City of Middletown

Anti-Data Center Policies

Middletown is labeled as having an enacted rule, though its description calls it a proposal; it would require on-site treatment of industrial cooling-water discharges and zoning approval, suggest closed-loop systems, and leave data-center classification uncertain.

current law · City of Middletown
Applies general zoning and development rules to data centers but does not establish data-center-specific regulations; the proposed water-treatment measures were only public comments, not enacted law.Middletown Ohio data-center-specific law search (no law identified)

What this means

If enacted, the proposal would add meaningful costs and design requirements by requiring on-site treatment of industrial cooling-water discharges and suggesting closed-loop systems for data centers. Data centers would also need zoning approval and meet applicable site standards, though their exact classification is uncertain.

People behind it

  • Moved approval of Ordinances O2026-24 and O2026-25 and Resolution R2026-12; seconded the Downtown Middletown, Inc. agreement and Resolution R2026-13 motions.

  • Moved approval of Resolution R2026-13 and seconded motions concerning Ordinances O2026-24 and O2026-26; proposed, then rescinded, an amendment to shorten the Downtown Middletown, Inc. agreement.

  • Seconded motions to approve Ordinance O2026-25 and Resolution R2026-12.

Show 4 more peopleShow fewer people
  • Moved the motion to authorize a two-year agreement with Downtown Middletown, Inc.

  • Was authorized to enter into the Downtown Middletown, Inc. agreement and carry out other contracts and actions approved at the meeting.

  • Adopted the development code and may initiate code text or map amendments.

  • Responsible for administering and enforcing the development code.

Restrictions & requirementsHide restrictions & requirements8
  • A data center must be allowed in its zoning district: uses not listed as permitted, permitted with standards, or conditional are prohibited. The Development Code Administrator decides whether an unlisted proposal is substantially similar to a listed use; an applicant who disagrees may appeal or ask the Planning Commission or City Council to initiate a code amendment. Unlisted uses are prohibited.

  • Before land is used or excavation or construction permits are issued, a certificate of zoning compliance is required. The certificate must show compliance with the code, zoning district, other applicable city codes, and approved plans. A certificate of zoning compliance shall be required.

  • If the use requires conditional-use approval under its zoning classification, the Planning Commission must review it at a public hearing and may approve it with modifications or additional conditions, or deny it. The Planning Commission shall hold a public hearing.

  • If a project is reviewed as manufacturing and production with caustic or hazardous materials, the applicant must provide a list of chemicals and document safety precautions. Buildings or structures containing those activities must be at least 600 feet from residential lot lines and 300 feet from other adjacent lot lines. The applicant shall provide the City a list.

  • New uses and activities must meet performance standards: no vibration discernible to human senses (except normal temporary construction vibration), noise and sound rules, and no odor harmful to humans, measured at the property line. No vibration which is discernible.

  • For nonresidential new construction, the zoning-compliance fee is $200 plus $0.01 per square foot, up to $1,000; the code also doubles listed fees for work done without a zoning certificate. Certificate of Zoning Compliance: non-residential (new construction) and fees shall be doubled for work done without a zoning certificate.

  • A certificate of zoning compliance expires after six months unless otherwise stated. An approved building permit must be obtained within one year, although up to two six-month extensions may be granted for good cause. All certificates of zoning compliance shall expire six (6) months.

  • Applications must be determined complete within five business days. If an application is incomplete, the applicant generally has 60 days to correct deficiencies or the filing fee is forfeited and the application withdrawn; a duplicate application cannot be submitted within 365 days after formal denial. within five business days and within 365 calendar days.