Bern Township

Anti-Data Center Policies

Bern Township’s enacted measure gives officials time to address gaps in zoning rules, potentially delaying developers’ challenges; it does not prohibit every data-center project.

Incentives

Financial Incentive
3

Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.

Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.

Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.

current law · Bern Township
The Supervisors adopted a curative amendment resolution declaring the zoning ordinance deficient regarding data centers.Bern Township, Berks County — data-center resolution unnumbered resolution 2026-07-07

What this means

The measure starts a protected period for local officials to fix gaps in their zoning rules. This can delay developers who need to challenge the old rules, but it does not by itself prohibit every data-center project.

Sources

current law · Bern Township
The Supervisors adopted a resolution on the invalidity of the township ordinance with regard to data centers.Bern Township, Berks County — data-center procedural resolution findings resolution

What this means

The measure starts a protected period for local officials to fix gaps in their zoning rules. This can delay developers who need to challenge the old rules, but it does not by itself prohibit every data-center project.

Sources

pending · Bern Township
The draft amends Chapter 184 as Ordinance No. ___-2026, the Supervisors' November 2, 2026 agenda lists approval to advertise it, and the township expects the Supervisors to consider adopting it at their January 4, 2027 meeting.Bern Township, Berks County — proposed data-center ordinance (None Adopted)

What this means

The proposal would impose cooling and water-use rules, money set aside for eventual removal and noise limits and sound testing. Data centers can still be approved, but these obligations meaningfully increase construction, compliance or review costs.

Restrictions & requirementsHide restrictions & requirements31
  • Conditional use where permitted in a district; no district named in the draft text, Section 184-153.1.F

  • Heat-rejection equipment 200 ft from residential districts and uses; no setback for buildings, F(2) Thermal Impact Mitigation Plan

  • Environmental impact study, steep slope analysis, and PNDI review required, F(2)(c), (e), and (l)

  • Updated water study only if withdrawal rises over 10%; no new approval for expansion, F(2) water feasibility study

  • Single 55 dBA limit, or the stricter time-of-day limit of Section 184-153, at the property line, F(4)

  • 70 dBC limit at the property line, F(4)

  • Preliminary study with the application and as-built study 6 months after occupancy; none at building permit, F(4)(a) and (d)

  • Testing weekdays 9:00 a.m. to 5:00 p.m., one generator at a time; no hours cap, F(4)(g)

  • Vibration study showing no perceptible vibration beyond the property line, F(2)(g).

  • Wells and surface withdrawals barred as the primary cooling source where public water is available; hydrogeologic report with aquifer test, F(2)(t) and water feasibility study

  • Water use for cooling must be described; closed-loop cooling not required, F(2)(u)

  • Section F(2)(c) of the draft requires a drought response plan showing compliance with state, water supplier, and local drought declarations, but the quarterly metered withdrawal reports to the Township in Section F(6)(r) apply only to on-site groundwater withdrawals subject to the monitoring plan, not to every data center.

  • Section F(2)(j) of the draft bars discharge of cooling system wastewater except by a DEP-licensed hauler or to sanitary sewer under a pretreatment permit or written sewer authority authorization, with sampling before each discharge, but does not require the authority or DEP approval to be in hand before the zoning permit.

  • Generators limited by DEP air quality authorization, with approval before a zoning permit, F(4)(g)

  • Thermal Impact Mitigation Plan with 3 degree F property line limit; no waste heat reuse review, F(2) Thermal Impact Mitigation Plan

  • Decommissioning removes servers, batteries, and refrigerants for disposal or recycling, F(10)(e).

  • Utility capacity confirmation with the application and executed service agreement before a zoning permit; no electrical inspection, F(2)(m).

  • On-site generation for normal operations not permitted as part of the use, F(2)(o)

  • Landscaped screening under Section 184-132.55 referenced; width not stated in the draft, F(2)(o) and F(10)(g)

  • Full cutoff shielding with 0.1 footcandle limit at residential property lines, F(2)(n)

  • Low-reflective, earth tone colors required, F(2)(q)

  • Emergency Response Plan reviewed by the fire company; no annual updates, radio coverage, or contact signs, F(2) Emergency Response Plan

  • First responders must receive system-specific training; funding not assigned, F(2) Emergency Response Plan [4]

  • Spill containment for fuels and 110% secondary containment for treatment chemicals; no storage setbacks, F(2)(n) and (j)

  • Annual fire safety inspections at the operator's expense; no third-party electrical inspection, F(2) Emergency Response Plan [5]

  • Section F(2)(a) of the draft requires a traffic impact study under Section 154-30.I(1)(c) with every conditional use application and truck traffic information after construction is completed, but does not require construction traffic analysis or a study area reaching the nearest arterial or interchange.

  • Second means of emergency ingress and egress required; no arterial road access rule, F(2)(m)

  • Security for the full estimate with contingency, removal within 12 months of a final notice, F(10)(d) and (j)

  • Section F(10) of the draft requires the decommissioning cost estimate to be recalculated annually and whenever equipment is added, and requires the Responsible Parties to increase the financial security to equal the recalculated amount within 30 days.

  • Quarterly groundwater withdrawal and level reports, F(6)

  • Section F(2) of the draft lets the Township retain a professional at the applicant's expense to review the water feasibility study before the conditional use decision, and Section F(4)(a) lets the Township have the sound study prepared at the operator's expense, but this review occurs at the conditional use stage rather than in land development review.

Benefits & exceptionsHide benefits & exceptions1
  • Proposed approval pathway: Proposed: conditional use (districts not named in the draft)