Muhlenberg Township

This restriction takes precedence while in effect. The rating below excludes temporary restrictions.

Mixed Data Center Policies

Muhlenberg Township has enacted a 12-month pause on processing data-center zoning-certificate applications, temporarily hindering new development and expansions that require a certificate.

Rating from Ohio statewide as there are no scored current or future laws outside temporary restrictions for Muhlenberg Township.

current law · Muhlenberg Township
This resolution establishes a 12-month moratorium on receiving, processing, issuing, or approving zoning certificates and related applications for data centers in Muhlenberg Township.Muhlenberg Township Resolution 2026-10

What this means

The measure would pause receiving, processing, issuing, or approving zoning-certificate applications for data centers for 12 months, making new development and expansion that needs a certificate substantially harder during that period (“twelve (12) month moratorium”). It is temporary, and the source does not describe a lasting operating restriction, so -4 fits better than an outright ban.

Timing

Ends
2027-02-02 at 23:59

The twelve-month moratorium expires at 11:59 p.m. on February 2, 2027. The Board may rescind it earlier.

People behind it

  • Adopted and enacted Resolution 2026-10 establishing the twelve-month data-center zoning moratorium.

  • Moved the motion to approve Resolution 2026-10.

  • Seconded the motion to approve Resolution 2026-10.

Restrictions & requirementsHide restrictions & requirements1
  • A twelve-month moratorium, effective immediately and lasting until 11:59 p.m. on February 2, 2027, bars the township from receiving, processing, issuing, or approving any application for a zoning certificate for a data center. The trustees may rescind the moratorium earlier.