Amwell Township

Anti-Data Center Policies

Pennsylvania requires data centers over 25 megawatts to obtain local approvals and meet power, grid-cost, environmental, and community commitments; covered facilities also face annual energy and water reporting. These rules make large projects harder, not impossible, while eligible centers may receive equipment tax breaks.

Rating and summary from Pennsylvania statewide as there are no scored current or future laws outside temporary restrictions for Amwell Township.

Incentives

Financial Incentive

Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.

pending · Amwell Township
The draft dated June 19, 2026 was presented at a public meeting on June 22, 2026, data center rules also appear in Section 400.21 of a draft township-wide zoning ordinance that the Planning Commission took comment on July 27, 2026, and the Supervisors' September 10, 2026 agenda listed no adoption vote or hearing on either draft.Amwell Township, Washington County — proposed data-center ordinance (None Adopted)

What this means

The proposal would impose setbacks from homes or other protected places and minimum site-size requirements. The limits sharply reduce usable sites or workable project designs, making development substantially harder despite an available approval route.

Restrictions & requirementsHide restrictions & requirements35
  • Conditional use; approvals expire without a building permit within 1 year, Section 4.A

  • Limited to the I District; CRP and CREP lands barred, but no preserved farmland or agricultural security area bar, Section 3.H

  • Section 4.D(4) caps data centers at 35 ft and rooftop equipment at 5 ft above the roof edge, with screening under Section 4.C(1), and Section 4.D(5) refers to the Light Industrial District height standard without stating it.

  • Environmental site assessment and impact study, Section 3.G(2); no riparian buffer

  • Section 8.A sets 40 dBA at night and 45 dBA in the day at the property line, measured with ANSI S1.4-2014 meters under generally accepted industry criteria.

  • Section 8.A bars noise more than 10 dBA above pre-development ambient, but ambient is not defined as L90 and no floor is stated.

  • 60 dBC day, 50 dBC night, Section 8.A

  • Section 8.A(1) to (3) requires a pre-construction study under typical operating conditions, an interim study at building permit, and an as-built study six months after occupancy, using ANSI S1.4 meters, but no study is required at full operating load.

  • Weekdays 8 a.m. to 8 p.m. only, 120 hours per generator per year, Sections 4.I and 10.D

  • ISO residential vibration curve and vibration study; not a none-perceptible standard, Section 8.A(4)-(5).

  • Public water only; private wells and surface water barred, Section 4.F(1)

  • Closed-loop systems named in water conservation rule; evaporative cooling not restricted, Section 4.F(5)

  • Projected average and peak water demand disclosed, Section 4.F(2)

  • Cooling wastewater disposal shown in the application with chemicals listed, Section 4.F(6)-(7).

  • Erosion and sediment control plan tied to stormwater management, Section 3.G(2)

  • EPA Tier 4 diesel generators and DEP air permit; no annual emissions testing, Section 4.I

  • Only heat detection systems; no waste heat plan

  • E-waste to approved disposal site; waste streams listed in decommissioning plan, Sections 3.F(5) and 10.J

  • Utility commitment letter and line capacity statement; no electrical inspection, Sections 3.C and 4.G(1).

  • LEED BD+C rating only; no energy usage plan, Section 4.G(2)

  • On-site generation is a separate use with a 1,500-ft setback, Sections 4.G(4) and 4.I.

  • Substations set back 1,500 ft; equipment enclosed or screened; no buried line rule, Sections 4.C(1) and 4.G(3)

  • 100-ft planted buffer along all exterior boundaries, Section 4.C(2).

  • Equipment enclosed or screened, 8-ft solid fence; no 12-ft or acoustic screening, Section 4.C

  • Elevations and photo simulations may be required, Section 10.A

  • Emergency response plan and posted contacts; no fire company review, annual update, or radio rule, Section 6.E

  • Hazardous materials plan; 1,500-ft setback for power generation structures; no spill containment stated, Sections 4.I and 10.K

  • Annual fire safety inspections; no electrical inspection, Section 6.E(6)

  • Haul roads identified and road bonds allowed; no construction hours, Section 5

  • 125% security; no closure notice or removal deadline confirmed, Section 9

  • Plan updated at 5 years and every 3 years after, Section 9.D(1)

  • One as-built sound study; annual report covers generator hours and complaints, not noise, water, or power, Sections 8.A(3) and 10.H

  • Section 4.K makes failure to maintain security fencing grounds for revocation of the conditional use, and Section 13.A provides civil enforcement with fines up to $500 a day, but no notice and hearing is required before revocation and Sections 616.1 and 617.2 of the MPC are not cited.

  • Township engineer paid by applicant for road review only; study review cost not assigned, Section 5.B

  • Applicant, owner, and operating entity named; end user not required, Section 3.C(1)(a)

Benefits & exceptionsHide benefits & exceptions1
  • Proposed approval pathway: Proposed conditional use in the Light Industrial District

Sources

Thank you to the Pennsylvania Data Center Ordinance Tracker for providing proposed local ordinance data for PA. Citation: padatacenterordinances.org, accessed November 3, 2026.Cookie preferences · Report missing data