Bear Creek Township
Anti-Data Center Policies
Bear Creek Township requires removal funds, noise limits and testing, and setbacks from homes and other protected places; data centers may still be approved, but compliance and review can cost more.
Incentives
Financial Incentive
Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.
current law · Bear Creek TownshipThe Board of Supervisors enacted Ordinance 4 of 2026 on October 15, 2026, after a public hearing on Ordinances 3 and 4 of 2026 scheduled for September 30, 2026, and the township posts the signed ordinance on its Proposed Zoning Amendments page.Bear Creek Township, Luzerne County — data-center ordinance (Ordinance 4 Of 2026)
What this means
The measure imposes money set aside for eventual removal, noise limits and sound testing and setbacks from homes or other protected places. Data centers can still be approved, but these obligations meaningfully increase construction, compliance or review costs.
Restrictions & requirementsHide restrictions & requirements33
Conditional use before the Board of Supervisors; no approval expiration, § 127-68.1.E
150-ft riparian buffer kept where possible, not widened at slopes or wetlands; EIS required, § 127-68.1.C(1) and C(9)(b)
Data center campus defined and limited to two principal buildings; no separation distance, § 127-7 and § 127-68.1.A(3)
Section 127-68.1.D(4) requires a Construction Phasing Plan identifying each phase, its timing, and supporting infrastructure, with each phase complying on its own, but no phase states its electrical demand and no new approval is required for added capacity.
Section 127-68.1.C(2)(a) sets 50 dBA Leq by day and 45 dBA Leq at night at the lot line and nearest sensitive receptor, and C(2)(b)[8] requires calibrated ANSI S1.4 Type 1 or Type 2 meters and generally accepted environmental noise methodology.
Low-frequency evaluation only if the township requires it; no dBC limit, § 127-68.1.C(2)(b)[5]
Section 127-68.1.C(2)(b) requires a predictive study with the conditional use application and an as-built study six months after occupancy using ANSI S1.4 meters, but the as-built sound study is not required at full operating load.
Section 127-68.1.C(14)(c) limits generator testing to 10:00 a.m. to 4:00 p.m. on weekdays and caps routine testing at 30 minutes per month, but the cap has no exception for longer tests required by code.
Section 127-68.1.C(3) sets a 65 VdB limit, bars perceptible vibration past the lot line, and requires predictive and as-built vibration studies at full load, but no vibration measurement method or standard is stated.
Public water or water hauled from outside the township required, with a will-serve letter; no pump test, § 127-68.1.C(10)(a)
Closed-loop, recirculation, or another water-efficient method; cooling type disclosed, § 127-68.1.C(10)(b)-(c)
Drought contingency plan and daily intake disclosed; no cap or ongoing reporting, § 127-68.1.C(9)(c) and C(10)(c)
Cooling system flush-out and backwash disposed under a DEP-approved plan, with sewage module and will-serve letter at application, § 127-68.1.C(12)
Township and watershed stormwater standards and the DEP BMP manual stated as applying, § 127-68.1.C(11)
Generators must meet DEP and EPA emission rules; Tier IV encouraged, not required; annual air quality testing, § 127-68.1.C(4) and C(14)(c)[6]-[7]
Heat mitigation plan including evaluation of waste heat reuse, § 127-68.1.C(5).
E-waste plan covers servers and batteries; refrigerants not named, § 127-68.1.C(13)(b)
Electric capacity verification with the application; no third-party electrical inspection, § 127-68.1.C(14)(e).
Energy management plan; roofs need only be solar-ready, § 127-68.1.C(14)(a)[3] and (d)
New lines buried unless infeasible, with no kV limit; no substation placement rule, § 127-68.1.B(7)
Rate and availability impacts must be documented; upgrade costs not assigned, § 127-68.1.C(14)(e)
Planted buffer yard of 50 to 100 ft with berms next to residential districts, § 127-68.1.B(2)-(4)
Ground equipment behind an 8-ft fence or wall and roof equipment screened on all sides; no 12-ft standard, § 127-68.1.B(6)
Owner must provide annual training with first responders; funding not required, § 127-68.1.C(6)(c)[7]
Containment systems for chemicals and suppressants; no storage setback, § 127-68.1.C(9)(a)
Annual fire and life-safety inspections, § 127-68.1.C(6)(c)[6]
Section 127-68.1.C(16) requires a Traffic Impact Study with every application covering the nearby highway network, peak-hour volumes, service levels, and trip generation, but it does not evaluate construction traffic or set a study area reaching the nearest arterial or interchange.
Security of 110% and notice of closure, but 18 months to remove, § 127-68.1.C(19)
Section 127-7 defines a data center to include cryptocurrency mining, blockchain processing, and artificial intelligence, and excludes incidental servers unless they are in a separate building, but the exclusion sets no stated size or power limit.
As-built sound and vibration studies after opening; annual air quality reports, § 127-68.1.C(2)-(4)
Section 127-68.1.E(5) allows revocation of the conditional use permit for violations of the performance standards and for failure to file annual air quality reports, but no notice and hearing precede revocation and Sections 616.1 and 617.2 of the Municipalities Planning Code are not cited.
Township-approved experts paid by the applicant prepare studies; township review cost not assigned, § 127-68.1.C(2)(b)[7]
Owner and operator named in the Developer's Agreement after approval, § 127-68.1.D(5)
Benefits & exceptionsHide benefits & exceptions1
Approval pathway: Conditional use in the I-1 Industrial District
Sources
Thank you to the Pennsylvania Data Center Ordinance Tracker for providing proposed local ordinance data for PA. Citation: padatacenterordinances.org, accessed November 3, 2026.Cookie preferences · Report missing data