City of Marion
Mixed Data Center Policies
Ohio offers qualifying data centers significant sales-tax exemptions on equipment, subject to investment, payroll, reporting, and other conditions, while fees apply to participants. New exemption requests are paused, which may raise costs for new projects; data centers are not banned.
Rating and summary from Ohio statewide as there are no scored current or future laws outside temporary restrictions for City of Marion.
pending · City of MarionProposes a temporary moratorium on establishing, constructing, or expanding data centers in the City of Marion, Ohio, along with renewable-energy requirements, noise limits, environmental protections, possible renewal, and an emergency declaration, as listed as old business in the October 19, 2026 committee agenda.City of Marion, Ohio Legislation 7 — Data Center Ordinance (2026)
What this means
The proposal includes a temporary moratorium on establishing, building, or expanding data centers, which could stop new projects and expansions while it is in effect. It also proposes renewable-energy, noise, and environmental requirements; the agenda does not state how long the moratorium would last or give details of those rules.
Timing
The agenda identifies a proposed temporary moratorium and states that renewal is provided for, but it does not specify an expiration date or ending condition.
People behind it
- Rollins
Identified sponsor of the data center moratorium ordinance.
- Cowell
Identified sponsor of the ordinance authorizing bids and contracts for fuel and road paint.
- R. Smith
Identified sponsor of the resolution creating a special investigative committee.
Show 1 more peopleShow fewer people
- Troiano
Identified sponsor of the ordinances providing additional appropriations for the Commercial Building Code Department and the SCMR Fund.
Restrictions & requirementsHide restrictions & requirements5
Establishes a temporary moratorium on establishing, constructing, or expanding data centers within the City of Marion.
Imposes renewable-energy requirements on data centers.
Imposes noise limits on data centers.
Imposes environmental-protection requirements on data centers.
Provides for renewal of the temporary moratorium.
Sources