Loading map…
Regbase

The Data Center Divide

City of Twinsburg

This restriction takes precedence while in effect. The rating below excludes temporary restrictions.

Strongly Pro-Data Center Policies

Twinsburg’s enacted ordinance blocks zoning and occupancy permits for data centers as a main use for up to 12 months and bars existing businesses from expanding into that use; it does not expressly stop current operations.

Rating from Summit County as there are no scored current or future laws outside temporary restrictions for City of Twinsburg.

current law · City of Twinsburg
Establishes a temporary moratorium of up to 12 months on accepting or considering applications and issuing zoning or occupancy permits for data centers as a principal use, including similar-use pathways and expansions of existing uses into data centers.City of Twinsburg Ordinance No. 2026-065

What this means

It would block zoning and occupancy permits for up to 12 months for buildings or uses involving data centers as a main use, and would prevent existing businesses from expanding into that use (12-month moratorium and expansion restriction). It does not expressly shut down existing data center operations, but the temporary halt would make new development and relevant expansions substantially harder.

Timing

Ends
Twelve months from the effective date of the ordinance, or earlier if changes are enacted to amend the Codified Ordinances or Council explicitly revokes the moratorium, whichever occurs first.

The moratorium applies to accepting, considering, or issuing zoning or occupancy permits for data centers as a principal use, and prohibits existing businesses from expanding into such uses during the moratorium.

People behind it

  • Mayor who requested that legislation establishing the data-center moratorium be created.

  • Recommended adoption of the moratorium and was tasked with studying possible data-center regulations.

  • Moved the motions to suspend the three-reading rule and adopt Ordinance 2026-065 as an emergency.

Show 2 more peopleShow fewer people
  • Seconded the motions to suspend the three-reading rule and adopt Ordinance 2026-065 as an emergency.

  • Enacted the ordinance establishing the 12-month data-center moratorium.

Restrictions & requirementsHide restrictions & requirements4
  • Data centers are not currently permitted as a principal use under the city's planning and zoning code.

  • For up to 12 months, the city may not accept for filing or consideration, or issue zoning or occupancy permits, for any building, structure, use, or change of use involving a data center as a principal use.

  • Existing businesses may not expand in any way that would involve a data center as a principal use during the moratorium.

  • The moratorium continues for 12 months from the ordinance's effective date, unless zoning-code changes address the issue or Council expressly revokes the moratorium earlier.

Sources

Data provided by Regbase · Cookie preferences · Report missing data