City of Allentown

Anti-Data Center Policies

Allentown requires data centers to undergo extensive studies and reviews, meet siting, size, and setback limits, and pay for utility upgrades and cleanup guarantees. They are not banned, but these rules can add substantial costs and delays.

Incentives

Financial Incentive

Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.

current law · City of Allentown
Requires public notice and detailed plans for large data centers, while setting rules for where they can be built and how they address noise, water, energy, safety, and eventual closure.Bill 52 (Legistar File 15-8508), amendment to Allentown data-center zoning ordinance

What this means

The measure would make data center projects substantially harder by requiring extensive environmental, noise, water, power, and emergency plans, while also limiting where and how large buildings can be. It also requires a financial guarantee covering the full estimated cost of decommissioning and site restoration, adding significant cost; these are major hurdles, though not an outright ban.

People behind it

  • Listed as a sponsor of Bill 52.

  • Listed as a sponsor of Bill 52.

  • Listed as a sponsor of Bill 52.

Show 1 more peopleShow fewer people
  • Identified as the department or bureau from which the bill originated and as the source of the initiative.

Restrictions & requirementsHide restrictions & requirements20
  • A new data center larger than 50,000 square feet must have a public meeting before the first relevant Zoning Hearing Board or Planning Commission meeting; if only a zoning permit is required, the meeting must be held at least two weeks before filing. The meeting must be publicly advertised and include an applicant representative able to answer questions. Public meeting requirement

  • For a new data center larger than 50,000 square feet, the applicant must maintain a public project website beginning at least two weeks before the public meeting and through final land-development approval, with project details, meeting dates, timelines, and permit status. Project website requirement

  • The measure’s summary states that data centers are removed from the IG zone. Removing the use from the IG zone

  • A data center must be at least 75 feet from a public-street right-of-way, 500 feet from specified residential, civic and institutional uses, child-care uses, and MX-N-, GX-N-, or N-zoned lots, and 50 feet from other lot lines. The 500-foot rule excludes cemeteries, governmental uses, transportation facilities, and infrastructure and utilities from the specified civic and institutional category. Setback requirements

  • A data center larger than 50,000 square feet must have a minimum lot area of 5 acres in the IG zone and 8 acres in the IM zone. Minimum lot area

  • A landscaped buffer at least 25 feet wide, including shade trees, evergreen trees, and planting beds, must be provided around the use’s perimeter, except at necessary perpendicular crossings; the tree rows must be staggered. Landscaped buffer

  • The Zoning Hearing Board may require additional berms, landscaping, fencing, or setbacks to protect public health and safety and avoid conflicts with neighboring uses. Additional protective measures

  • Applicants must submit a qualified professional’s environmental-impact evaluation covering air, soil and water quality, groundwater, wildlife and habitat, and greenhouse-gas emissions, considering typical and adverse conditions and proposing mitigation where necessary. Environmental impact evaluation

  • Applicants must provide pre- and post-construction sound studies covering full-spectrum noise, daytime and nighttime conditions, and worst-case full-buildout operations, plus a vibration study showing vibration will not be perceptible beyond the property line. Before occupancy, an as-built sound study is required; another is due six months after the certificate of occupancy and may be required later by the City. Noise and vibration studies

  • If an as-built study finds a noise violation or conditions inconsistent with the study’s representations or mitigation measures, the City may cancel, revoke, withhold, or suspend a permit. Permit enforcement

  • Applicants must submit a certified water-utilization report and documentation that the Lehigh County Authority will supply the needed water. If utility capacity is insufficient or detrimental impacts are identified, the applicant must fund necessary infrastructure or system improvements. Nonpublic water sources require a feasibility study and applicable agency review and approval; wastewater disposal must also be demonstrated and approved. Water and sewer requirements

  • Applicants must submit a certified energy-management plan and identify renewable-energy contributions. For a grid connection, they must document available capacity and service and assess impacts on electric rates or availability; necessary mitigation or system improvements are at the applicant’s expense. Power-supply requirements

  • Applicants must submit electronic-waste and decommissioning/site-restoration plans. After at least 12 months of cessation, equipment and related improvements must be removed and the site restored, unless the City allows more time because operations are intended to resume in the near future. Removal must begin within one year after that period and finish within three years after work begins. A bond or letter of credit equal to 100% of estimated decommissioning and restoration costs must be posted before land development, earth disturbance, or building permits. Decommissioning and financial security

  • A certified thermal-impact mitigation plan, including strategies for waste-heat reuse or dissipation, is required. Thermal mitigation plan

