City of Fairborn

This restriction takes precedence while in effect. The rating below excludes temporary restrictions.

Mixed Data Center Policies

Fairborn enacted a pause on approvals for new data centers for 12 months, extendable by up to six months, while it studies zoning rules. Existing operations do not appear to be covered.

Rating from Ohio statewide as there are no scored current or future laws outside temporary restrictions for City of Fairborn.

current law · City of Fairborn
Pauses approval of data center development in Fairborn for 12 months, with a possible extension of up to six months.City of Fairborn Resolution 38-26 (2026)

What this means

The measure would pause approvals for new data centers for 12 months, with an extension of up to six more months, while the city studies possible zoning rules (a 12-month pause). That could substantially delay or block new projects during that period, though it does not appear to ban existing data center operations.

Timing

Ends
12 months after adoption

The moratoriums are temporary and may be extended for up to six additional months. They may also end earlier if permanent regulations are adopted sooner.

People behind it

  • City Planner who presented Resolution 38-26 and conveyed staff’s recommendation for approval.

Restrictions & requirementsHide restrictions & requirements1
  • Approval of data centers is subject to a temporary moratorium for 12 months, with an authorized extension of up to six additional months (temporary moratoriums ... 12 months ... six additional months).

Sources

expired · City of Fairborn
Temporarily halts approvals for data centers in Fairborn, including under a 12-month moratorium adopted in 2026 and an earlier 180-day moratorium in 2022.Fairborn Ordinance 25-22 (2022)

What this means

The city’s 12-month temporary moratorium would temporarily make it much harder to build or expand data centers by pausing approvals. The source also lists an earlier 180-day moratorium, but neither measure is a permanent ban.

People behind it

  • Adopted Resolution 38-26, which established temporary moratoria.

  • Issued Ordinance 25-22, imposing a temporary data center moratorium.

Restrictions & requirementsHide restrictions & requirements1
  • Tracker describes a temporary moratorium on permits, certificates and approvals for data-center operation or property use. Original text not verified.