel, and other hazardous materials. emergency response plan.
Applicants must provide a certified thermal-impact mitigation plan explaining how waste heat will be managed, dissipated, or reused. thermal impact mitigation plan.
A preconstruction study by a qualified acoustical expert must show compliance at any lot line with maximum noise levels of 60 dBA daytime and 55 dBA nighttime, and 75 dBC daytime and 70 dBC nighttime. Pure tones must be at least 5 dBA below the applicable maximum; the study must assess major equipment and specified operating conditions, including peak cooling and generator testing. maximum noise levels.
A post-construction sound study of operating conditions must be submitted no earlier than one month and no later than 12 months after the first Certificate of Occupancy; the City may direct additional testing based on a reasonable complaint or evidence of changed operations. no sooner than one month.
Applicants must provide a vibration study demonstrating that data-center vibrations will not be perceptible above 65 VdB beyond the lot line. 65 VdB.
A qualified professional must conduct a photometric study demonstrating compliance with the zoning ordinance’s lighting-control requirements, including Article 1318.25(f). photometric study.
A data center must provide at least 1.20 parking spaces per employee on the largest shift; if the number of employees is unknown, at least five spaces are required. 1.20 parking spaces.
A data center must be at least 200 feet from any right-of-way and from the lot line of any lot outside the IN district, and at least 1,000 feet from a residential-district lot or an existing dwelling, school, day care, park, hospital, or community recreation center. at least 1,000 feet.
A data center may not exceed 80 feet in height, including rooftop structures. shall not exceed 80 feet.
Minimum front, side, and rear yard setbacks are each 80 feet. Minimum front yard setback.
The required buffer yard must be at least 40 feet wide. Equipment yards, generators, substations, and utility infrastructure must have a secure fence at least 8 feet high, with an exterior evergreen screen at least 6 feet high when planted and expected to reach at least 15 feet at maturity. minimum buffer yard.
Building coverage is limited by a size-based lot-area formula: buildings under 50,000 square feet may have up to 50% building coverage; above 50,000 and below 250,000 square feet, each additional square foot of building area requires 3 additional square feet of lot area; at 250,000 square feet or more, each additional square foot above that threshold requires 5 additional square feet of lot area. maximum percent building coverages.
Benefits & exceptionsHide benefits & exceptions1
Data centers may seek approval as a Special Exception in the Industrial (IN) district, providing a route to approval subject to case-by-case review by the Zoning Hearing Board; approval is not automatic. Special Exception within the Industrial (IN) Zoning District
Sources
current law · City of BethlehemRestricts data centers to specified industrial districts by special exception and requires applicants to meet detailed environmental, utility, noise, safety, setback, height, and site-design standards.Bethlehem zoning text amendment regulating data centers (Bill No. 28-2026 / Ordinance No. 2026-___)
What this means
The proposal would make future data centers substantially harder to build: it requires special-exception approval, extensive studies, and large setbacks. The meeting record says few industrial lots could support them, though smaller projects may still be possible; an application already in progress would be grandfathered under the existing rules.
People behind it
- Rachel Leon
Listed as a sponsor of Bill No. 28-2026, the data-center zoning amendment. The minutes identify Leon as a sponsor; the roll call gives her full name.
- Justin Amann
Listed as a sponsor of Bill No. 28-2026, the data-center zoning amendment. The minutes identify Amann as a sponsor; the roll call gives his full name.
