Strongly Pro-Data Center Policies

Summit County’s enacted agreement provides public funding and a site for a large data center for the city to operate, benefiting this project specifically without broadly easing development for others.

Rating and summary from Summit County as there are no scored current or future laws outside temporary restrictions for City of Fairlawn.

pending · City of Fairlawn
Authorizes the mayor to sign a nonbinding agreement for Summit County and Fairlawn to develop a modular data center on city-owned land and set out how it would be funded, owned, and leased.Fairlawn Ordinance 2024-034A (2024) — Term Sheet for Countywide Broadband Fiber Ring and Related Data Center

What this means

The proposal supports building and operating a modular data center, with public funding and long-term leases, but it is a specific public project rather than a broad incentive for data center development. The term sheet is non-binding until definitive agreements, so the practical benefit is meaningful but limited.

People behind it

  • Sponsor of Ordinance 2024-034A, which authorizes execution of the broadband project term sheet.

  • A term-sheet party responsible for undertaking construction of the fiber ring and acquiring and installing the data center.

  • A term-sheet party that will sublease and operate the fiber ring and data center, and form a broadband utility.

Show 2 more peopleShow fewer people
  • A term-sheet party responsible for providing project funding and plans and materials for the fiber ring, and leasing the fiber ring and data center.

  • A term-sheet party that will provide land for the data center and participate in project coordination and related agreements.

Restrictions & requirementsHide restrictions & requirements9
  • The proposed data center is limited to a modular facility on City-owned land near 3300 Fairlawn Service Drive. a modular data center located on City-owned land

  • The Authority would acquire and install the facility under specifications mutually agreed by the Cooperative Parties, adding a multi-party agreement step to procurement. specifications mutually agreed to by the Cooperative Parties

  • The County must determine how to finance the data center before the Cooperative Agreement is executed, and enter any additional agreements needed for that financing. prior to execution of the Cooperative Agreement

  • The proposed ownership and operating arrangement runs through the Authority, County, and COG: the Authority owns the facility, leases it to the County, and the County subleases it to the COG, which then sub-subleases space to the City and County. owned by the Authority and leased to the County

  • The lease structure requires payment of base rent tied to annual debt service, plus additional rent covering management, operation, maintenance, repairs, and related fees and costs. annual debt service, both principal and interest

  • The County must maintain property and casualty insurance and general liability insurance, name the Authority as an additional insured, and procure any other coverage the parties determine is necessary. naming the Authority as an additional insured

  • The proposed master lease lasts 20 years; the County may purchase the data center after the fifth anniversary, but must purchase it at the end of the term. The COG’s purchase option is available at the end of its 20-year sublease or when financing debt service is fully paid, and only after the County acquires the facility. at any time after the 5th anniversary

  • The proposed land lease is for 20 years, with a $1 annual rent; it extends to 99 years if the COG purchases the data center at the end of the sublease. a term of 20 years

  • The term sheet is non-binding until its terms are incorporated into definitive agreements and those agreements are approved by each Cooperative Party’s board or legislative authority. duly approved by the board or legislative authority

Benefits & exceptionsHide benefits & exceptions5
  • The Authority is to acquire and install a modular data center, with the County intending to finance those costs. The County must determine the financing method before the Cooperative Agreement; the proposed lease rent would reflect the resulting annual debt service. These are nonbinding plans until definitive agreements are approved and executed. acquisition and installation of a modular data center

  • The City would lease the Authority enough City-owned land near 3300 Fairlawn Service Drive for the data center for $1 per year for 20 years. If the COG later purchases the data center, the land lease would extend to 99 years and could be assigned to the COG. annual rental payment of $1.00

  • The proposed lease chain would have the Authority lease the data center to the County and the County sublease it to the COG. The County, then the COG, would be responsible for operating, maintaining, and repairing it; sub-sublease rents from the City and County would collectively cover base rent and operating costs. responsible for operating, maintaining and repairing the Data Center

  • The COG could sub-sublease data-center space not needed by the City or County to other entities, on terms agreed with those entities. space within the Data Center that is not needed

  • The County could choose to buy the data center after the fifth anniversary of the master lease, provided it takes appropriate steps to remain responsible for the financing debt service; it would have to buy the data center at the end of the 20-year lease. After the County acquires it, the COG could buy it for $1 at the end of its 20-year sublease or once the financing debt is fully paid. after the 5th anniversary