  • Applicants must submit an emergency-response plan for review and acceptance by the City Fire Department and Lehigh County Office of Emergency Management. Data centers with energy storage must demonstrate compliance with NFPA Standard 855 or similar standards and include battery-specific fire suppression; approval requires sufficiently protective fire, containment, ventilation, and evacuation procedures. Emergency-management requirements

  • Building façades facing a public street, specified nearby zoning or residential uses, or other designated frontages must incorporate at least two specified design elements every 150 horizontal feet. Façade design requirements

  • At least one off-street loading space must be provided. Loading-space requirement

  • Building height is limited to 50 feet. On lots of at least 15 acres, height may reach 70 feet only with special-exception approval and compliance with the referenced supplemental building regulations. Height limits and exception

  • Required plans, studies, assessments, and strategies must be submitted with the zoning-permit application, or with the land-development application if that is filed first. The City may require supplements or amendments before zoning approval; required documents must be reviewed and accepted by the City Engineer or a third-party consultant, whose reasonable review fees may be charged to the applicant. Document review and consultant fees

  • Data-center applications must be referred to the City Planning Commission and Environmental Advisory Council for review and comment; the applicant must review their feedback and incorporate it into necessary mitigation strategies. Required agency referrals

Benefits & exceptionsHide benefits & exceptions4
  • The ordinance recognizes data centers as either a principal or accessory use, allowing for the possibility of data center operations alongside another permitted use. The use table and other zoning rules still apply. principal or accessory use

  • On lots of at least 15 acres, building height may reach 70 feet with special-exception approval, rather than the standard 50-foot maximum. maximum of 70 feet

  • If necessary electric-grid improvements are deemed infeasible by the City Engineer and utility provider, on-site utility methods may be considered, subject to City ordinances. on-site utility methods may be considered

  • If operations cease for 12 months, the City may agree to give the owner or operator more time before decommissioning requirements apply when there is intent to resume the use in the near future. allow the owner or operator additional time

Sources

current law · City of Allentown
Creates a specific data center zoning category and requires setbacks, environmental and utility studies, emergency plans, and other safeguards for new facilities.Bill 20 (Legistar File 15-8288), enacted as Ordinance No. 16223

What this means

The measure creates a defined zoning category for data centers, but requires extensive studies, plans, buffers, and reviews before approval. It also makes applicants pay for needed utility upgrades and sets limits on location, lot size, and building height, creating significant costs and barriers. Supplemental use regulations

People behind it

  • Identified as the measure’s sponsor.

Restrictions & requirementsHide restrictions & requirements26
  • New data centers and accessory uses must be at least 75 feet from a public-street right-of-way, 200 feet from specified residential, civic/institutional, child-care, or zoned lots, and 50 feet from other lot lines. Required separation distances

  • A data center with more than 50,000 square feet of indoor gross floor area requires at least 5 acres in the IG zone or 8 acres in the IM zone. Minimum lot area

  • A landscaped buffer at least 25 feet wide, including shade trees, evergreen trees, and planting beds, is required around the use, except at necessary perpendicular crossings; tree rows must be staggered. Landscaped buffer

  • The zoning hearing board may require berms, landscaping, fencing, and additional setbacks to protect public health and safety or avoid conflicts with neighboring uses. Additional site protections

  • Applicants must provide a narrative describing on-site activities, operating hours, expected vehicle trips, and materials or equipment stored on site. Operations narrative

  • Applicants must submit a qualified professional’s environmental-impact evaluation covering air, soil, water, groundwater, wildlife and habitat, and greenhouse-gas emissions under typical and relevant adverse conditions, with mitigation strategies where necessary. Environmental-impact evaluation

  • A licensed acoustics professional or qualifying engineer must prepare a sound study demonstrating compliance with the city’s noise rules and assessing persistent tonal or low-frequency noise; the study must identify recommended mitigation. Sound study

  • An as-built sound study is required six months after the certificate of occupancy and again when the City requests one. Follow-up sound study

  • A qualified professional must provide a vibration study demonstrating that vibration will not be perceptible to a person beyond the property line. Vibration study

  • A professional engineer must certify a Water Utilization Report detailing water intake, sources, discharge, destinations, and cooling-system type and efficiency, and demonstrating stormwater compliance; the City may require amended or supplemental reports before zoning approval. Water Utilization Report

  • Applicants must provide Lehigh County Authority certification that it will supply the required water. If utility capacity is insufficient or a detrimental impact is identified, the applicant must pay for necessary infrastructure upgrades or system improvements. Water supply and upgrades