Restrictions & requirementsHide restrictions & requirements21
Data centers are limited to the Industrial zoning district as a special-exception use, requiring special-exception approval. special exception
All required plans, studies, evaluations, assessments, and strategies must be submitted with the zoning permit or land-development application, whichever comes first. The applicant bears the burden of showing compliance, and the stricter rule applies if zoning requirements conflict. submitted together with the zoning permit
A qualified professional must prepare and certify an environmental impact assessment covering applicable impacts to karst features, air, soil, water, wildlife and habitat, and stormwater in normal and adverse conditions; mitigation strategies must be proposed where needed. environmental impact assessment
The applicant must provide a certified water-utilization report detailing water sources, average and peak demand, seasonal variation, cooling systems, reuse or recycling, drought and extreme-heat assumptions, and needed improvements, and demonstrate adequate public-water capacity. water utilization report
The applicant must document wastewater characteristics, volume, destination, and pretreatment needs, and demonstrate adequate disposal capacity for domestic wastewater and cooling or industrial wastewater. wastewater disposal documentation
A professional engineer must certify an energy-management plan stating anticipated peak and annual electricity demand, load phasing, energy sources, anticipated utility upgrades, and backup-power sources; the applicant must also provide a power-usage-effectiveness analysis and identify efficiency measures. energy management plan
If connecting to the electric grid, the applicant must provide the electricity provider’s certification that capacity is available and it will serve the center, and note known project-attributable effects on rates or electricity availability for other uses. capacity is available
On-lot power generation designed or used to supply the data center is treated as a separate primary use, not as part of or accessory to the data center, and must be approved under the zoning rules for that use. separate and primary use
The applicant must provide an electronic-waste and decommissioning plan for safely removing or disposing of servers, batteries, hazardous materials, electronic waste, cooling equipment, and related infrastructure when equipment is replaced or the center is decommissioned. electronic waste and decommissioning plan
A qualified professional must certify an emergency-response plan addressing fire suppression and containment, ventilation, evacuation, site access, hydrants and water flow, high-voltage equipment, any needed first-responder training, and the type, quantity, and location of onsite batteries, fuel, and other hazardous materials. emergency response plan
A qualified professional must certify a thermal-impact mitigation plan explaining how waste heat will be managed, dissipated, or reused. thermal impact mitigation plan
A qualified acoustical expert must conduct a full-spectrum preconstruction sound study showing compliance at any lot line with maximum levels of 60 dBA daytime and 55 dBA nighttime, and 75 dBC daytime and 70 dBC nighttime. Pure tones may not exceed a level 5 dBA below the applicable dBA limit. The study must assess major equipment and normal, peak-cooling, generator-testing, tonal, low-frequency, and cumulative noise. maximum noise levels
A post-construction sound study of operating conditions must be submitted no sooner than one month and no later than 12 months after the first Certificate of Occupancy; the City may require additional testing after a reasonable complaint or evidence of changed operations. no sooner than one month
A vibration study must demonstrate that vibrations will not be perceptible above 65 VdB beyond any lot line. 65 VdB
A qualified professional must conduct a photometric study demonstrating compliance with the lighting controls in Article 1318.25, including subsection (f). photometric study
Parking must be provided at 1.20 spaces per employee on the largest shift; if employee numbers are unknown, at least five spaces are required. 1.20 parking spaces
A data center must be at least 200 feet from a right-of-way and from the lot line of any lot outside the IN district, and at least 1,000 feet from a residential-zoned lot or an existing dwelling, school, child or adult day care, park, hospital, or community recreation center. at least 1,000 feet
Building height, including rooftop structures, may not exceed 80 feet. 80 feet in height
Minimum front, side, and rear yard setbacks are each 80 feet. Minimum front yard setback
The required buffer yard is at least 40 feet wide. Equipment yards, generators, substations, and utility infrastructure must have a secure fence at least 8 feet high, with an evergreen screen outside it at least 6 feet high at planting and expected to reach 15 feet at maturity. 40 feet wide
Building coverage is limited by building size: buildings under 50,000 square feet have a 50% maximum; above 50,000 and below 250,000 square feet, 3 additional square feet of lot area are required per additional square foot of building area; at 250,000 square feet or more, 5 additional square feet of lot area are required per additional square foot above 250,000. maximum percent building coverages
Benefits & exceptionsHide benefits & exceptions1
The measure creates a path for data centers to be approved by special exception in the Industrial Zoning District, subject to the ordinance’s standards and other applicable zoning requirements. (special exception in the Industrial Zoning District)
Sources
current law · Bethlehem CityCity Council gave Bill 28-2026 final passage by a 6-1 vote on October 20, 2026 as Ordinance No. 2026-29, which the Mayor approved on October 21, 2026, and two data center proposals filed before the vote, including 2184 Industrial Drive, will be reviewed under the earlier rules.Bethlehem City, Lehigh County — data-center ordinance (No. 2026-29)
What this means
The measure imposes setbacks from homes or other protected places and noise limits and sound testing. Data centers still have an approval route, but the siting or operating limits significantly narrow feasible projects.
