City of Mount Healthy
Mixed Data Center Policies
Ohio offers qualifying data centers significant sales-tax exemptions on equipment, subject to investment, payroll, reporting, and other conditions, while fees apply to participants. New exemption requests are paused, which may raise costs for new projects; data centers are not banned.
Rating and summary from Ohio statewide as there are no scored current or future laws outside temporary restrictions for City of Mount Healthy.
current law · City of Mt. HealthyTreats data centers as an unlisted use, leaving the city to decide whether each proposal fits an allowed or conditional use category.Mount Healthy Ohio data center-specific laws and bans
Restrictions & requirementsHide restrictions & requirements8
Unlisted-use rule: a use not listed as permitted or conditional in a zoning district is prohibited there. If a proposed use is not specified in any district, the City Manager or designee decides whether it is similar to a listed use; a similar use must follow that use’s requirements, and the decision may be appealed by the affected property owner or agent. Unlisted uses
Zoning permit: a permit is required before constructing or occupying a proposed structure or addition, changing a building or land use, or reoccupying or reusing a nonresidential property. Any required site-plan or conditional-use approval must come first. Permit required
Site-plan review: required for permitted uses in buildings of 5,000 square feet or more, for conditional uses, and for additions to existing buildings or parking areas. Smaller permitted uses generally receive Level A review; qualifying larger or conditional projects receive Planning Commission Level B review. Review levels
Conditional-use approval, if required by the use’s classification: the application must be filed at least 20 days before the meeting, with a fee and site plan; public notice and a hearing are required. Approval expires after 12 months unless construction is complete or the use has begun, with a possible extension of up to 12 months. Conditional-use procedure
Operating limits: uses must not create a nuisance beyond the lot through noise, glare, fumes, odor, dust, vibration, or heat. Light fixtures must be direct-cutoff and prevent light spill or trespass beyond the property. Nuisance and lighting rules
Stormwater limit: development, redevelopment, or changes to a property’s surface characteristics must not cause additional stormwater runoff to flow onto adjacent properties. Stormwater provision
Application costs and guarantees: zoning-code applications and reviews are subject to fees. The approving body may also require a performance guarantee to ensure compliance or completion of improvements; it must be deposited before building permits are issued. Fees and guarantees
Site-plan deadline: approval expires after 12 months unless substantial construction has begun and is continuing. One extension of up to 12 months may be granted if requested in writing before expiration and the stated conditions are met. Expiration