  • For nonpublic water sources, applicants must submit a water-feasibility study addressing supply and impacts on nearby wells and waters; applicable withdrawals require review and approval by the Delaware River Basin Commission, Lehigh County Authority, and Pennsylvania DEP. Nonpublic-water requirements

  • Applicants must demonstrate adequate wastewater disposal approved by Pennsylvania DEP; cooling water may not be discharged into the city’s municipal separate storm sewer system. Wastewater and discharge rules

  • Applicants must identify the share of energy use met by on-site renewable generation and submit an engineer-certified Energy Management Plan covering annual electricity demand, supply sources, storage capacity if applicable, and energy-efficiency and clean-energy efforts. Energy disclosures and plan

  • For a proposed grid connection, applicants must provide the electric provider’s certification of available capacity and willingness to serve, plus an assessment of effects on electric rates or availability for other users. If capacity is insufficient or detrimental impacts are found, applicants must fund necessary system improvements; on-site utility methods may be considered if improvements are deemed infeasible by the City Engineer and utility provider. Grid documentation and improvements

  • Applicants must submit an Electronic Waste Plan for safe removal, recycling, or disposal of server infrastructure, hazardous materials, batteries, and related waste when the facility is updated or decommissioned. Electronic Waste Plan

  • An engineer-certified Thermal Impact Mitigation Plan must include strategies for reusing or dissipating waste heat. Thermal Impact Mitigation Plan

  • Applicants must submit an Emergency Response Plan reviewed and accepted by the City Fire Department and Lehigh County Office of Emergency Management during special-exception or land-development review. It must address fire response, containment, ventilation, evacuation, emergency access, responder training, and annual professional fire-safety inspections. Emergency Response Plan requirements

  • Data centers proposing battery or other energy storage must demonstrate compliance with NFPA Standard 855 or similar standards and install fire-suppression systems designed specifically for battery storage. Energy-storage fire safety

  • A data center cannot be approved unless its fire-suppression, containment, ventilation, and evacuation procedures are shown to adequately protect public health, safety, and welfare. Approval condition for fire procedures

  • Façades facing a public street, specified nearby zoning lots, an existing residential use, or other specified frontages must include at least two listed design features every 150 horizontal feet. Façade design rules

  • At least one off-street loading space is required for each data center. Loading-space requirement

  • Building height is limited to 50 feet. On lots of at least 15 acres, height may reach 70 feet only with special-exception approval and compliance with specified workshop-building regulations. Height limit and exception

  • Required plans, studies, evaluations, assessments, and strategies must accompany the zoning-permit application, or the land-development application if that is submitted first; the City may require supplements or amendments before zoning approval. Application submissions and review

  • Data-center applications must be referred to the Allentown City Planning Commission and Environmental Advisory Council for review and comment; applicants must review and incorporate their feedback into necessary mitigation strategies. Commission and council review

  • All required documents must be reviewed and accepted by the City Engineer or a third-party consultant. If the City requires third-party review, the applicant must pay the reasonable fees. Technical review and applicant fees

Benefits & exceptionsHide benefits & exceptions5
  • The ordinance creates an express Data Center Use category and adds it to the zoning use table and Manufacturing & Industry group. The provided text does not identify which zoning districts allow the use. Adds the use category Data Center Use.

  • The definition recognizes a broad range of accessory facilities and equipment—including substations, utilities, cooling and water-treatment facilities, and temporary backup generators—as data center accessory uses. They must be on the same tract or adjacent parcels developed as one unified project; energy-generation systems intended to supply normal operations are excluded. Data Center Accessory Use.

  • Buildings may reach 70 feet through special-exception approval on lots of at least 15 acres; otherwise, the stated maximum height is 50 feet. The supplemental workshop-building regulations also apply. On lots 15 acres or larger.

  • If the City Engineer and utility provider determine necessary electric-system improvements are infeasible, on-site utility methods may be considered, subject to City ordinances. on-site utility methods may be considered.

  • The ordinance provides a route to use nonpublic water sources, subject to a feasibility study and applicable review and approval by the Delaware River Basin Commission, Lehigh County Authority, and Pennsylvania DEP. If the use uses nonpublic water sources.