Restrictions & requirementsHide restrictions & requirements27
Special exception only in the IN district; changed from permitted in LI, IN and PI, Section 2 (Art. 1305.01.e)
Special exception by the Zoning Hearing Board, Art. 1305.01.e; no approval expiration in the amendment
Article 1322.03(q)(12)(ii) places a Data Center at least 1,000 ft from the lot line of any residential district lot or existing dwelling, and the Data Center definition includes backup generators, water cooling facilities, and utility substations as part of the facility.
Environmental impact assessment covering karst, water quality, wildlife habitat and stormwater, Art. 1322.03(q)(1); no riparian buffer
60 dBA day and 55 dBA night at any lot line, above 50/45, Art. 1322.03(q)(8)(i)(A)
75 dBC day and 70 dBC night, above 60/55; study must evaluate low-frequency noise, Art. 1322.03(q)(8)(i)(B) and (ii)
Pre-construction study with the application and post-construction study 1 to 12 months after first CO; none at building permit, Art. 1322.03(q)(8)
Generator testing only evaluated in the sound study; no hours or cap, Art. 1322.03(q)(8)(ii)
Vibration study showing nothing perceptible above 65 VdB beyond any lot line; a numeric threshold rather than a no-perceptible standard, Art. 1322.03(q)(9)
Water utilization report and proof of adequate public water capacity; no well restriction or pump test, Art. 1322.03(q)(2)
Cooling system type and efficiency must be disclosed, Art. 1322.03(q)(2)(i)
Projected average and peak daily water demand disclosed; no cap, reporting or drought plan, Art. 1322.03(q)(2)(i)
Wastewater documentation including cooling wastewater, with adequacy approved by the City Water and Sewer Resources Department before approval, Art. 1322.03(q)(3)
Thermal impact mitigation plan identifying how waste heat will be managed, dissipated, or reused, Art. 1322.03(q)(7).
Electronic waste and decommissioning plan for servers, batteries, hazardous materials and cooling equipment; refrigerants not named, Art. 1322.03(q)(5)
Utility certification of capacity and service with the application; no third-party electrical inspection, Art. 1322.03(q)(4)(ii).
Energy management plan with power usage effectiveness analysis; no on-site renewable requirement, Art. 1322.03(q)(4)(i)
Substations fenced and surrounded by an evergreen screen; placement and line burial not addressed, Art. 1322.03(q)(15)
Battery locations disclosed in the emergency plan only; no NFPA 855, Art. 1322.03(q)(6)
Buffer yard of 40 ft, Art. 1322.03(q)(15)
Photometric study showing compliance with the lighting controls of Art. 1318.25, including 1318.25(f), Art. 1322.03(q)(10); the base lighting text was not reviewed
Equipment yards, generators and substations fenced 8 ft and screened by evergreens 6 ft at planting growing to 15 ft; no acoustic screening, Art. 1322.03(q)(15)
Emergency response plan certified by a qualified professional, Art. 1322.03(q)(6); no fire company review, annual update, radio coverage or posted contacts
Emergency plan must address any necessary first responder training, Art. 1322.03(q)(6); funding not assigned
Type, quantity and location of battery, fuel and other hazardous materials documented, Art. 1322.03(q)(6); no storage setbacks or containment
Decommissioning plan required without financial security, Art. 1322.03(q)(5)
One post-construction sound study after opening, with more testing at City direction on complaint, Art. 1322.03(q)(8)(iii)
Benefits & exceptionsHide benefits & exceptions1
Approval pathway: Special exception in the IN district only (Ordinance No. 2026-29)
Sources
- www.bethlehem-pa.gov
- www.bethlehem-pa.gov
- www.bethlehem-pa.gov
- www.bethlehem-pa.gov
- img1.wsimg.com
- www.bethlehem-pa.gov
- www.bethlehem-pa.gov
- www.bethlehem-pa.gov
- www.bethlehem-pa.gov
- www.bethlehem-pa.gov
- www.bethlehem-pa.gov
- www.bethlehem-pa.gov
- www.nbcphiladelphia.com
- lehighdaily.com
- www.bethlehem-pa.gov
- www.bethlehem-pa.gov
- padatacenterordinances.org
current law · Bethlehem CityCity Council gave Bill 28-2026 final passage by a 6-1 vote on October 20, 2026 as Ordinance No. 2026-29, which the Mayor approved on October 21, 2026, and two data center proposals filed before the vote, including 2184 Industrial Drive, will be reviewed under the earlier rules.Bethlehem City, Northampton County — data-center ordinance (No. 2026-29)
What this means
The measure imposes setbacks from homes or other protected places and noise limits and sound testing. Data centers still have an approval route, but the siting or operating limits significantly narrow feasible projects.
