Beech Creek Township

Anti-Data Center Policies

Beech Creek Township’s enacted ordinance limits noise and backup or on-site power, requires sound testing and setbacks from homes or other protected places, and increases project costs; data centers may still be approved.

Incentives

Financial Incentive

Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.

current law · Beech Creek Township
The Board of Supervisors enacted the standards as Ordinance No. 08.03.2026.01 on August 3, 2026, according to the signed ordinance, which takes effect 30 days after adoption.Beech Creek Township, Clinton County — data-center ordinance (No. 08.03.2026.01)

What this means

The measure imposes noise limits and sound testing, setbacks from homes or other protected places and limits on backup generators or on-site power. Data centers can still be approved, but these obligations meaningfully increase construction, compliance or review costs.

Restrictions & requirementsHide restrictions & requirements20
  • Conditional use hearing before the Board of Supervisors; no approval expiration, Amendment 2 and Section 6.36.N

  • Barred from 100-year and 500-year floodplains; no riparian buffer, Section 6.36.G

  • Noise Mitigation Plan with acoustic study at zoning application; no later study, Section 6.36.A(1)

  • Water Utilization Report on intake and sources, and proof that needs can be met without threatening existing service; no hydrogeologic study, Section 6.36.D and P

  • Cooling system type and efficiency disclosed; no method required, Section 6.36.D(1)

  • Total daily intake volume disclosed; no cap, reporting or drought plan, Section 6.36.D(1)

  • Discharge volumes and destinations and sewage treatment capacity disclosed; no cooling discharge approval, Section 6.36.D and P

  • EPA Tier 4 generators with annual testing and reports to the Township, Section 6.36.B

  • Thermal Impact Mitigation Plan with waste heat reuse or dissipation strategies; no modeled property line temperature effects, Section 6.36.F

  • Electronic Waste Plan for removal and recycling of servers, hazardous materials and batteries; no disposal contract kept in effect, Section 6.36.E

  • Energy Management Plan certified by an engineer; renewable energy only a good faith effort, Section 6.36.C

  • Accessory electrical substations screened, Section 6.36.L(1)

  • Battery systems must meet fire suppression standards and be UL certified; no NFPA 855, Section 6.36.M(2)

  • 100-ft buffer yard along residential property lines and street frontage, with a landscape plan; no year-round screening or plant replacement standard, Section 6.36.K

  • Ground equipment enclosed or behind a noise-absorbing solid barrier and rooftop equipment screened on four sides; no 12-ft standard, Section 6.36.L

  • Emergency Response Plan reviewed by the Township; no fire company review or annual updates, Section 6.36.M(1)

  • Battery systems must follow hazardous material handling protocols; no disclosure, setbacks or containment, Section 6.36.M(2)

  • Decommissioning plan with a bond based on estimated cost, removal within 18 months of abandonment; no 110% security or closure notice, Section 6.36.Q

  • Annual emissions testing reports only; no noise, water or power reports, Section 6.36.B(2)

  • Developer public informational meeting before any Planning Commission meeting or hearing; no project website, Section 6.36.N

Benefits & exceptionsHide benefits & exceptions1
  • Approval pathway: Conditional use in the Light Industrial Zone

Sources

Thank you to the Pennsylvania Data Center Ordinance Tracker for providing proposed local ordinance data for PA. Citation: padatacenterordinances.org, accessed November 3, 2026.Cookie preferences · Report missing data