City of Heath
Anti-Data Center Policies
Heath allows data centers in planned developments, subject to utility, screening, buffering, noise, and fuel-safety requirements that may add costs and approval time. Some rules can be waived, and certain green-space and sidewalk requirements do not apply to data-center-only sites.
current law · City of HeathLimits primary-use data centers to planned-unit-development districts and requires adequate utility access, screening and buffers, noise studies and limits, nonreflective facades, security measures, and fuel-handling safety protocols for on-site generators.Heath Ohio Codified Ordinances Chapter 1190, §1190.06
What this means
The measure allows data centers in a Planned Unit Development, including a smaller site in some cases, but adds requirements for utility access, screening, buffers, noise studies and limits, and safety planning for fuel. These rules could add design costs and approval time, though some requirements can be waived and the measure exempts data-center-only sites from certain green-space and sidewalk rules (data-center standards).
People behind it
- Heath City Council
The City’s legislative body; the data-center standards were enacted in Ordinance 82-2024, which the source says passed on January 21, 2025.
- Heath Planning Commission
Administers the development regulations and reviews PUD development plans, including plans for data centers.
- Chief of the Division of Building and Zoning Inspection
Makes specified determinations under the data-center standards, including decisions about screening, buffers, noise-sensitive uses, and equipment enclosure.
Restrictions & requirementsHide restrictions & requirements16
A data center used as a primary property use is allowed only in a Planned Unit Development (PUD) District: “only be permitted in the PUD District”.
A PUD application normally requires at least 40 acres. A smaller tract may be accepted when the proposed use is solely a data center, but acceptance is not automatic: “only proposed use … is … a data center”.
The PUD process requires a sketch-plan discussion and a formal rezoning application with 14 copies of a preliminary development plan, prepared by specified design and engineering professionals, plus required plans and supporting information: “Fourteen (14) copies of a preliminary development plan”.
PUD approval requires public hearings before the Planning Commission and City Council, with the Commission forwarding a recommendation to Council: “reviewed at a public hearing by the Commission”.
PUD approval lasts three years for submitting and recording the required subdivision plat; without that, approval is void and the land reverts to agricultural zoning unless Council approves an extension: “within the three year time limit”.
The data-center property must have ready and sufficient access to the utilities needed for its size and function, which may include electricity, water, and fiber-optic connectivity: “ready and sufficient access to all utilities”.
Ground-level and rooftop mechanical equipment and other facilities must be screened from major roads, adjacent properties, and incompatible uses. The Building and Zoning chief may modify or waive screening for equipment found to have no adverse impact: “screened from the view of major streets and roads”.
An adequate buffer is required where the data-center property shares a lot line with residential, commercial, or other land uses determined to be incompatible; natural elements are preferred, with solid walls or fencing allowed if natural buffering is unavailable, infeasible, or inadequate: “an adequate buffer zone shall be provided”.
If the property shares a lot line with a noise-sensitive use, the applicant must submit a certified third-party acoustic engineer’s sound study with the rezoning application. Operating sound may not exceed the greater of 55 decibels at the lot line or the measured average baseline there: “must obtain a sound study”.
Cooling, ventilation, and power-generation equipment must be fully enclosed with visually solid materials compatible with the main building. The Building and Zoning chief may waive enclosure when it is infeasible due to manufacturer specifications or safety reasons: “shall be fully enclosed”.
Building facades must be non-reflective unless the Building and Zoning chief finds no adverse impact; any proposed windows must use forced-entry-resistant and fire-resistant glass: “windows must be composed of forced-entry-resistant and fire-resistant glass”.
Adequate security measures are required. If perimeter fencing is permitted, it cannot be chain-link or include barbed wire or similar deterrents: “shall not be chain-link”.
If the data center has a primary or secondary diesel or gas generator, the applicant must confer with appropriate agencies, including the City Fire Department, and develop on-site fuel delivery, handling, and storage safety protocols: “develop necessary safety protocols”.
PUD buildings are generally limited to 35 feet in height unless a different height is indicated and approved in the development plan, and a building’s ground-level floor coverage cannot exceed 50% of its lot or parcel: “shall not exceed thirty-five (35) feet” and “greater than fifty percent (50%)”.
PUD utilities must be underground. The development plan may show below-ground storage facilities only if they are illustrated on the plan: “All utilities shall be placed underground”.
The PUD generally requires common green space equal to at least 20% of gross site area and sidewalks in residential and commercial areas. The green-space and sidewalk requirements do not apply where a parcel’s primary and sole use is a data center: “shall not apply to the development”.
Benefits & exceptionsHide benefits & exceptions9
A data center as a property's primary use is allowed in the PUD District, though it may be located only in that district as a primary use. Only be permitted in the PUD District.
A data-center-only proposal may be accepted for a tract smaller than the usual 40-acre minimum; acceptance is discretionary, not automatic. The only proposed use is for the construction and operation of a data center.
If a parcel's primary and sole use is a data center, the PUD's 20% common-green-space requirement and sidewalk requirements do not apply. Sections 1190.05(c) and 1190.05(i) shall not apply.
The PUD process combines zoning review with some subdivision-plat review, and approval of the PUD development plan also approves the preliminary subdivision plan. Combined review of zoning and some subdivision plat requirements.
The PUD plan can request deviations from City development and subdivision rules, including street widths, block dimensions, sidewalks, and rights-of-way; an approved deviation does not require a separate Board of Zoning Appeals variance or waiver. Approval is subject to review and findings concerning PUD intent, design benefits, safety, infrastructure, and maintenance. A separate variance or waiver ... shall not be required.
Where screening is required, the Building and Zoning Inspection chief may modify or waive it for particular equipment or facilities determined to have no adverse impact on adjacent property or the public. Screening requirements ... may be modified or waived.