Restrictions & requirementsHide restrictions & requirements27
Special exception only in the IN district; changed from permitted in LI, IN and PI, Section 2 (Art. 1305.01.e)
Special exception by the Zoning Hearing Board, Art. 1305.01.e; no approval expiration in the amendment
Article 1322.03(q)(12)(ii) places a Data Center at least 1,000 ft from the lot line of any residential district lot or existing dwelling, and the Data Center definition includes backup generators, water cooling facilities, and utility substations as part of the facility.
Environmental impact assessment covering karst, water quality, wildlife habitat and stormwater, Art. 1322.03(q)(1); no riparian buffer
60 dBA day and 55 dBA night at any lot line, above 50/45, Art. 1322.03(q)(8)(i)(A)
75 dBC day and 70 dBC night, above 60/55; study must evaluate low-frequency noise, Art. 1322.03(q)(8)(i)(B) and (ii)
Pre-construction study with the application and post-construction study 1 to 12 months after first CO; none at building permit, Art. 1322.03(q)(8)
Generator testing only evaluated in the sound study; no hours or cap, Art. 1322.03(q)(8)(ii)
Vibration study showing nothing perceptible above 65 VdB beyond any lot line; a numeric threshold rather than a no-perceptible standard, Art. 1322.03(q)(9)
Water utilization report and proof of adequate public water capacity; no well restriction or pump test, Art. 1322.03(q)(2)
Cooling system type and efficiency must be disclosed, Art. 1322.03(q)(2)(i)
Projected average and peak daily water demand disclosed; no cap, reporting or drought plan, Art. 1322.03(q)(2)(i)
Wastewater documentation including cooling wastewater, with adequacy approved by the City Water and Sewer Resources Department before approval, Art. 1322.03(q)(3)
Thermal impact mitigation plan identifying how waste heat will be managed, dissipated, or reused, Art. 1322.03(q)(7).
Electronic waste and decommissioning plan for servers, batteries, hazardous materials and cooling equipment; refrigerants not named, Art. 1322.03(q)(5)
Utility certification of capacity and service with the application; no third-party electrical inspection, Art. 1322.03(q)(4)(ii).
Energy management plan with power usage effectiveness analysis; no on-site renewable requirement, Art. 1322.03(q)(4)(i)
Substations fenced and surrounded by an evergreen screen; placement and line burial not addressed, Art. 1322.03(q)(15)
Battery locations disclosed in the emergency plan only; no NFPA 855, Art. 1322.03(q)(6)
Buffer yard of 40 ft, Art. 1322.03(q)(15)
Photometric study showing compliance with the lighting controls of Art. 1318.25, including 1318.25(f), Art. 1322.03(q)(10); the base lighting text was not reviewed
Equipment yards, generators and substations fenced 8 ft and screened by evergreens 6 ft at planting growing to 15 ft; no acoustic screening, Art. 1322.03(q)(15)
Emergency response plan certified by a qualified professional, Art. 1322.03(q)(6); no fire company review, annual update, radio coverage or posted contacts
Emergency plan must address any necessary first responder training, Art. 1322.03(q)(6); funding not assigned
Type, quantity and location of battery, fuel and other hazardous materials documented, Art. 1322.03(q)(6); no storage setbacks or containment
Decommissioning plan required without financial security, Art. 1322.03(q)(5)
One post-construction sound study after opening, with more testing at City direction on complaint, Art. 1322.03(q)(8)(iii)
Benefits & exceptionsHide benefits & exceptions1
Approval pathway: Special exception in the IN district only (Ordinance No. 2026-29)
Sources
Thank you to the Pennsylvania Data Center Ordinance Tracker for providing proposed local ordinance data for PA. Citation: padatacenterordinances.org, accessed November 3, 2026.Cookie preferences · Report missing data