Village of Perry

Mixed Data Center Policies

Ohio offers qualifying data centers significant sales-tax exemptions on equipment, subject to investment, payroll, reporting, and other conditions, while fees apply to participants. New exemption requests are paused, which may raise costs for new projects; data centers are not banned.

Rating and summary from Ohio statewide as there are no scored current or future laws outside temporary restrictions for Village of Perry.

current law · Village of Perry
This proposed initiative would require hyperscale data-center developers seeking special tax incentives to provide financial guarantees to the community.Perry Issue 16: Hyperscale Data Center Tax Incentive Financial Guarantee Requirement

Sources

No source provided.

repealed · Village of Perry; the 2026 moratorium excludes the property known as Champion Farm
Prohibits the Village of Perry from accepting or approving data-center applications for one year, except for the Champion Farm property.Village of Perry Ordinance 2025-02 and Ordinance 2025-05

What this means

The measure would pause acceptance and approval of data-center applications for one year, making new projects and expansions substantially harder during that period. The moratorium would not cover Champion Farm, but its broad reach and duration make the effect strongly restrictive (one-year moratorium, excluding Champion Farm).

Timing

Ends
one year after enactment; the provided text does not specify the starting date

The one-year moratorium excludes the property known as “Champion Farm” (one-year moratorium).

Restrictions & requirementsHide restrictions & requirements1
  • The ordinance imposes a one-year moratorium on accepting and approving data-center applications within the Village, except for the property known as “Champion Farm.” (one-year moratorium)

Benefits & exceptionsHide benefits & exceptions1
  • Ordinance 2025-02 amended the zoning code to add data center campuses to Industrial District uses and establish special regulations for them; Ordinance 2025-05 later repealed it, so this provision was withdrawn. Added data center campuses Repealing Ordinance No. 2025-02

Sources