Loading map…

City of Highland Heights

Mixed Data Center Policies

Ohio offers qualifying data centers significant sales-tax exemptions on equipment, subject to investment, payroll, reporting, and other conditions, while fees apply to participants. New exemption requests are paused, which may raise costs for new projects; data centers are not banned.

Rating and summary from Ohio statewide as there are no scored current or future laws outside temporary restrictions for City of Highland Heights.

pending · City of Highland Heights
Would temporarily prohibit data centers in Highland Heights for up to six months while the city reviews its zoning rules.Highland Heights Resolution 46-2026 (2026)

What this means

The proposed measure would pause data center development in the city for up to six months while officials review zoning rules, which could significantly delay projects. The short time limit makes it less restrictive than a permanent ban. The moratorium would last no more than six months.

Timing

Ends
No later than six months from the resolution’s effective date

The agenda describes a moratorium “for a period not to exceed six months from the effective date of this resolution” (source). No calendar expiration date or extension condition is stated.

People behind it

  • Listed with Council as a Whole as responsible for the first reading of Proposed Resolution 46-2026.

  • Listed with Mayor Chuck Brunello Jr. as responsible for the first reading of Proposed Resolution 46-2026.

Restrictions & requirementsHide restrictions & requirements1
  • Imposes a moratorium on data centers for a period not to exceed six months from the resolution’s effective date, while the City reviews its zoning code regarding data-center use.