Benton Township

Anti-Data Center Policies

Benton Township requires data centers to meet setbacks, minimum site sizes, and location limits; approval remains possible, but fewer sites may qualify.

Incentives

Financial Incentive

Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.

current law · Benton Township
The Board of Supervisors adopted Ordinance No. 01-26 and the Data Center Overlay Map on July 22, 2026, after a public hearing that evening.Benton Township, Columbia County — data-center ordinance (No. 01-26)

What this means

The measure imposes setbacks from homes or other protected places, minimum site-size requirements and limited eligible locations. Data centers still have an approval route, but the siting or operating limits significantly narrow feasible projects.

Restrictions & requirementsHide restrictions & requirements38
  • Section 4.1 establishes the Data Center Overlay District as shown on the Official Zoning Map, and Section 4.4 states that no Data Center shall be permitted outside it.

  • Conditional use in the DCOD; no expiration of approval if construction does not begin, Section 7(A)

  • Overlay siting considers avoiding prime agricultural soils where feasible; no bar on preserved farmland or agricultural security areas, Section 4(2)(d)

  • 300-ft front, side, and rear yard setbacks; no separate setback from residential uses or districts, Section 8(C)

  • 50-ft building height unless approved through the Master Plan; mechanical equipment up to 65 ft, Section 8(D) and (I)

  • Environmental Impact Statement required covering wetlands, floodplains, steep slopes, and habitat; no riparian buffer width, Sections 6(B)(1), 9(I), and 10(B)

  • Section 6.A.3 defines a Data Center Campus as buildings on a unified tract or assemblage of parcels under common ownership or control, Section 7.A permits the campus as one conditional use under one Master Plan (Section 9), and Section 8.G requires one mile between data centers on separate properties.

  • Section 7.E bars a later phase until prior phases comply, and Section 9.E requires the Energy Demand Analysis to state projected electrical demand for each phase of development.

  • 55 dBA day and 50 dBA night and weekends at the property line, 45 dBA at night at Sensitive Receptor property lines, Section 9(C)

  • Section 9.C requires preliminary, interim, and as-built noise studies, with measurements under ANSI S1.4-2014, but does not require the as-built study to be taken at full operating load.

  • Generator testing permitted per manufacturer and industry standards; no hours limit, Section 9(C)

  • Section 9.J sets 0.1 in/sec PPV at the property line and requires a Vibration Impact Study using PPV or the then current industry standard, but names no measurement standard or procedure.

  • Groundwater and surface water may not be used for cooling, and a hydrogeologic Water Feasibility Study is required; no pump tests specified, Sections 6(B)(3) and 11(C)

  • Only air-cooled or sealed non-evaporative closed-loop cooling permitted; evaporative cooling prohibited, Section 11(A)-(B)

  • Monthly water use reporting; no drought response plan, Section 14(C)

  • Cooling wastewater, blowdown, and thermal discharge prohibited, with certification in the Stormwater Management Plan submitted with the application, Sections 9(G) and 11(A)(1)(e)

  • DEP, Conservation District, and County SALDO stormwater standards stated as applying; cooling discharges barred from stormwater facilities, Section 9(G)

  • Backup power must meet DEP and EPA air-quality standards; Tier IV generators may be required, Sections 9(E) and 11(G)

  • Heat Plume Mitigation Plan with dispersion modeling and heat plume monitoring; no waste heat reuse review, Sections 6(B)(5), 10(F), and 14(B)

  • Decommissioning plan covers removal of hazardous materials, batteries, and transformers, and BESS recycling; servers and refrigerants not named, Section 9(M)-(N)

  • Utility Capacity Letters required with the application; no third-party electrical inspection before occupancy, Sections 6(B)(4), 9(E), and 10(E).

  • On-site generation must be described in the Energy Demand Analysis and nuclear systems are prohibited; not treated as a separate use, Sections 9(E) and 12.1

  • Substations are accessory uses and must be screened from roads and adjoining properties; no burial of lines, Sections 6(A)(4) and 9(K)

  • BESS must meet NFPA 855 with BESS-specific fire suppression and thermal runaway procedures, Section 9(N).

  • Utility documentation must disclose required upgrades and responsibility for them; applicant payment not required, Section 9(E)

  • Landscaping and Buffering Plan with evergreen screening or berms; no buffer width, Section 9(K)

  • Screening of mechanical equipment, cooling infrastructure, and substations required; no height or acoustic standard, Section 9(K)

  • Emergency Response Plan coordinated with emergency services, approved by the Township, with 24-hour contacts; no annual updates or radio coverage, Sections 9(F) and 11(I)

  • Community Benefit Agreement must address contributions to offset impacts on police and fire services, but payment cannot be a condition of approval; no training requirement, Section 5

  • Hazardous materials management in the ERP and BESS spill containment; no storage setbacks, Sections 9(F) and 9(N)

  • Section 10.H lists a Traffic Impact Study among the required application contents but states no scope, so construction traffic and the study area are not addressed.

  • Emergency access addressed in the ERP; no road classification or secondary access requirement, Section 9(F)

  • Construction hours and designated truck routes set; no road damage bond, Section 13(A) and (E)

  • Financial security required and decommissioning after 12 months of inactivity; no 110% amount or six-month removal deadline, Sections 9(M) and 15

  • Security reviewed every three years; no update after the first year, Sections 9(M) and 15(C)

  • Continuous noise monitoring, monthly water use reporting, and annual energy reporting, Sections 12(C) and 14

  • Section 17 makes violations zoning violations enforced under the Zoning Ordinance and the MPC and states that approvals may be revoked, but gives no revocation grounds, notice, or hearing.

  • Applicant reimburses Township experts only for confirmed vibration violations and decommissioning estimates; no general paid review of studies, Sections 9(J) and 9(M)

Benefits & exceptionsHide benefits & exceptions1
  • Approval pathway: Conditional use in the Data Center Overlay District

Sources

Thank you to the Pennsylvania Data Center Ordinance Tracker for providing proposed local ordinance data for PA. Citation: padatacenterordinances.org, accessed November 3, 2026.Cookie preferences · Report missing data