Sources

current law · City of Allentown
Requires data center projects to provide public notice and follow rules for location, noise, water and power use, environmental impacts, emergency response, and cleanup when operations end.Allentown Zoning Ordinance, including Chapter 660, Section 660-38.H(2) (Ordinance No. 16166, amended by Ordinance No. 16223 and Bill 52 / Ordinance No. 16232)

What this means

The measure would make new data centers significantly harder to build by requiring extensive studies and approvals, a bond covering estimated cleanup costs, and greater separation from some uses. It would not ban data centers outright, but these requirements could add substantial cost and delay.

People behind it

  • Listed as a sponsor of the bill.

  • Listed as a sponsor of the bill.

  • Listed as a sponsor of the bill.

Show 3 more peopleShow fewer people
  • Responsible for administering and enforcing the ordinance.

  • Identified, together with CED, as the source of the bill.

  • Identified, together with City Council, as the source of the bill.

Restrictions & requirementsHide restrictions & requirements20
  • The bill summary says data centers would be removed from the IG zone, restricting where they may locate.

  • New data centers and accessory data center uses must be at least 75 feet from a public street right-of-way, 500 feet from specified residential, civic, child-care, and designated-zoned lots, and 50 feet from other lot lines.

  • Data centers over 50,000 square feet must have a lot of at least 5 acres in the IG zone or 8 acres in the IM zone.

  • Before a new principal data center larger than 50,000 square feet is established, the applicant must hold an advertised public meeting before the first relevant Zoning Hearing Board or Planning Commission meeting. If only a zoning permit is needed, the meeting must occur two weeks before submission. The applicant must maintain a public project website starting at least two weeks before the meeting and through final land development approval.

  • Applicants must submit a qualified professional’s evaluation of potential impacts on air, soil, water, groundwater, wildlife and habitat, and greenhouse gas emissions, considering typical and adverse conditions and identifying mitigation where needed.

  • Applicants must provide a certified water-utilization report, documentation that the Lehigh County Authority will supply needed water, and—if using a nonpublic water source—an approved feasibility study. They must fund necessary utility improvements if capacity is insufficient or impacts are detrimental, and obtain PA DEP approval for adequate wastewater disposal.

  • Applicants must identify renewable energy use and submit a certified Energy Management Plan. For grid connections, they must provide utility capacity and service documentation and assess effects on electricity rates or availability; they must fund necessary improvements if capacity is insufficient or impacts are detrimental.

  • A qualified, independent acoustical professional must conduct full-spectrum sound studies covering baseline and worst-case operations, nighttime noise, generators, and vibration. Vibration must not be perceptible beyond the property line. An as-built study is required before occupancy, another six months after occupancy, and further studies may be requested. Noise violations or departures from approved representations may result in permit cancellation, revocation, withholding, or suspension.

  • Applicants must submit electronic-waste and decommissioning and site-restoration plans. After at least 12 months of ceased operation, equipment and improvements must be removed and the site restored unless the City allows more time because use is expected to resume soon. Removal must begin within one year after that 12-month period and finish within three years after work begins. Before land development, earth disturbance, or building permits, the applicant must post a bond or letter of credit equal to 100% of estimated removal and restoration costs.

  • Applicants must submit a certified Thermal Impact Mitigation Plan addressing waste-heat reuse or dissipation.

  • Applicants must submit an Emergency Response Plan reviewed and accepted by the City Fire Department and Lehigh County Office of Emergency Management, including specified fire, evacuation, access, training, and inspection procedures. Battery or other energy-storage systems must meet NFPA 855 or similar standards and include battery-specific fire suppression; approval requires adequate protection of public health and safety.

  • Building façades facing specified streets, lots, or uses must incorporate at least two listed design elements every 150 horizontal feet.

  • Each data center must provide at least one off-street loading space. Building height is limited to 50 feet, except that a lot of at least 15 acres may seek special-exception approval for a height up to 70 feet.

  • Required plans, studies, evaluations, assessments, and strategies must be submitted with the zoning permit application or an earlier land development application. They are subject to City review and may require supplementation; the applicant must pay reasonable third-party review fees when required. Applications are also referred to the City Planning Commission and Environmental Advisory Council for review and comment.

  • Under the zoning ordinance, a zoning permit is required before a new or expanded use or building proceeds, and a building permit cannot issue until the zoning permit is issued. A site plan is generally required for a new principal nonresidential building and for a nonresidential expansion adding more than 2,000 square feet.

  • Under the zoning ordinance, uses not specifically listed must be classified by the zoning officer; a use that cannot reasonably be classified in a listed category is prohibited. Whether a data center is allowed therefore depends on its classification and the site’s zoning district.

