Borough of Berwick

Anti-Data Center Policies

Berwick borough’s enacted measure sets noise limits, requires sound testing, and creates setbacks from homes and other protected places. Data centers may still be approved, but must meet added requirements that increase costs.

Incentives

Financial Incentive

Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.

current law · Berwick Borough
The current rules are in Ordinance No. 2026-04, the Berwick Borough 2026 Zoning Ordinance, which Borough Council approved on August 3, 2026.Berwick Borough, Columbia County — data-center ordinance (No. 2026-04)

What this means

The measure imposes noise limits and sound testing and setbacks from homes or other protected places. Data centers can still be approved, but these obligations meaningfully increase construction, compliance or review costs.

Restrictions & requirementsHide restrictions & requirements20
  • 200 to 400 ft setbacks protect neighboring uses at less than 1,000 ft, § 802.21.A.5

  • Industrial district height limits applied to data centers, with generators kept below the roof line, § 802.21.A and A.6

  • Full impact assessment with environmental compatibility report and hydrogeological study; no riparian buffer, § 802.21.C

  • Single 50 dBA property line limit, § 802.21.A.6

  • Noise protocol with projected day and night levels before approval; no later study, § 802.21.C.1.iv

  • Vibration isolation required for mechanical systems; no study or property line standard, § 802.21.A.f and 4.a.iv

  • Hydrogeological drawdown study where wells or recharge areas are affected; no pump tests or bar on wells, § 802.21.C.1.iii

  • Closed-loop, hybrid, or reclaimed-water cooling; open-loop prohibited, but hybrid systems allowed, § 802.21.A.7

  • Stamped water use plan with daily and peak withdrawals; no cap or reporting, § 802.21.A.g and 4.a.ii

  • Utility coordination plan with substation capacity and redundant service confirmation; no electrical inspection, § 802.21.A.a and 4.a.ii

  • Electrical demand, peak and base load documented; no on-site renewable requirement, § 802.21.C.1.ii

  • On-site generation not addressed as a separate use; backup generators limited to outages

  • Required utility upgrades must be identified; cost not assigned, § 802.21.C.1.ii

  • Section 802.21 subsection 5 requires a 200 ft minimum buffer of native evergreens, berms, opaque fencing, and a gravel firebreak, with setbacks of 400 ft next to residential districts and effective layering for noise and visual impact, but it does not require replacement of dead or diseased plants.

  • Long facades must include articulation, step-backs, or landscaping, § 802.21.A.e

  • Opaque fencing, acoustic shielding, and baffled generator enclosures; no screening height, § 802.21.A.e and f

  • Fire protection and emergency operations plan with site maps for emergency services; no fire company review or annual updates, § 802.21.C.1.i

  • Traffic analysis in the full impact assessment for sites over 5,000 sq ft or 1 MW, § 802.21.B and 4.a.vii

  • Two ingress and egress points and no reliance on residential streets; no arterial requirement, § 802.21.A.c

  • Removal and restoration within 180 days of notice with bonding of unspecified amount, § 802.21.A.j

Benefits & exceptionsHide benefits & exceptions1
  • Approval pathway: Special exception in the I-2 General Industrial District, with minor data centers also in the I-1 Light Industrial District

Sources

Thank you to the Pennsylvania Data Center Ordinance Tracker for providing proposed local ordinance data for PA. Citation: padatacenterordinances.org, accessed November 3, 2026.Cookie preferences · Report missing data