Vienna Township
Mixed Data Center Policies
Ohio offers qualifying data centers significant sales-tax exemptions on equipment, subject to investment, payroll, reporting, and other conditions, while fees apply to participants. New exemption requests are paused, which may raise costs for new projects; data centers are not banned.
Rating and summary from Ohio statewide as there are no scored current or future laws outside temporary restrictions for Vienna Township.
expired · Vienna TownshipImposes a 180-day moratorium on accepting data-center applications, issuing permits, and constructing data centers in Vienna Township, as approved by the Board of Trustees on February 17 and confirmed unanimously on March 3, 2026 (approved a 180-day moratorium).Vienna Township Data Center Moratorium Resolution (2026)
What this means
The township approved a 180-day pause on data-center applications, permits, and construction, then extended the moratorium by 60 days. That is a major, though temporary, obstacle to building or expanding data centers; the proposed zoning amendment’s specific rules are not included in the sources.
Timing
- Ends
- Oct 16, 2026
The 180-day data-center moratorium was later extended by 60 days, with the stated expiration date of October 16, 2026 (60 day extension ... to October 16, 2026).
People behind it
- Mr. Haddle
Moved the motion establishing the 180-day moratorium on data-center applications, permitting, and construction, and later moved the motion recording Ms. Ellis's affirmative vote.
- Mr. Pegg
Seconded the motion establishing the data-center moratorium.
- Ms. Ellis
Seconded the motion recording her affirmative vote on the data-center moratorium and moved the motion extending the moratorium to October 16, 2026.
Show 2 more peopleShow fewer people
- Vienna Township Zoning Commission
Submitted the proposed text amendment to Vienna Township Zoning Resolution Section 53 concerning data centers.
- Vienna Township Board of Trustees
Responsible for considering and approving, denying, or returning the proposed data-center zoning language.
Restrictions & requirementsHide restrictions & requirements2
A 180-day moratorium was imposed on accepting data-center applications, issuing permits, and constructing data centers in Vienna Township; the moratorium was later extended by 60 days through October 16, 2026.
Vienna Township scheduled a public hearing and special trustee meeting to consider a proposed zoning-text amendment specifically governing data centers. The trustees may approve, deny, or return the proposed amendment to the Zoning Commission.