Loading map…

City of Lebanon

Mixed Data Center Policies

Lebanon allows data centers in three designated districts only with conditional-use approval, which requires a public hearing and review of neighborhood compatibility and health and safety impacts.

Rating from Ohio statewide as there are no scored current or future laws outside temporary restrictions for City of Lebanon.

current law · City of Lebanon
Restricts data centers to conditional-use approval in Lebanon’s Innovation, Light Industrial, and Heavy Industrial districts.Lebanon Ohio data center zoning provisions

What this means

The measure allows data centers in the Innovation, Light Industrial, and Heavy Industrial districts, but only with conditional-use approval, adding review steps and uncertainty for projects (data centers). Approval requires a public hearing and meeting standards such as compatibility with the neighborhood and avoiding harm to health and safety (conditional-use review criteria).

Timing

Ends
Until a replacement plan is approved and a guarantee is established, or payment is made to the City’s Tree Fund.

The moratorium applies to development permit applications for a site following notice of a tree-protection violation. No extension condition is stated.

People behind it

  • May initiate zoning text amendments and makes the final decision on them.

  • May request that City Council initiate a zoning text amendment and reviews and recommends on amendment applications.

  • Reviews amendment applications, prepares staff reports, and administers the zoning code.

Restrictions & requirementsHide restrictions & requirements7
  • The use table lists data centers as conditional uses in the IN (Innovation), I-1 (Light Industrial), and I-2 (Heavy Industrial) districts; they are not listed as permitted uses in the other business districts. Data Centers

  • A data center conditional-use application requires Planning Commission review and a public hearing. Notice is generally required at least 20 days beforehand; owners within 500 feet receive mailed notice unless more than 100 properties are within that distance, in which case published notice alone is required. Application fees are set by City Council. Conditional Uses

  • The Planning Commission may approve a conditional use with conditions, and approval depends on criteria including compatibility with the neighborhood, compliance with the code, and avoiding harmful effects on public services, health, safety, or nearby property. The approval must be recorded with the Warren County Clerk; it expires if a building permit is not obtained within one year, unless an extension is granted. Conditional use approval

  • New nonresidential development generally requires an approved site plan before a zoning permit can issue; data center projects not qualifying for administrative review go through major site plan review by the Planning Commission. Site plan approval expires if a building permit is not obtained within one year, unless an extension is granted. site plan review

  • In the Innovation District, development must use integrated master-planned site plans and provide pedestrian, bicycle, and vehicle connections; architecture, parking placement, loading-dock visibility, landscaping, and greenspace are also regulated. Innovation District standards

  • In I-1 and I-2 districts, a yard abutting a residential district must have at least a 75-foot setback. Industrial performance standards also regulate noise and emissions, among other impacts; for example, noise limits are reduced by six decibels where an I-1 or I-2 district adjoins residential zoning. industrial setbacks

  • Buildings other than accessory storage buildings must connect to public water and a central sanitary sewer system of adequate capacity and design. public water and sewer

Benefits & exceptionsHide benefits & exceptions2
  • Data centers are allowed as conditional uses in the Innovation (IN), Light Industrial (I-1), and Heavy Industrial (I-2) districts, subject to approval; in IN, they are also subject to the district’s additional standards. “Data Centers”

  • Approved rezonings, site plans, variances, and conditional uses remain valid until their expiration date and are governed by the standards in effect when approved. This protects approved data-center projects from later code changes, subject to applicable expiration terms. “remain valid until their expiration date”

Sources

Cookie preferences · Report missing data