Benton Township

Anti-Data Center Policies

Benton Township’s enacted ordinance requires setbacks from homes and other protected places, minimum site sizes, and cooling and water-use rules. Data centers can still be approved, but these limits narrow where and how they can operate.

Incentives

Financial Incentive

Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.

current law · Benton Township
The Supervisors enacted Ordinance No. 9-22-26 at a special meeting after the public hearing on September 22, 2026, and it took effect on September 27, 2026.Benton Township, Lackawanna County — data-center ordinance (No. 9-22-26)

What this means

The measure imposes setbacks from homes or other protected places, minimum site-size requirements and cooling and water-use rules. Data centers still have an approval route, but the siting or operating limits significantly narrow feasible projects.

Restrictions & requirementsHide restrictions & requirements33
  • Conditional use before the Supervisors; approval expires if construction does not begin within one year, § 859.3(C)

  • 100 ft setback from streams, wetlands, and floodplains, with an acoustic and ecological impact report; no wider buffer on steep slopes, § 859.6(C) and § 859.9(A)

  • Section 859.8 sets 45 dBA weekday daytime and 40 dBA at all other times at the property line, established by a 72-hour test under ANSI S12.18-1994 Method II and ANSI S1.4 with a Type I sound level meter.

  • 60 dBC weekday daytime and 50 dBC at all other times, § 859.8

  • Section 859.8 requires pre-construction, conditional use, building permit, and as-built studies six months after occupancy under ANSI S12.18 and S1.4 with Type I meters, but the as-built study is not required at full operating load.

  • Section 859.8(F)(3) bars routine generator testing on weekday nights, weekends, and holidays, and Section 859.9(B)(2) limits testing to Tuesdays from 10:00 a.m. to 2:00 p.m., but no daily or annual hours cap is stated and no allowance is made for code-required tests outside that window.

  • Closed-loop cooling required and open evaporative cooling towers prohibited unless exempted, § 859.10(G).

  • Projected water demand disclosed in the feasibility study; no use cap, usage reporting, or drought plan, § 859.10(C)

  • Section 859.10(F) requires the applicant to demonstrate that disposal of domestic, cooling, and industrial wastewater has been provided and approved by the Sewage Enforcement Officer and DEP as part of the conditional use showing, and Section 859.10(H) requires NPDES coverage for any cooling or process discharge before building approvals.

  • Environmental impact assessment must cover stormwater effects; no stormwater standards, § 859.13

  • Thermal Impact Mitigation Plan including evaluation of waste heat reuse, § 859.12(C).

  • Electronic Waste Plan for servers, hazardous materials, and batteries, with refrigerants addressed at decommissioning, § 859.19 and § 859.20(C).

  • Utility certification of capacity and an independent grid capacity study at application; no electrical inspection, § 859.12(B)(3).

  • Plan to minimize energy and water use and a load management plan; no on-site renewable requirement, § 859.12(A) and (B)(7)

  • Generation supplying power during normal operations is a separate use with its own approval, § 859.12(B)(4).

  • Substations screened and primary distribution lines buried; substation placement not addressed, § 859.7(F) and § 859.12(B)(9)

  • Section 859.12(B) requires a grid capacity study and ratepayer impact analysis with the application and a binding Grid Impact and Cost Allocation Agreement with the serving utility assigning 100 percent of new transmission, substation, and generation costs to the applicant, but it does not require disclosure of the estimated upgrade cost, the tariff terms, or an executed service agreement before the zoning permit.

  • 50-ft buffer yard along residential property lines, § 859.7(A)

  • Fully shielded fixtures and 0.1 footcandle limit 20 ft beyond the property line, § 859.18

  • Viewshed mitigation may require changes to exterior materials, including no reflective glass; no facade standards, § 859.7(H)

  • All equipment enclosed or screened, ground equipment to 8 ft with noise-absorbing barriers, § 859.7(F)

  • Emergency Response Plan accepted by the fire department, with radio coverage and 24-hour contact signage; no annual plan update, § 859.15

  • Spill prevention and secondary containment for hazardous fluids; no storage setbacks, § 859.11

  • Annual fire safety inspections by local fire departments; no electrical inspection, § 859.15(A)(9)

  • Environmental impact assessment must address traffic; no separate traffic impact study, § 859.13(A)(4)

  • Two means of emergency ingress and egress; no road class requirement, § 859.14

  • Right-of-way restoration with financial security for utility work; no work hours or haul routes, § 859.12(B)(9)

  • Security of net decommissioning cost plus 10% and 48-hour closure notice, but removal within 12 months, § 859.20(B) and (G)

  • Section 859.20(F) requires Net Decommissioning Cost estimates after the first year of operation and every fifth year, and requires the owner to post and maintain decommissioning funds equal to Net Decommissioning Costs plus 10 percent, so the security follows the updated estimate.

  • Semi-annual energy reports and annual noise compliance reports, § 859.9(C) and § 859.12(B)(8)

  • Section 859.24 requires permit revocation or operational suspension when violations are not remediated and fines of up to $1,000 per day, but no notice or hearing precedes revocation and MPC Sections 616.1 and 617.2 are not cited.

  • Section 859.23 requires a $20,000 escrow paid with the land development plan submission for the Township's professional fees, with all required studies included for preliminary and final land development plan approval, and Section 859.8 lets the Township require third-party reviews at the applicant's cost.

  • Applicant public meeting before first Planning Commission or Supervisors review and a project website kept through final approval, § 859.22

Benefits & exceptionsHide benefits & exceptions1
  • Approval pathway: Conditional use in the Industrial District

Sources

Thank you to the Pennsylvania Data Center Ordinance Tracker for providing proposed local ordinance data for PA. Citation: padatacenterordinances.org, accessed November 3, 2026.Cookie preferences · Report missing data