  • Under the zoning ordinance, projects with at least 5 acres of developable land generally must satisfy Master Plan Development requirements before subdivision or site-plan submission; developments in industrial and public-institutional zones are exempt.

  • If classified as manufacturing or industry, a data center must provide off-street parking based on employment: one space per four employees for uses up to 50,000 square feet and one per two employees for uses over 50,000 square feet, except in MX-D and GX-D zones.

  • Under the zoning ordinance, buildings over 4,000 square feet used for business, trade, or industry must provide loading spaces: one per 10,000 square feet for manufacturing and industry uses or one per 5,000 square feet for warehousing and distribution uses.

  • All uses must meet operating performance standards: recurring noxious odors or dust may not be detectable beyond the property, and noise and vibration must comply with Chapter 400.

Benefits & exceptionsHide benefits & exceptions2
  • On lots of at least 15 acres, a data center building may reach 70 feet in height with special exception approval and compliance with the referenced supplemental regulations. Height may be increased to a maximum of 70 feet.

  • If grid-system improvements needed for a data center are determined infeasible by the City Engineer and the utility provider, on-site utility methods may be considered, subject to City ordinances. On-site utility methods may be considered.

Sources

current law · Allentown City
The rules first adopted by Ordinance No. 16223 on June 17, 2026, were tightened by Ordinance No. 16232, which City Council passed on August 5, 2026, and the Mayor signed on August 10, 2026.Allentown City, Lehigh County — data-center ordinance (No. 16232)

What this means

The measure imposes setbacks from homes or other protected places. Data centers still have an approval route, but the siting or operating limits significantly narrow feasible projects.

Restrictions & requirementsHide restrictions & requirements25
  • Environmental impact evaluation required, Ord. 16232, § 660-38.H

  • Chapter 400 Noise limits stated to apply, Ord. 16232, § 660-38.H

  • Full spectrum dBA and dBC study; no dBC limit, Ord. 16232, § 660-38.H

  • Studies at submittal, before occupancy, and six months after; none at building permit, Ord. 16232, § 660-38.H

  • Generator sound levels studied; no testing limits

  • Vibration study showing none past the property line, Ord. 16232, § 660-38.H.

  • Authority supply certification; feasibility study for non-public sources, Ord. 16232, § 660-38.H

  • Cooling system type disclosed in Water Utilization Report, Ord. 16232, § 660-38.H

  • Daily intake volume disclosed; no cap or drought plan, Ord. 16232, § 660-38.H

  • Section 660-38.H(h)(5) requires the applicant to demonstrate that adequate wastewater disposal has been provided and approved by the PA DEP and bars cooling water discharge to the MS4, and Section 660-38.H(h)(1) requires a Water Utilization Report of discharge volumes and destinations before any zoning approval.

  • Thermal Impact Mitigation Plan with waste heat reuse, Ord. 16232, § 660-38.H.

  • Electronic Waste Plan; batteries and refrigerants disposed per law, recycling not required, Ord. 16232, § 660-38.H

  • Electric provider capacity certification; no third-party inspection, Ord. 16232, § 660-38.H.

  • Energy Management Plan; renewables encouraged only, Ord. 16232, § 660-38.H

  • Section 660-38.H(i)(3) and (4) require an assessment identifying impacts on electric rates or availability attributable to the use and require the applicant to provide, at its own expense, the system improvements needed where capacity is insufficient.

  • 25-ft landscaped buffer, Ord. 16232, § 660-38.H

  • Plan accepted by Fire Department and county OEM; no updates, radio, or contacts, Ord. 16232, § 660-38.H

  • Plan must ensure responder training; no funding, Ord. 16232, § 660-38.H

  • Annual fire safety inspections, Ord. 16232, § 660-38.H

  • Trip description only; no traffic study

  • Bond of 100% of cost; removal within one to three years, Ord. 16232, § 660-38.H

  • As-built sound studies after opening and on request, Ord. 16232, § 660-38.H

  • Section 660-38.H(g)(6) authorizes the zoning officer to cancel, revoke, withhold, or suspend a permit for noise violations under Section 660-123.C, but the text read provides no notice or hearing before revocation.

  • Section 660-38.H(r) makes the applicant pay reasonable fees for third-party consultants who review the required documents, but the review occurs before zoning approval at the special exception stage, not in land development review.

  • Public meeting before review and website kept through final approval, Ord. 16232, § 660-38.H

Benefits & exceptionsHide benefits & exceptions1
  • Approval pathway: Special exception in the Industrial Manufacturing district