The noise limit is the greater of 55 decibels at the property line or the average baseline level measured there in the required study. The study is required when the property shares a lot line with residential, commercial, or other noise-sensitive zoning. The greater of ... fifty-five decibels ... or ... average baseline sound levels.
The City may waive the requirement to fully enclose cooling, ventilation, or power-generation equipment if full enclosure is infeasible based on manufacturer specifications or safety reasons. May be waived ... if ... full enclosure is not feasible.
A reflective data-center facade may be allowed if the Building and Zoning Inspection chief determines it will not adversely affect adjacent properties or the public. A reflective building facade will not have any adverse impact.
Sources
failed · City of HeathRequires primary-use data centers to locate in a planned development district and meet rules for utility access, screening, buffering, noise, building facades, security, and fuel handling.No Heath-specific data-center regulations found in available sources
What this means
The measure allows data centers through the PUD process, but adds potentially costly requirements such as sound studies, noise limits, screening, buffers, and enclosed equipment (noise mitigation requirements). Some burdens are offset: a data-center-only site is exempt from the usual green-space and sidewalk rules (those standards shall not apply).
People behind it
- Heath Planning Commission
The City identifies the Commission as administering development regulations; under the PUD process, it reviews development plans and makes recommendations.
- Heath Building and Zoning Department
The City identifies the Department as responsible for reviewing development plans and enforcing zoning ordinances.
Restrictions & requirementsHide restrictions & requirements11
A data center that is the primary use of a property is permitted only in a PUD district. That requires PUD rezoning and development-plan review, including public hearings before the Planning Commission and City Council; the approved preliminary plan also requires a subdivision plat to be recorded within three years or approval is void unless extended. Data centers are limited to the PUD District PUD approval and three-year deadline
PUD applications normally require a tract of at least 40 acres. A smaller application may be accepted when the data center is the tract’s only proposed use. Minimum tract size and data-center exception
The property must have ready and sufficient access to the utilities needed for the data center’s function and size, which may include electricity, water, and fiber-optic connectivity. Ready and sufficient access to utilities
Ground-level and rooftop mechanical equipment and other data-center facilities must be screened from major roads, adjacent properties, and properties with uses deemed incompatible. Screening may use buildings, berms, vegetation, trees, shrubs, or solid walls or fences; the City may modify or waive it for facilities found to have no adverse impact. Screening of data-center facilities
An adequate buffer is required where the data-center property shares a lot line with residential, commercial, or other land uses deemed incompatible. Native vegetation, trees, shrubs, or berms are preferred; solid, visually appealing walls or fencing may be used if natural elements are unavailable, infeasible, or inadequate. Buffer zone requirement
If the property shares a lot line with residential, commercial, or other noise-sensitive property, the applicant must obtain a certified third-party acoustic study documenting baseline sound levels, including measurements at each lot line, and submit it with the rezoning application. While operating, the data center may not exceed the greater of 55 decibels at the lot line or the average baseline levels measured at any lot line. Associated cooling, ventilation, and power-generation equipment must be fully enclosed in visually solid, compatible materials, unless the City finds enclosure infeasible for manufacturer or safety reasons. Noise study and operating limit
Building facades must be non-reflective unless the City determines reflection will have no adverse impact. Any proposed windows must use forced-entry-resistant and fire-resistant glass. Facade and window requirements
The data-center premises must have adequate security measures. If perimeter fencing is used, it cannot be chain-link or include barbed wire or similar intruder-deterrence features. If the center has a primary or secondary diesel or gas generator, the applicant must consult appropriate governmental agencies and develop on-site fuel delivery, handling, and storage safety protocols. Security and generator-fuel requirements
Other PUD standards include a 35-foot building-height limit unless a different height is indicated and approved in the development plan, and a limit of 50% of a lot’s area for a building’s ground-level floor coverage. Commercial and industrial uses are also subject to an 80% maximum lot coverage for buildings, parking, and traffic circulation. PUD height and coverage limits
PUDs generally must preserve at least 20% of gross site area as common green space and provide sidewalks or other pedestrian circulation. Those two requirements do not apply when the primary and sole use of the parcel is a data center; they may apply to other data-center developments. Data-center exception to green-space and sidewalk rules
PUD operating standards also prohibit smoke emissions from industrial or commercial processes and odorous gases or matter detectable at or beyond the PUD boundary. PUD smoke and odor standards
Benefits & exceptionsHide benefits & exceptions7
Data centers are expressly permitted uses in a PUD; a data center as a primary use is permitted only in the PUD District. “Data centers”
A PUD application for less than the normally required 40 acres may be accepted when the data center is the tract’s only proposed use; acceptance is not guaranteed. “only proposed use”
For a parcel used solely and primarily as a data center, the PUD requirement for 20% common green space and the PUD sidewalk requirements do not apply. “shall not apply”
PUD review combines zoning review with some subdivision review, and approval of the PUD development plan also approves the preliminary subdivision plan. “combined review”
The Planning Commission may recommend, and Council may approve, deviations from City development and subdivision regulations through the PUD approval process, without a separate Board of Zoning Appeals variance or waiver. Approval requires the specified findings, including no negative impact on public safety, infrastructure function, or long-term maintenance. “A separate variance or waiver”
Screening of data-center equipment or facilities may be modified or waived if the Building and Zoning Inspection chief determines they have no adverse impact on adjacent properties or the public. “may be modified or waived”
Where the required sound study applies, the operating sound limit is the greater of 55 decibels at the lot line or the measured average baseline level at a lot line. This can allow a higher limit where baseline sound is above 55 decibels; the study is required when the property shares a lot line with a noise-sensitive or specified adjacent use. “the greater of”