Loading map…

City of Forest Park

Mixed Data Center Policies

Ohio offers qualifying data centers significant sales-tax exemptions on equipment, subject to investment, payroll, reporting, and other conditions, while fees apply to participants. New exemption requests are paused, which may raise costs for new projects; data centers are not banned.

Rating and summary from Ohio statewide as there are no scored current or future laws outside temporary restrictions for City of Forest Park.

expired · City of Forest Park
Prohibits Forest Park from reviewing applications or issuing new zoning certificates for data centers for 180 days, unless the moratorium is ended or extended by City Council.Forest Park Resolution No. 07-2026

What this means

The measure would pause review of new data-center applications and issuance of new zoning certificates for 180 days, delaying new projects and any expansions that require a new certificate (pause on new applications and certificates). Existing valid certificates would remain in effect, so already-approved centers could continue operating; the temporary moratorium is still a substantial barrier to new development.

Timing

Ends
180 days following the effective date

The Council may terminate or extend the moratorium. The moratorium will automatically expire unless the Council does so.

People behind it

  • Adopted the resolution and may terminate or extend the moratorium; identified as a body that will gather information and develop regulations.

  • Identified as responsible for gathering information and helping develop regulations during the moratorium.

Restrictions & requirementsHide restrictions & requirements1
  • For 180 days after the resolution takes effect, the City may not review applications or issue new zoning certificates of compliance for data centers. Existing valid certificates are unaffected, and Council may terminate or extend the moratorium. The moratorium will automatically expire 180 days following the effective date.

Benefits & exceptionsHide benefits & exceptions1
  • Previously issued valid data-center zoning certificates remain valid during the moratorium, allowing those facilities to continue operating; this protection applies only to certificates issued before the resolution’s effective date. Valid certificates remain valid

Sources

Cookie preferences · Report missing data